单选题A customer is interested in using two Power 550 servers to implement a new two node cluster. The cluster willbe using SAN attached disk for shared storage and will be attached to one IP network. Which of the followingadapter configurations will meet th

题目
单选题
A customer is interested in using two Power 550 servers to implement a new two node cluster. The cluster willbe using SAN attached disk for shared storage and will be attached to one IP network. Which of the followingadapter configurations will meet the customer requirements while reducing single points of failure?()
A

A

B

B

C

C

D

D


相似考题
更多“单选题A customer is interested in using two Power 550 servers to implement a new two node cluster. The cluster willbe using SAN attached disk for shared storage and will be attached to one IP network. Which of the followingadapter configurations will meet th”相关问题
  • 第1题:

    You plan to implement a Hyper-V host cluster. The cluster will contain two servers connected to a Storage Area Network (SAN). You need to recommend a storage location for virtual machine (VM) snapshots. The solution must ensure that the VMs can fail over. Which storage location should you recommend?()

    • A、a domain-based Distributed File System (DFS) namespace
    • B、a network share
    • C、the SAN
    • D、a local hard disk

    正确答案:C

  • 第2题:

    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()

    • A、What are the plans for Disaster Recovery? 
    • B、What are the plans for data migration? 
    • C、Would iSCSI meet your needs? 
    • D、How much space is available in the current storage systems?

    正确答案:B

  • 第3题:

    A cluster administrator has been asked to install HACMP on two nodes with the following  hardware:   -two CPUs, - 1GB RAM, - one 1 36GB drive, -two 10/100/1000 Ethernet adapters, and -GB Fibre Channel adapters dual attached to SAN storage.  In order to eliminate single points of failure,the administrator should first add which of the following:()   

    • A、 an additional 1GB RAM to each node.
    • B、 Another bootable mirrored disk drive.
    • C、 A 10/100/1000 GB Ethernet adapter to be attached to a redundant switch.
    • D、 Nothing,because this is a viable cluster solution with no single points of failure.

    正确答案:B

  • 第4题:

    A customer is planning a PowerHA cluster split across two sites. The sites are located 10km apart. There is aDS8000 storage array at each site with SAN connectivity between the two arrays. There are only enough IPinterfaces for one IP network in this cluster. How can they ensure that disk data is automatically mirrored and synchronized between sites?()

    • A、Purchase PowerHA/XD license
    • B、Purchase PowerHA with GLVM license
    • C、Implement PowerHA with split-site LVM
    • D、Implement PowerHA with cross-site LVM

    正确答案:D

  • 第5题:

    You are designing a Hyper-V solution. You plan to virtualize an application server. The application server requires failover clustering that uses shared storage. You need to choose the correct storage solution. What should you choose?()

    • A、two child partitions with VHDs stored on an iSCSI SAN
    • B、two child partitions with volumes mounted from an iSCSI SAN
    • C、two host servers with iSCSI-attached storage enabled for Cluster Shared Volumes (CSVs)
    • D、two host servers with Fibre ChannelCattached storage enabled for Cluster Shared Volumes (CSVs)

    正确答案:B

  • 第6题:

    You need to recommend the server configurations for the new failover cluster. The configurations must support the company's planned changes    Which two actions should you recommend?()

    • A、From Hyper-V Manager on each node, configure one virtual network.
    • B、From Hyper-V Manager on one node, configure two virtual networks.
    • C、Install one network adapter on each node. Configure the network adapters to use multiple IP ddresses.
    • D、Install two network adapters on each node. Configure the network adapters to communicate on  separate subnets.

    正确答案:A,D

  • 第7题:

    单选题
    A customer is planning a PowerHA cluster split across two sites. The sites are located 10km apart. There is aDS8000 storage array at each site with SAN connectivity between the two arrays. There are only enough IPinterfaces for one IP network in this cluster. How can they ensure that disk data is automatically mirrored and synchronized between sites?()
    A

    Purchase PowerHA/XD license

    B

    Purchase PowerHA with GLVM license

    C

    Implement PowerHA with split-site LVM

    D

    Implement PowerHA with cross-site LVM


    正确答案: D
    解析: 暂无解析

  • 第8题:

    单选题
    A cluster administrator has been asked to install HACMP on two nodes with the following  hardware:   -two CPUs, - 1GB RAM, - one 1 36GB drive, -two 10/100/1000 Ethernet adapters, and -GB Fibre Channel adapters dual attached to SAN storage.  In order to eliminate single points of failure,the administrator should first add which of the following:()
    A

     an additional 1GB RAM to each node.

    B

     Another bootable mirrored disk drive.

    C

     A 10/100/1000 GB Ethernet adapter to be attached to a redundant switch.

    D

     Nothing,because this is a viable cluster solution with no single points of failure.


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    You plan to implement a Hyper-V host cluster. The cluster will contain two servers connected to a Storage Area Network (SAN). You need to recommend a storage location for virtual machine (VM) snapshots. The solution must ensure that the VMs can fail over. Which storage location should you recommend?()
    A

    a domain-based Distributed File System (DFS) namespace

    B

    a network share

    C

    the SAN

    D

    a local hard disk


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()
    A

    What are the plans for Disaster Recovery? 

    B

    What are the plans for data migration? 

    C

    Would iSCSI meet your needs? 

    D

    How much space is available in the current storage systems?


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    Two file servers have run out of local disk space. The internal drives are at capacity and the company has traditionally only used local disks for storage. Which of the following is the MOST cost effective solution to add storage to both servers?()
    A

    Install fiber cards into the servers and add direct attached storage.

    B

    Install fiber cards into the servers and implement a SAN solution.

    C

    Attach a USB drive to one of the servers.

    D

    Add a NAS to the environment


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    Two file servers have run out of local disk space. The internal drives are at capacity and the company has traditionally only used local disks for storage.  Which of the following is the MOST cost effective solution to add storage to both servers?()
    A

     Install fiber cards into the servers and add direct attached storage.

    B

     Install fiber cards into the servers and implement a SAN solution.

    C

     Attach a USB drive to one of the servers.

    D

     Add a NAS to the environment.


    正确答案: B
    解析: 暂无解析

  • 第13题:

    Which two statements about Network Attached Storage are correct?()

    • A、Data is accessed using NFS or CIFS.
    • B、Data is accessed at the block level.
    • C、NAS is referred to as captive storage.
    • D、Storage devices can be shared between users.
    • E、A NAS implementation is not as fast as a DAS implementation.

    正确答案:C,D

  • 第14题:

    A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()

    • A、Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs
    • B、Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.
    • C、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.
    • D、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.

    正确答案:C

  • 第15题:

    Company.com is migrating from a third party managed disk subsystem to an IBM TotalStorage Enterprise Storage Server. Connection of the new storage server is complete, and it has been tested on all of the nodes in the three node HACMP cluster.  How does the customer migrate to the new storage server with minimum down time?()

    • A、 Shut down one node at a time and let the other node serve the application
    • B、 Stop HACMP with the forced option and perform migration of the disks on one node,then restart HACMP
    • C、 Stop both nodes and perform the migration all at once using standard AIX commands in parallel, then restart the cluster
    • D、 Use C-SPOC to add the new disks to the cluster and migrate the information off the existing disks, then remove the old disks with C-SPOC

    正确答案:D

  • 第16题:

    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()

    • A、What are Disaster Recoveryplans
    • B、What are plans for datamigration
    • C、What storage system space isavailable
    • D、DoesiSCSI meet the needs

    正确答案:B

  • 第17题:

    Your network includes Windows Server 2008 R2 Hyper-V servers. You are configuring the servers in a failover cluster that will host highly available virtual machines (HAVMs).  You plan to manage the servers in the cluster by using Microsoft System Center Virtual Machine Manager (VMM) 2008 R2. You need to design a storage solution for the cluster that allows you to migrate virtual machines (VMs) into and out of the cluster by using SAN migration.  Which two actions should you include in your design?()

    • A、Enable the automount feature on each node in the cluster
    • B、Install a Virtual Disk Service (VDS) hardware provider on each node in the cluster
    • C、Place all VMs on a single Cluster Shared Volume (CSV)
    • D、Place all VMs on a dedicated logical unit number (LUN)

    正确答案:B,D

  • 第18题:

    You are designing a Hyper-V solution. You plan to virtualize an application server. The application server requires failover clustering that uses shared storage. You need to choose the correct storage solution. What should you choose?()

    • A、Two child partitions with volumes mounted from an iSCSI SAN
    • B、Two host servers with Fibre Channel-attached storage enabled for Cluster Shared Volumes (CSVs)
    • C、Two host servers with iSCSI-attached storage enabled for Cluster Shared Volumes (CSVs)
    • D、Two child partitions with VHDs stored on an iSCSI SAN

    正确答案:A

  • 第19题:

    单选题
    During a planning session, the customer indicates that they intend to build two independent two- Node clusters (cluster ’A’ and ’B’) that will be provided shared storage form an IBM TotalStorage FAStT900 server. The customer intends to present 2 LUNs to cluster ’A’, and 2 LUNs to cluster ’B’. All hosts will be dual attached via fibre.  What additional hardware or software is necessary to make this a valid configuration?()
    A

     SAN switches

    B

     Fibre channel Hub(s)

    C

     IBM Storage Manager Agents

    D

     IBM Subsystem Device Driver


    正确答案: C
    解析: 暂无解析

  • 第20题:

    单选题
    A customer is interested in using two Power 550 servers to implement a new two node cluster. The cluster willbe using SAN attached disk for shared storage and will be attached to one IP network. Which of the followingadapter configurations will meet the customer requirements while reducing single points of failure?()
    A

    A

    B

    B

    C

    C

    D

    D


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()
    A

    What are Disaster Recoveryplans

    B

    What are plans for datamigration

    C

    What storage system space isavailable

    D

    DoesiSCSI meet the needs


    正确答案: A
    解析: 暂无解析

  • 第22题:

    单选题
    A two-node cluster is attached via SAN to shared disk. The customer has requested that one of  the nodes be moved to another room 300 feet away. However, this distance exceeds the length specified by the RS232 specifications.  What solution would resolve the RS232 specification issue with the fewest additional components?()
    A

     Target mode fiber channel can be used with a SAN solution.

    B

     The heartbeat could be established by using a disk heartbeat.

    C

     An RS232 line driver can be used to extend the existing serial connection.

    D

     The NIM for the serial connection can be altered to compensate for the additional delay caused by the increased distance.


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()
    A

    Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs

    B

    Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.

    C

    Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.

    D

    Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.


    正确答案: A
    解析: 暂无解析

  • 第24题:

    单选题
    Company.com is migrating from a third party managed disk subsystem to an IBM TotalStorage Enterprise Storage Server. Connection of the new storage server is complete, and it has been tested on all of the nodes in the three node HACMP cluster.  How does the customer migrate to the new storage server with minimum down time?()
    A

     Shut down one node at a time and let the other node serve the application

    B

     Stop HACMP with the forced option and perform migration of the disks on one node,then restart HACMP

    C

     Stop both nodes and perform the migration all at once using standard AIX commands in parallel, then restart the cluster

    D

     Use C-SPOC to add the new disks to the cluster and migrate the information off the existing disks, then remove the old disks with C-SPOC


    正确答案: D