( )can be considered as part of risk mitigation. A、Risk identificationB、Purchasing insuranceC、Assessment of outcomesD、Assessment of probabilities

题目

( )can be considered as part of risk mitigation.

  • A、Risk identification
  • B、Purchasing insurance
  • C、Assessment of outcomes
  • D、Assessment of probabilities

相似考题
参考答案和解析
正确答案:D
更多“( )can be considered as part of risk mitigation. A、Risk identificationB、Purchasing insuranceC、Assessment of outcomesD、Assessment of probabilities”相关问题
  • 第1题:

    Giving a part of project work to a contractor is an example of:

    A risk mitigation

    B risk assignment

    C risk delegation

    D risk deflection

    E risk assumption


    正确答案:D

  • 第2题:

    It is useful to conduct project risk assessment according to the project's

    A charter

    B statement of work

    C Work Breakdown structure

    D network

    E budget


    正确答案:C

  • 第3题:

    184 Which of the following activities can be considered as part of risk mitigation

    A. risk identification

    B. purchasing insurance

    C. assessment of outcomes

    D. assessment of probabilities

    E. C and D only


    正确答案:B

  • 第4题:

    178 "Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .

    A. be completed in reduced overall time than other projects.

    B. be in a higher risk category than other projects.

    C. not be compatible with project risk and assessment

    D. A and B

    E. All of the above


    正确答案:D

  • 第5题:

    The most crucial time for project risk assessment is (75) .A.when a problem surfacesSXB

    The most crucial time for project risk assessment is (75) .

    A.when a problem surfaces

    B.during the planning phase

    C.during the close-out phase

    D.after the project schedule has been published


    正确答案:A
    项目风险评估最重要的时间是:当问题呈现时在规划阶段在收尾阶段在项目进度发布后

  • 第6题:

    The most crucial time for project risk assessment is ( ).

    A.when a problem surfaces

    B.during the planning phase

    C.during the close-out phase

    D.after the project schedule has been published


    正确答案:B

  • 第7题:

    The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:B
    解析:定量风险分析过程分析风险事件的影响并对这些风险赋予一个数值化的评价。

  • 第8题:

    ( )is not included in Information Security Risk Assessment Process.

    A.Establishing information security risk criteria
    B.Identifying the information security risks
    C.Formulating an information security risk treatment plan
    D.Analysing the information security risk

    答案:A
    解析:
    信息安全风险评估过程不包括建立信息安全风险准则。

  • 第9题:

    The most crucial time for project risk assessment is ( ).

    • A、when a problem surfaces
    • B、during the planning phase
    • C、during the close-out phase
    • D、after the project schedule has been published

    正确答案:B

  • 第10题:

    健康危险度评价(health risk assessment)


    正确答案:是按一定的准则,对有害环境因素作用于特定人群的有害健康效应进行综合定性,定量评价的过程

  • 第11题:

    名词解释题
    健康危险度评价(health risk assessment)

    正确答案: 是按一定的准则,对有害环境因素作用于特定人群的有害健康效应进行综合定性,定量评价的过程
    解析: 暂无解析

  • 第12题:

    多选题
    风险评估(Risk assessment)包括哪几个过程?()
    A

    风险识别

    B

    风险分析

    C

    人群脆弱性分析

    D

    风险评价

    E

    风险沟通


    正确答案: A,E
    解析: 暂无解析

  • 第13题:

    Which of the following activities can be considered as part of risk mitigation

    A risk identification

    B purchasing insurance

    C assessment of outcomes

    D assessment of probabilities

    E C and D only


    正确答案:B

  • 第14题:

    111 It is useful to conduct project risk assessment according to the project's

    A. charter

    B. statement of work

    C. Work Breakdown structure

    D. network

    E. budget


    正确答案:C

  • 第15题:

    15 Total project risk can be defined as:

    A. the sum of the probabilities of project risks events times the sum of consequences of those risks

    B. the sum of the products of each project risk event times its consequences

    C. the sum of the consequences of all project risk events

    D. the sum of the probabilities of all project risk events

    E. 1 - the sum of the probabilities of all project risk events


    正确答案:B

  • 第16题:

    听力原文:Although it is a normal part of banking, excessive interest rate risk can pose a significant threat to a bank's earnings and capital base.

    (4)

    A.Interest rate risk is a normal part of banking operations.

    B.Interest rate risk is a terrible threat to banking operations.

    C.A bank's earnings and capital base is a normal part of banking.

    D.A bank's earnings and capital base can pose a significant threat to banking.


    正确答案:A
    解析:单句意思为“尽管利率风险是银行业常见的风险,但它可以对银行收入和资本基础造成严重威胁”。只有A项意思正确。

  • 第17题:

    Workarounds are determined during which risk management process? (75).

    A. Risk identification

    B. Quantitative risk analysis

    C. Plan risk responses

    D. Risk monitoring and control


    正确答案:D
    权变措施是在风险管理过程中的(75)过程确定的?。A.风险识别B.风险定量分析C.规划风险应对D.风险监测和控制

  • 第18题:

    The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.

    A.Risk Identification

    B.Quantitative Risk Analysis

    C.Qualitative Risk Analysis

    D.Risk Monitoring and Control


    正确答案:A
    解析:项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。选项A是风险识别,选项B是定量风险分析,选项C是定性风险分析,选项D是风险监控。

  • 第19题:

    () can be considered as part of risk mitigation.

    A.Risk identification
    B.Purchasing insurance
    C.Assessment of outcomes
    D.Assessment of probabilities

    答案:D
    解析:
    ()可以被认为是风险缓解的一部分。A、风险识别B、购买保险C、成果评估D、概率评估注意题干中:as part of.

  • 第20题:

    The most crucial time for project risk assessment is ( ) .

    A.when a problem surfaces
    B.during the planning phase
    C.during the close-out phase
    D.after the project schedule has been published

    答案:B
    解析:
    进行项目风险评估最关键的时候是规划阶段。A.问题出现时 B.规划阶段 C.结束阶段 D.项目进度公布后

  • 第21题:

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

    • A、Risk Identification
    • B、Quantitative Risk Analysis
    • C、Qualitative Risk Analysis
    • D、Risk Monitoring and Control

    正确答案:B

  • 第22题:

    风险评估(Risk assessment)包括哪几个过程?()

    • A、风险识别
    • B、风险分析
    • C、人群脆弱性分析
    • D、风险评价
    • E、风险沟通

    正确答案:A,B,D

  • 第23题:

    名词解释题
    危险度评定(risk assessment)

    正确答案: 是指特定的靶机体、系统或(亚)人群暴露于某一危害,考虑到有关因素固有特征和特定靶系统的特征,计算或估计预期的危险的过程,包括评定伴随的不确定性。
    解析: 暂无解析