when replacing an SVC node due to a failure
when migrating from a Windows OS to a Linux OS
when replacing older storage with newer storage
when performing a firmware upgrade on the SVC console
第1题:
In which situation is shredding XML data recommended?()
第2题:
Which of the following is most accurate in describing the required types of FCP zoningconsiderations when implementing a SAN Volume Controller (SVC)?()
第3题:
A customer has a mission-critical application with redundant fabrics. The customer plans to replace older EMC Symmetrix 8830 systems with an IBM System Storage DS8700 and an IBM SAN Volume Controller (SVC). Which statement best describes the way to minimize the impact of data migration on the production environment()
第4题:
For which two tasks would it be best NOT to use the utility SQL*Loader?()
第5题:
A data file become corrupted in your database due to bad sectors on the disk. Because of corruption, you lost all the important tables in that data file. Which method would you use for recovery?()
第6题:
In which situations will the ASM metadata backup help you recover the ASM disk in a disk group?()
第7题:
Metro Mirror
HSM
SVC
Global Copy
第8题:
Flash back all the tables in the data file, one by one.
Restore the data file to a new location and perform a media recovery.
Flash back the database, there is no need to restore the data file.
Restore the data file from the most recent backup and flash the database.
第9题:
pressure builds up in the nozzle which causes a surge of water
the only opening in a passageway is the one from which the nozzle is being advanced
pressure in the fire hose drops below 100 psi
a bulkhead collapses due to heat and pressure
第10题:
flash back all the tables in the data file, one by one
restore the data file to a new location and perform a media recovery
flash back the database; there is no need to restore the data file
restore the data file from the most recent backup and flash back the database
第11题:
zoning is typically limited to controlling access to physical storage
zoning is focused on access control between SVC nodes and host systems
zoning is focused on access to physical storage arrays, SVC clusters, and hosts
zoning is focused on the access relationship between SVC nodes and the physical storagearrays
第12题:
Back up the data, remove the failing disk from the volume group, then restore the data to the new disk.
Use the migratepv command to move data from one disk to another and then remove the failing disk from the volume group.
Use the mirrorvg command to mirror the data to the new disk, break the mirror and then remove the failing disk from the volume group.
Create a new filesystem on the new disk and use the mv command to move the data to the new filesystem, and then remove the failing disk from the volume group.
第13题:
All of the following are data optimization (space efficiency) technologies from IBM EXCEPT().
第14题:
A mainframe customer with a 2105-800 storage subsystem will be migrating to a new data center.They will be replacing existing servers with newer hardware and the 2105 subsystem with an IBMSystem Storage DS8100. The data centers are 613 kilometers apart. The data migration andproduction cutover must be accomplished with minimal disruption. Which solution best meetsthese requirements?()
第15题:
Error log analysis indicates that a disk is starting to fail and will need to be replaced. The failing disk contains multiple logical volumes which span multiple disks. A free disk has been added to the failing disk’s volume group.Which of the following is the most efficient method to move the data from the failing disk to the new disk?()
第16题:
Identify two situations in which the block header grows in a data block. ()
第17题:
You need to dump the data from the master server and import it into a new slave server. Which mysqldump option can be used when dumping data from the master server in order to include the master server's binary log information?()
第18题:
A loss of quorum has occurred on one of the disks in the failed volume group.
Selective fallover caused by an application moves a resource group to a takeover node.
A check is made to ensure at least one complete copy of all data is available in the volume group.
The MISSING_PV=TRUE environment variable has been set causing the volume group to be forced online.
第19题:
IBM DS8700
IBM XIV GUI
IBM System Storage N7600
IBM SAN Volume Controller (SVC)
第20题:
The data destruction requirements
The user awareness training program
The laws and legal requirements of the data
The companys individual data retention policies
第21题:
Scaling
Copying
Duplex
Simplex
第22题:
Include-master-info
Master-binlog
Include-log-file
Master-data
第23题:
the production environment does not require an outage
the production environment requires an outage to install the SVC
the production environment requires an outage to install the DS8700
the production environment requires an outage to remove the EMC systems