Define Activities is the process ofidentifying the specific actions to be performed toproduce the()A、projectelementsB、work draftsC、workpackageD、projectdeliverables

题目

Define Activities is the process ofidentifying the specific actions to be performed toproduce the()

  • A、projectelements
  • B、work drafts
  • C、workpackage
  • D、projectdeliverables

相似考题
参考答案和解析
正确答案:D
更多“Define Activities is the process ofidentifying the specific actions to be performed toproduce the()A、projectelementsB、work draftsC、workpackageD、projectdeliverables”相关问题
  • 第1题:

    68 The Cost Performance Index (CPI) measures:

    A. cost of work performed vs planned costs.

    B. work performed vs cost of work performed.

    C. work performed vs planned work.

    D. direct costs vs indirect costs.

    E. floating costs vs. sunk costs.


    正确答案:B

  • 第2题:

    ● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.

    (74)

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    试题(74)分析
        项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。
    参考答案
        (74)A

  • 第3题:

    ● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).

    (71)

    A. project elements

    B. work drafts

    C. work package

    D. project deliverables


    正确答案:D

  • 第4题:

    Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

    A.Develop Schedule

    B.Estimate Activity Resources

    C.Define Activities

    D.Sequence Activities


    正确答案:A
    解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

  • 第5题:

    The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B

  • 第6题:

    The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B
    解析:项目范围说明书是制订质量计划的—项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

  • 第7题:

    The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).

    A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index


    正确答案:A

  • 第8题:

    In project time management,activity definition is the process of identifying and documenting the specification to be performed to produce the project deliverables.( )are not output of activity definition.

    A.Activity list
    B.Work Break down Structures
    C.Activity Attributes
    D.Mile stone Lists

    答案:B
    解析:
    翻译:在项目管理中,活动定义是识别和记录项目可交付物而采取的具体行动的过程。( )不是活动定义的输出。A.活动清单 B.工作分解结构 C.活动属性 D.里程碑清单

  • 第9题:

    Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.

    A.Developing project charter
    B.Developing project management plan
    C.Analyzing project risks
    D.Monitoring and controlling project

    答案:C
    解析:
    项目整合管理包括在项目管理过程组中识别、定义、组合、统一和协调各种过程和项目管理活动的过程和活动。识别项目风险过程不属于项目整合管理。
    A制定项目章程,B制定项目管理计划,C识别项目风险,D指导与管理项目。

  • 第10题:

    The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

    • A、work performance information
    • B、scope statement
    • C、changerequests
    • D、process analysis

    正确答案:B

  • 第11题:

    单选题
    Define Activities is the process ofidentifying the specific actions to be performed toproduce the()
    A

    projectelements

    B

    work drafts

    C

    workpackage

    D

    projectdeliverables


    正确答案: D
    解析: 该题的关键词为"Define Activities、identifying the specific actions",其语句结构为"Define Activities(主语)is(谓语)the process ofidentifying the specific actions to beperformed to produce the_ ",含义为"活动定义是为了生成什么而执行所识别出的特定活动",这是考察进度管理知识领域中的活动定义的概念,活动定义是为了生成交付物或子交付物而执行的活动,因此选择选项D。

  • 第12题:

    多选题
    Identify the activities performed as part of the Automatic SQL Tuning process in the maintenance window?()
    A

    generating the SQL profile

    B

    testing and accepting the SQL profile

    C

    generating a list of candidate SQLs for tuning

    D

    adding tuned SQL plans into the SQL plan baseline

    E

    tuning each SQL statement in the order of importance

    F

    generating baselines that include candidate SQLs for tuning


    正确答案: B,A
    解析: 暂无解析

  • 第13题:

    ● Scope Management:

    A entails managing the project's work content.

    B is a subset of configuration management and as such is performed by CM specialists.

    C is concerned with naming all activities performed, the end products which results and the resources consumed.

    D is not a concern of the project manager.

    E None of the above.


    正确答案:C

  • 第14题:

    Define Activities is the process of identifying the specific actions to be performed to produce the (71).

    A.project elements

    B.work drafts

    C.work package

    D.project deliverables


    正确答案:D
    解析:活动定义过程识别是为了生产项目的可交付物而必须执行的具体活动。

  • 第15题:

    ● In order to achieve the major goals of business process improvement, process simplification and improvement, FAA managers need to fully understand the cost, time, and quality of activities performed by employees or machines throughout an entire organization. ABC methods enable () to cost out measurements to business simplification and process improvement. () A. computers B. managers C. clients D. consumers


    正确答案:B
        为了达到业务流程改进、过程简化和改进的主要目的,FAA经理们需要充分理解那些由员工或机器执行的、贯穿整个组织的活动的成本、时间和质量。ABC法能让经理们估算出度量业务简化和过程改进的成本。

  • 第16题:

    ● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)

    (75)

    A. Project Scope Statement

    B. Project Management Plan

    C. Forecasts

    D. Project Charter


    正确答案:B

    试题(75)分析
      项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到    (75) 。
      A.项目范围说明书                    B.项目管理计划
      C.项目预测                          D.项目章程
    参考答案
      (75)B

  • 第17题:

    The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter


    正确答案:B
    制定项目管理计划过程定义、准备、集成和协调所有的分计划,以形成项目管理计划 。

  • 第18题:

    The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).

    A.Project Scope Statement

    B.Project Management Plan

    C.Forecasts

    D.Project Charter


    正确答案:B

  • 第19题:

    In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.

    A.Activity list

    B.Work Breakdown Structures

    C.Activity Attributes

    D.Milestone Lists


    正确答案:B

  • 第20题:

    The Develop Project Management Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ( )

    A. Project Scope Statement
    B.Project Management Plan
    C.Forecasts
    D.Project Charter

    答案:B
    解析:
    项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到(75)。

    A. 项目范围说明书 B. 项目管理计划

    C. 项目预测 D. 项目章程

  • 第21题:

    Define Activities is the process of identifying the specific actions to be performed to produce the ( ) .

    A.project elements
    B.work drafts
    C.work package
    D.project deliverables

    答案:D
    解析:

  • 第22题:

    Identify the activities performed as part of the Automatic SQL Tuning process in the maintenance window?()

    • A、generating the SQL profile
    • B、testing and accepting the SQL profile
    • C、generating a list of candidate SQLs for tuning
    • D、adding tuned SQL plans into the SQL plan baseline
    • E、tuning each SQL statement in the order of importance
    • F、generating baselines that include candidate SQLs for tuning

    正确答案:A,B,C,E

  • 第23题:

    单选题
    The master shall ensure that any seafarers()are provided with an adequate period of rest.
    A

    who have performed work for 14 hours

    B

    who have performed work in a scheduled rest period

    C

    who have performed work in a scheduled work period

    D

    who works hard


    正确答案: C
    解析: 暂无解析