  • 第1题:

    ● Organizations perform. work to achieve a set of objectives. Generally,work can be categorized as either projects or operations, although the twosometimes are (67) .

    A.confused

    B.same

    C.overlap

    D.dissever


    正确答案:C

  • 第2题:

    A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.

    A.phases

    B.processes

    C.segments

    D.pieces


    正确答案:A

  • 第3题:

    In which situations computers do not perform. better than the human mind?

    A、performing an operation

    B、docking a big ship

    C、playing backgammon

    D、doing the work of a postal clerk


    参考答案:ABD

  • 第4题:

    Before sending your resume to prospective employers

    or scheduling any interviews , you need to analyze the job market. Analyzing the job market involves determining actual job

    openings and gathering information about organizations for which you want to work.


    参考答案:在给目标雇主发简历或接受面试之前,你需要分析工作市场。分析工作市场需要你锁定实际的职位空缺,收集你想进入的机构的信息。

  • 第5题:

    To achieve success in your career, the most important factor, according to the passage, is to ______.

    A) work as a consultant to your superiors

    B) project a favorable image to the people around you

    C) let your superiors know how good you are

    D) perform. well your tasks given by your superiors


    正确答案:C
    答案:C
    [试题分析] 细节题。
    [详细解答] 意为:“让上司知道你的工作干得是多么好”。这实际上是克里蒙的观点。在第二段,作者引用了克里蒙的观点,在他看来,人的成功百分之六十靠的是表现自己 (exposure),他认为,能做好工作的人在今天司空见惯,虽然做好工作可能提高工资,但是却不一定能带来实质性的晋升,晋升更多地取决于:有多少人了解你,了解你的工作,了解你的人在公司里地位的高低(how high up they are)。

  • 第6题:

    A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project.
    The life cycle provides the basic for managing the project, regardless of the specific work involved.

    A.phases
    B.processes
    C.segments
    D. pieces

    答案:A
    解析:
    一个项目的生命周期由若干个顺序相连的(73)组成,阶段的名字和个数由组织的控制需要决定。项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的。
    (73)A. 阶段 B. 过程 C. 片段 D. 碎片

  • 第7题:

    A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved. 空白(2)处应选择()

    • A、plan
    • B、fraction
    • C、main
    • D、framework

    正确答案:D

  • 第8题:

    A work order has been created to perform corrective maintenance on a defective generator. All required information has been provided in the work order, but required materials are not in stock and  have to be ordered.  What is the status of the work order, after a maintenance manager has approved the work order? ()

    • A、 Approved (APPR)
    • B、 Waiting on Materials (WMATL)
    • C、 Waiting to be Scheduled (WSCH)
    • D、 Waiting on Plant Condition (WPCOND)

    正确答案:B

  • 第9题:

    You work as a database administrator at Certkiller .com. You are working in an online transaction processing (OLTP) environment. You realize that the salary for an employee, John, has been accidentally modified in the EMPLOYEEStable. Two days ago, the data was in the correct state. Flashback logs generated during last two days are available in the flash recovery area. Which option would you choose to bring the data to the correct state while ensuring that no other data in the same table is affected?()

    • A、 perform point-in-time recovery
    • B、 perform a Flashback Table operation to restore the table to the state it was in two days ago
    • C、 perform a Flashback Database operation to restore the database to the state it was in two days ago
    • D、 perform Flashback Versions Query and Flashback Transaction Query to determine all the necessary undo SQL statements, and then use them for recovery

    正确答案:D

  • 第10题:

    单选题
    Which organizations can post to the same set of books?()
    A

    those organizations that share the same functional currency, calendar and accounting flexfield structure

    B

    those organizations that share the same currency but do not share the same calendar and accounting flexfield structure

    C

    those organizations that share the same accounting flexfield structure but do not share the same calendar and functional currency

    D

    those organizations that share the same calendar but do not share the same functional currency and accounting flexfield structure


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    What does the author mean by saying “tighten their belts” (Line 4, Para 1)?
    A

    Many organizations plan to reduce the book and magazine budgets.

    B

    Many organizations plan to reduce the unnecessary expenditures.

    C

    Many organizations encounter management crisis.

    D

    Many bosses want to cut their belts short.


    正确答案: B
    解析:
    第一段倒数第二句指出“In an effort to tighten their belts many organizations have decided to reduce the book and magazine budgets…”(许多组织已经决定减少……书和杂志的预算),由此可知该短语的意思是“节省开支”,对应选项B(许多组织计划减少不必要的开支)。

  • 第12题:

    单选题
    You work as a database administrator for Certkiller .com. Your database is in NOARCHIVELOG mode and you want to perform a backup. Which type of backup would be appropriate in this case? ()
    A

    Hot backup

    B

    Online backup

    C

    consistent backup

    D

    incremental backup

    E

    inconsistent backup


    正确答案: D
    解析: 暂无解析

  • 第13题:

    ● A project life cycle is a collection of generally sequential project (73)whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74)for managing the project, regardless of the specific work involved.

    (73)

    A. phases

    B. processes

    C. segments

    D. pieces

    (74)

    A. plan

    B. fraction

    C. main

    D. framework


    正确答案:A,D

  • 第14题:

    根据材料回答3~4题: A project life cycle is a collection of generally sequential project(73)whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic(74)for managing the project,regardless ofthe specific work involve D. A.phases B.processes C.segments D.pieces


    正确答案:A

  • 第15题:

    PPHC and Gooseneck are two organizations that do similar community work. Each has hired a new staff member to make contact with and provide services to new parents.

    Elaine has accepted a job with PPHC. She has a degree in psychology but has never done this type of work before. On her first day, after showing her to her desk and introducing her to colleagues, the director gives her a town map and a list of the names of the families she will be responsible for, and wishes her luck. After lunch, Elaine sets out to contact the families, worried about what she'll do or say when she meets them.

    Mark has a degree similar to Elaine's, and has just been hired by Gooseneck. On his first day, he learns that his job will consist of training for the next week. Mark spends two days going on family visits with experienced staff members, and discusses with them what they did and why. He role-plays some situations with other staff members, and gets some direct instruction from them. By the following week, when he's on his own, he feels he has a pretty good idea of what he needs to do, and how to go about it. And he knows that his training will continue.

    Which situation would you rather be in, being thrown into the thick of things with no training or being trained to prepare for the work you're going to do?

    21. What are PPHC and Gooseneck?

    A. They are two companies that do similar business.

    B. They are two organizations that do different community work.

    C. They are two organizations that do similar community work.

    22. Which degree does Elaine have?

    A. Psychology degree.

    B. Physiology degree.

    C. Sociology degree.

    23. Which of the following statements is true according to the passage?

    A. Elaine has done this type of community work so her organization doesn't provide staff training.

    B. Mark has a clear idea of his job after the training.

    C. Mark knows his training comes to an end.

    24. How is Mark trained to be prepared for his work?

    A. Mark spends two days on family visits with experienced staff members and discuss with them.

    B. Mark role-plays some situations with other staff members and gets some direct instruction from them.

    C.Both A and B.

    25. What is the main idea of the passage?

    A. The importance of training.

    B. Different training ways.

    C. Elaine's and Mark's work experience.


    参考答案:21-25:CBBCA


  • 第16题:

    Which organizations can post to the same set of books?()

    A.those organizations that share the same functional currency, calendar and accounting flexfield structure

    B.those organizations that share the same currency but do not share the same calendar and accounting flexfield structure

    C.those organizations that share the same accounting flexfield structure but do not share the same calendar and functional currency

    D.those organizations that share the same calendar but do not share the same functional currency and accounting flexfield structure


    参考答案:A

  • 第17题:

    Organizations perform. work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are(67).

    A.confused

    B.same

    C.overlap

    D.dissever


    正确答案:C
    解析:组织执行工作以达成一组目标。通常,工作可被分为项目或是运营,虽然两者在某些时候会有所重叠。

  • 第18题:

    A project life cycle is a collection of generally sequential project whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic () for managing the project, regardless of the specific work involved.

    A. plan
    B. fraction
    C. main
    D.framework

    答案:D
    解析:
    一个项目的生命周期由若干个顺序相连的阶段组成,阶段的名字和个数由组织的控制需要决定。项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的()

  • 第19题:

    Which of the following access levels allows a user to perform normal day to day work with their own files but does not allow them to change system files or computer performance?()

    • A、Administrator
    • B、User
    • C、Guest
    • D、Power user

    正确答案:B

  • 第20题:

    You work as a database administrator for Certkiller .com. Your database is in NOARCHIVELOG mode and you want to perform a backup. Which type of backup would be appropriate in this case? ()

    • A、Hot backup
    • B、Online backup
    • C、consistent backup
    • D、incremental backup
    • E、inconsistent backup

    正确答案:C

  • 第21题:

    单选题
    A work order has been created to perform corrective maintenance on a defective generator. All required information has been provided in the work order, but required materials are not in stock and  have to be ordered.  What is the status of the work order, after a maintenance manager has approved the work order? ()
    A

     Approved (APPR)

    B

     Waiting on Materials (WMATL)

    C

     Waiting to be Scheduled (WSCH)

    D

     Waiting on Plant Condition (WPCOND)


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
    A

    confused

    B

    same

    C

    overlap

    D

    dissever


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    You work as a database administrator at Certkiller .com. You are working in an online transaction processing (OLTP) environment. You realize that the salary for an employee, John, has been accidentally modified in the EMPLOYEEStable. Two days ago, the data was in the correct state. Flashback logs generated during last two days are available in the flash recovery area. Which option would you choose to bring the data to the correct state while ensuring that no other data in the same table is affected?()
    A

     perform point-in-time recovery

    B

     perform a Flashback Table operation to restore the table to the state it was in two days ago

    C

     perform a Flashback Database operation to restore the database to the state it was in two days ago

    D

     perform Flashback Versions Query and Flashback Transaction Query to determine all the necessary undo SQL statements, and then use them for recovery


    正确答案: C
    解析: 暂无解析