An administrator is planning to bring a newly purchased server online. Which of the following should the administrator do FIRST?()A、Follow the pre-installation plan and procedures.B、Review the system logs to check for errors.C、Notify all users that the ol

题目

An administrator is planning to bring a newly purchased server online. Which of the following should the administrator do FIRST?()

  • A、Follow the pre-installation plan and procedures.
  • B、Review the system logs to check for errors.
  • C、Notify all users that the old system will be taken offline.
  • D、Apply all security updates to the system.

相似考题
更多“An administrator is planning to ”相关问题
  • 第1题:

    123 Which of the following constitute Juran's "quality trilogy":

    A. planning, inspection, control.

    B. planning, improvement, control.

    C. planning, organization, control.

    D. product, price, customer.

    E. design, build, deliver.


    正确答案:B

  • 第2题:

    MRPII指的是:()

    A.material requirement planning。

    B.management requirement planning。

    C.manufacturing resource planning。

    D.material revenue planning。

    E.Material risk planning。


    正确答案:C

  • 第3题:

    ideally, lesson planning should be done at two levels: _______________.

    A. before-class planning and after-class planning

    B. before-class preparation and after-class feedback

    C. before-class planning and after-class reflection

    D. macro planning and micro planning


    正确答案是:D

  • 第4题:

    A network administrator is planning a network installation for a large organization.The design requires 100 separate subnetworks,so the company has acquired a Class B network address.What subnet mask will provide the 100 subnetworks required, if 500 usable host addresses are required per subnet?()

    • A、255.255.240.0
    • B、255.255.248.0
    • C、255.255.252.0
    • D、255.255.254.0
    • E、255.255.255.0
    • F、255.255.255.192

    正确答案:D

  • 第5题:

    You are planning a new VLAN-based network solution.  What is one item you should consider when creating your implementation plan as it concerns VLANs?()

    • A、generic router and switch configuration parameters
    • B、end-to-end test plan after all components have been installed and  configured
    • C、administrator assignments
    • D、rollback plan

    正确答案:D

  • 第6题:

    An administrator is planning an upgrade of a major software package on an application server.The software has been identified, the project approved and the upgrade purchased. Which of the following steps should the administrator take NEXT?()

    • A、Create a test environment for the new version.
    • B、Determine system requirements for the upgrade.
    • C、Request bids from other competing vendors in the product space.
    • D、Document the upgrade.

    正确答案:A

  • 第7题:

    An administrator wants to deploy a complex LPARenvironment on a 595. What is the most current tool available for documenting the proposed LPAR configuration and determining if there are adequate IO resources?()

    • A、LPAR Planning Tool.
    • B、System Planning Tool.
    • C、LPAR Validation Tool.
    • D、System Validation Tool.

    正确答案:B

  • 第8题:

    An administrator is planning for a six node cluster but is concerned about the administration needed tomanage user accounts throughout the cluster. What PowerHA feature could the administrator use to reducethe administration overhead?()

    • A、LDAP Authentication Module
    • B、Smart Assist for Active Directory
    • C、C-SPOC for user and password management
    • D、File Collections designating one node as the primary authentication node

    正确答案:C

  • 第9题:

    During an internal IT organization planning session, it is decided that a new cluster node would  Enhance the performance of a distributed corporate application. Planning details have been assigned to the administrator. System outages are limited to one weekend per month; therefore, availability will be a key issue in the planning process.  How much cluster downtime will need to be allocated for adding a new node?()  

    • A、 None,everything can be done with the cluster active.
    • B、 Minimal downtime will be required to import the volume groups.
    • C、 Several hours are required for testing before final synchronization.
    • D、 Minimal downtime will be required to connect and test the serial network.

    正确答案:A

  • 第10题:

    单选题
    An administrator has an existing HMC and POWER6 570 connected to a network switch.  The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
    A

    An additional switch for the new HMc  

    B

    Asynchronous adapters on the new HMc

    C

    The two 570 servers are directly connected to the new HMc  

    D

    One 570 is directly connected to the new HMC and the other is directly connected to the existing HMc


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    An administrator is planning an upgrade of a major software package on an application server. The software has been tested successfully in a test environment and it is ready to go into production.  Which of the following steps should the administrator take next?()
    A

     Identify necessary operating system updates

    B

     Implement the change

    C

     Document the change

    D

     Schedule system down time


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    An administrator wants to use the online planning worksheets as an aid to configuring a PowerHA cluster.Which PowerHA fileset would the administrator need to install in order to obtain this tool?()
    A

    cluster.es.haw

    B

    cluster.es.worksheets

    C

    cluster.es.tools.worksheets

    D

    cluster.es.server.worksheets


    正确答案: D
    解析: 暂无解析

  • 第13题:

    116 Planning activities such that predetermined resource availability pools are not exceeded is called: A. Resource leveling.

    B. Manpower leveling.

    C. Resource limited planning.

    D. Manpower planning.

    E. Manpower contingency planning.


    正确答案:C

  • 第14题:

    Lesson planning should be done at two levels: _____.

    A.macro planning and micro planning

    B.day by day and one week


    参考答案:A

  • 第15题:

    The project life-cycle can be described as().

    A.project concept, project planning, project execution, and project close-out
    B.project planning, work authorization, and project reporting
    C.project planning, project control, project definition, WBS development, and project termination
    D.project concept, project execution, and project reporting

    答案:A
    解析:
    关于项目周期划分正确的是(72)。

    A. 启动、计划、执行、收尾

    B. 计划、授权、报告

    C. 计划、控制、方案设计、WBS的发展、终止

    D. 启动、执行、报告

  • 第16题:

    计划(Planning)


    正确答案:是为实现组织管理目标而对未来行动方案做出选择和安排的工作过程。

  • 第17题:

    ()is the management system to control the material consumed, reduce inventory in the manufacture company.

    • A、DRP (Distribution Resource Planning) 
    • B、LRP (Logistics Resource Planning)
    • C、MRP (Material Requirements Planning)
    • D、ERP (Enterprise Resource Planning)

    正确答案:C

  • 第18题:

    An administrator is planning an upgrade of a major software package on an application server.The software has been tested successfully in a test environment and it is ready to go into production. Which of the following steps should the administrator take next?()

    • A、Identify necessary operating system updates
    • B、Implement the change
    • C、Document the change
    • D、Schedule system down time

    正确答案:D

  • 第19题:

    An administrator wants to deploy a complex LPAR environment on a 595. What is the most current tool available for documenting the proposed LPAR configuration and determining if there are adequate IO resources?()

    • A、LPAR Planning Tool.
    • B、System Planning Tool.
    • C、LPAR Validation Tool.
    • D、System Validation Tool.

    正确答案:B

  • 第20题:

    An administrator wants to use the online planning worksheets as an aid to configuring a PowerHA cluster.Which PowerHA fileset would the administrator need to install in order to obtain this tool?()

    • A、cluster.es.haw
    • B、cluster.es.worksheets
    • C、cluster.es.tools.worksheets
    • D、cluster.es.server.worksheets

    正确答案:B

  • 第21题:

    单选题
    An administrator is planning to bring a newly purchased server online. Which of the following should the administrator do FIRST?()
    A

     Follow the pre-installation plan and procedures.按照预先安装计划和程序。

    B

     Review the system logs to check for errors.

    C

     Notify all users that the old system will be taken offline.

    D

     Apply all security updates to the system.


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    A network administrator is planning a network installation for a large organization.The design requires 100 separate subnetworks,so the company has acquired a Class B network address.What subnet mask will provide the 100 subnetworks required, if 500 usable host addresses are required per subnet?()
    A

    255.255.240.0

    B

    255.255.248.0

    C

    255.255.252.0

    D

    255.255.254.0

    E

    255.255.255.0

    F

    255.255.255.192


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
    A

    An additional switch for the new HMC

    B

    Asynchronous adapters on the new HMC

    C

    The two 570 servers are directly connected to the new HMC

    D

    One 570 is directly connected to the new HMC and the other is directly connected to the existing HMC


    正确答案: B
    解析: 暂无解析

  • 第24题:

    单选题
    During an internal IT organization planning session, it is decided that a new cluster node would  Enhance the performance of a distributed corporate application. Planning details have been assigned to the administrator. System outages are limited to one weekend per month; therefore, availability will be a key issue in the planning process.  How much cluster downtime will need to be allocated for adding a new node?()
    A

     None,everything can be done with the cluster active.

    B

     Minimal downtime will be required to import the volume groups.

    C

     Several hours are required for testing before final synchronization.

    D

     Minimal downtime will be required to connect and test the serial network.


    正确答案: C
    解析: 暂无解析