()is the process of obtaining the stakeholders’ formal acceptance of the completed project scopE. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificati

题目

()is the process of obtaining the stakeholders’ formal acceptance of the completed project scopE. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

  • A、Project acceptance
  • B、Scope verification
  • C、Scope definition
  • D、WBS Creation

相似考题
更多“()is the process of obtaining the stakeholders’ formal acceptance of the completed project scopE. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificatio”相关问题
  • 第1题:

    is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    A.Project acceptance

    B.Scope verification

    C.Scope definition

    D.WBS Creation


    正确答案:B
    解析:范围验证是指获取项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。

  • 第2题:

    The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

    A.work performance information

    B.scope statement

    C.change requests

    D.process analysis


    正确答案:B
    解析:项目范围说明书是制订质量计划的—项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

  • 第3题:

    The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A、project scope statement

    B、work package

    C、WBS

    D、project scope plan


    参考答案:C

  • 第4题:

    Validate Scope is the process of formalizing acceptance of completed().

    A.project deliverables

    B.WBS

    C.activities

    D.milestones


    正确答案:A

  • 第5题:

    ()describees,indetail,the project's deliverables and the work required to create those deliverables.


    A.Product scope description
    B.Project objectives
    C.Produce specification
    D.The project scope statement


    答案:D
    解析:
    项目范围说明书详细描述了项目的可交付物和提供这些可交付物必须要做的工作。

  • 第6题:

    () is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily.

    A.Project acceptance
    B.Scope verification
    C.Scope definition
    D.WBS Creation

    答案:B
    解析:
    范围验证是指获得项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。

  • 第7题:

    The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.

    A.project charter
    B.project scope goal
    C.project budget
    D.project scope statement

    答案:D
    解析:
    翻译:范围管理计划是团队如何准备项目范围说明文件,包括描述创建WBS,核实项目的可交付成果的完成,并为项目范围变更控制的要求。A.项目章程 B.项目范围目标C.项目预算 D.范围说明书

  • 第8题:

    The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

    • A、work performance information
    • B、scope statement
    • C、changerequests
    • D、process analysis

    正确答案:B

  • 第9题:

    () is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    • A、projectacceptance
    • B、scopeverification
    • C、scopedefinition
    • D、WBS Creation

    正确答案:B

  • 第10题:

    ()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    • A、Project acceptance
    • B、Scope verification
    • C、Scope definition
    • D、WBS Creation

    正确答案:B

  • 第11题:

    单选题
    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.
    A

    Product scope description

    B

    Project objectives

    C

    Stakeholder Analysis

    D

    The project scope statement


    正确答案: B
    解析: 参考答案:D

  • 第12题:

    单选题
    ()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
    A

    Project acceptance

    B

    Scope verification

    C

    Scope definition

    D

    WBS Creation


    正确答案: D
    解析: 范围验证是指获取项目干系人对已完成的项目范围的正式认可的过程。验证范围包括评审可交付物和工作成果,以确保这些工作都已按照范围定义中的要求完成。

  • 第13题:

    ______describes,in detail,the project's deliverables and the work required to create those deliverables.

    A.Product scope description

    B.Project objectives

    C.Stakeholder Analysis

    D.The project scope statement


    正确答案:D
    解析:项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。
    选项A是产品范围说明书,选项B是项目目标,选项C是干系人分析,选项D是项目范围说明书。故D是正确的。

  • 第14题:

    ()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。

    A、Validate scope

    B、Define scope

    C、Control scope

    D、Collect requirement


    正确答案:C

  • 第15题:

    is the process of obtaining the stakeholdrs' formal acceptance of the completed project Scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    A.Project acceptance

    B.Scope verification

    C.Scope definition

    D.WBS Creation


    正确答案:B
    解析:范围验证是指获取项目干系人对已完成的项目范围的正式认可的过程。验证范围包括评审可交付物和工作成果,以确保这些工作都已按照范围定义中的要求完成。

  • 第16题:

    The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

    A.project charter

    B.project scope goal

    C.project budget

    D.project scope statement


    正确答案:C

  • 第17题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第18题:

    The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A.Project scope statement
    B.Work package
    C.WBS
    D.Project scope plan

    答案:C
    解析:
    ()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
    A.项目范围说明书B.工作包C.WBS?D.项目范围计划

  • 第19题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A. Create scopE
    B. Project stakeholder management
    C. Project scope management
    D. Project cost management

    答案:C
    解析:

  • 第20题:

    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    • A、Product scope description
    • B、Project objectives
    • C、Stakeholder Analysis
    • D、The project scope statement

    正确答案:D

  • 第21题:

    The () describes, in detail, the project's deliverables and the work required to create those deliverables.

    • A、project scope statement
    • B、project requirement
    • C、project charter
    • D、product specification

    正确答案:A

  • 第22题:

    单选题
    () is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
    A

    projectacceptance

    B

    scopeverification

    C

    scopedefinition

    D

    WBS Creation


    正确答案: A
    解析: 该题的关键词为"obtaining the stakeholders' formal acceptance、 verifying the scope",其语句结构为" (主语)1S(谓语)the process of obtaining the stakeholders' formal acceptance ofthe completed project scope",含义为"什么过程是为已完成的项目范围获取干系人的正式验收",选项B对项目的范围进行验证,其他选项容易排除。

  • 第23题:

    单选题
    ()is the process of obtaining the stakeholders’ formal acceptance of the completed project scopE. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
    A

    Project acceptance

    B

    Scope verification

    C

    Scope definition

    D

    WBS Creation


    正确答案: D
    解析: 范围验证是指获取项目干系人对已完成的项目范围的正式认可的过程。验证范围包括评审可交付物和工作成果,以确保这些工作都已按照范围定义中的要求完成。