多选题A customer has just purchased six x346 servers running Windows 2003 Web Edition.They are expecting to add six additional x346’s in three months.They have a requirement to automatically deploy the current server image upon the new servers. What TWO acti

题目
多选题
A customer has just purchased six x346 servers running Windows 2003 Web Edition.They are expecting to add six additional x346’s in three months.They have a requirement to automatically deploy the current server image upon the new servers. What TWO actions are required to complete this task?()
A

Ensure Director Agent is installed on the new servers.

B

Ensure a DHCP Sever is installed and configured in the environment.

C

Ensure Server Plus Pack option has been installed and configured.

D

Ensure Software Distribution has been installed on the IBM Director Server and an image has been created.

E

Ensure Remote Deployment Manager has been installed on the IBM Director Server and an image has been created.


相似考题
更多“多选题A customer has just purchased six x346 servers running Windows 2003 Web Edition.They are expecting to add six additional x346’s in three months.They have a requirement to automatically deploy the current server image upon the new servers. What TWO acti”相关问题
  • 第1题:

    A customer has just purchased six x346 servers running Windows 2003 Web Edition.They are expecting to add six additional x346’s in three months.They have a requirement to automatically deploy the current server image upon the new servers. What TWO actions are required to complete this task?()

    • A、Ensure Director Agent is installed on the new servers.
    • B、Ensure a DHCP Sever is installed and configured in the environment.
    • C、Ensure Server Plus Pack option has been installed and configured.
    • D、Ensure Software Distribution has been installed on the IBM Director Server and an image has been created.
    • E、Ensure Remote Deployment Manager has been installed on the IBM Director Server and an image has been created.

    正确答案:B,E

  • 第2题:

    The workload requirement for a Web server running in Micro-Partitioned p5-550 has increased 300 percent over the past six months. The initial partition definitions assigned 0.5 processing units and one virtual processor to the Web server partition. Three months previously, an additional 0.5 CPU was added to the Web server partition. When the technical specialist attempted to allocate a further 0.5 CPU to this partition, no additional performance was achieved. Which of the following actions would most likely resolve the problem?()

    • A、Add another virtual Ethernet.
    • B、Change the partition to be uncapped.
    • C、Change the number of virtual processors to 2.
    • D、Increase the amount of memory assigned to the partition by 300 percent.

    正确答案:C

  • 第3题:

    A p5 570 12 way was purchased with the plan to install six LPARs running AIX 5.2. The machine has 12 disks spread evenly over the internal server drawers. The customer would now like to add a seventh LPAR. Which of the following should be added for the seventh LPAR boot device?()

    • A、An additional 7311-D10 drawer
    • B、An adapter to boot off a SAN device
    • C、An additional disk to the media bay
    • D、Two disks to the internal configuration

    正确答案:B

  • 第4题:

    A customer’s new rack contains 12 x p655 servers.   The customer currently has an HMC with one 128-port async adapter with a rack mounted 16-port RAN. The HMC is already attached to two pSeries p630s.  What upgrades, if any, are needed to the HMC to support the new p655 servers?()

    • A、No upgrades are needed.
    • B、Add another 16-port RAN.
    • C、Add an 8-port async adapter.
    • D、Add an additional 128-port adapter.

    正确答案:C

  • 第5题:

    A customer is running a number of non-IBM servers purchased two years ago and has settled on one of the new IBM xSeries servers as a migration path.  From the following options, which is the preferred migration path?()

    • A、Copy the image of the non-IBM servers and copy that image to the IBM servers, then reboot the IBM servers.
    • B、Copy the image from the non-IBM servers with RDM and install them with IBM Director to the new IBM servers. Reboot the IBM servers.
    • C、Install a fresh operating system using ServerGuide, and then install the applications and copy the data from the old servers.
    • D、Install a fresh operating system on the IBM servers and then run ServerGuide on the IBM servers to migrate the applications and data to the IBM servers.

    正确答案:C

  • 第6题:

    A customer has six Windows 2003 servers, three RedHat Linux servers, and three Netware servers.  The current environment is direct attached storage.  The customer needs a 2Gb Fibre solution that can scale up to 64 partitions over the next three years and provide connectivity to all three platforms.  The customer also needs a fibre attached backup solution.  Which of the following solutions has the best combination of price and performance?()

    • A、A DS4300 Turbo with Fibre Attached Tape Library
    • B、A DS4500 with EXP700’s and Fibre Attached Tape Library
    • C、A DS4500 with EXP710’s and Fibre Attached Tape Library
    • D、A DS4300 with Additional EXP710’s and a SCSI Attached Tape Library

    正确答案:A

  • 第7题:

    You have an Exchange Server 2003 organization. All servers have 32-bit hardware. You plan to transition to Exchange Server 2010 and deploy new Mailbox servers.  You need to evaluate the current servers to provide recommendations for the deployment of the newMailbox servers.  What should you include in the evaluation?()

    • A、.number of concurrent connections to Outlook Web App .number of mailbox databases.memory utilization
    • B、.number of concurrent connections to Outlook Web App .RPC latency.disk I/O latency
    • C、.number of concurrent MAPI connections.size of mailbox databases.number of mailboxes
    • D、.number of mailboxes.disk I/O latency.RPC latency

    正确答案:C

  • 第8题:

    You have an Exchange Server 2003 organization. All servers have 32-bit hardware. You plan to transition to Exchange Server 2010 and deploy new Mailbox servers.  You need to evaluate the current servers to provide recommendations for the deployment of the new Mailbox servers.  What should you include in the evaluation?()

    • A、.number of concurrent connections to Outlook Web App .number of mailbox databases.memory utilization
    • B、.number of concurrent connections to Outlook Web App .RPC latency.disk I/O latency
    • C、.number of concurrent MAPI connections.size of mailbox databases.number of mailboxes
    • D、.number of mailboxes.disk I/O latency.RPC latency

    正确答案:C

  • 第9题:

    单选题
    A customer needs to add three JS22 blade servers. The customer currently has three HS21 Blade servers and one LS41 4-socket Blade Server. Based upon this information,  what additional items does the customer need to purchase? ()
    A

    An IBM BladeCenter H chassis for the JS22 Blade servers

    B

    A concurrent KVM daughter card

    C

    A pair of IBM BladeCenter Power Supplies

    D

    A second Management Module


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    Your company purchases 15 new 64-bit servers as follows: èFive of the servers have a single processor.    èFive of the servers have a single dual core processor. èFive of the servers have two quad core processors.   You plan to deploy Windows Server 2008 R2 on the new servers by using Windows Deployment Services (WDS).  You need to recommend a WDS install image strategy that meets the following requirements: Minimizes the number of install images   Supports the deployment of Windows Server 2008 R2 What should you recommend?()
    A

    one install image file that contains three install images

    B

    one install image file that contains a single install image

    C

    two install image files that each contain a single install image

    D

    three install image files that each contain a single install image


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    A customer has four 2-way 2U front-end web servers that are currently running at 15% CPU utilization.  These servers provide points of access for users worldwide, and volume is expected to triple in the next six months and aggressively grow thereafter.  They want to upgrade these systems to newer technology and stay within the 8U of rack space that they are replacing.  Which solution would fit the customer’s requirements?()
    A

    Three x366 4-ways running VMWare ESX Server.

    B

    An x445 8-way Xeon MP attached to a DS4300 and running VMWare ESX Server.

    C

    An x445 16-way Xeon MP attached to an EXP400 and running VMWare ESX Server.

    D

    Four x346 2-ways running VMWare ESX Server.


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    ompany.com has a Micro-Partitioned p5-570 4-way with six application partitions and two VIO servers. Each VIO server has been allocated 0.5 CPU and the application servers have been allocated 0.4 CPUs. The marketing department wants to deploy a new Web server to support the release of a product. The systems architect has recommended that the Web server will require a whole CPU. Which of the following should the technical specialist suggest to provide the most cost-effective deployment?()
    A

    Remove one application server partition and apply its CPU resources to the Web server.

    B

    Reassign the CPU from one of the VIO servers and create the new partition.

    C

    Add 0.6 CPU to one of the application servers and run the Web service with the application. 

    D

    Reassign a total of 0.4 CPUs from the application servers and create a new partition with awhole CPU for new deployment.


    正确答案: D
    解析: 暂无解析

  • 第13题:

    A customer needs to deploy ten dual processor Xeon servers.  Six servers will be running Linux and Apache, and the other four will be Citrix presentation servers.  The customer’s main concerns are the rack space and the option to have SATA drives.  The maximum memory required is 8GB.  Which of the following options will provide the best price and performance?()

    • A、Ten x306’s with internal SATA drives
    • B、Five x346’s with internal SATA drives and VMWare ESX Server
    • C、Five x366’s partitioned into two VMs each with VMWare ESX Server
    • D、Ten x336’s with internal SATA drives

    正确答案:D

  • 第14题:

    ompany.com has a Micro-Partitioned p5-570 4-way with six application partitions and two VIO servers. Each VIO server has been allocated 0.5 CPU and the application servers have been allocated 0.4 CPUs. The marketing department wants to deploy a new Web server to support the release of a product. The systems architect has recommended that the Web server will require a whole CPU. Which of the following should the technical specialist suggest to provide the most cost-effective deployment?()

    • A、Remove one application server partition and apply its CPU resources to the Web server.
    • B、Reassign the CPU from one of the VIO servers and create the new partition.
    • C、Add 0.6 CPU to one of the application servers and run the Web service with the application. 
    • D、Reassign a total of 0.4 CPUs from the application servers and create a new partition with awhole CPU for new deployment.

    正确答案:D

  • 第15题:

    A customer has four 2-way 2U front-end web servers that are currently running at 15% CPU utilization.  These servers provide points of access for users worldwide, and volume is expected to triple in the next six months and aggressively grow thereafter.  They want to upgrade these systems to newer technology and stay within the 8U of rack space that they are replacing.  Which solution would fit the customer’s requirements?()

    • A、Three x366 4-ways running VMWare ESX Server.
    • B、An x445 8-way Xeon MP attached to a DS4300 and running VMWare ESX Server.
    • C、An x445 16-way Xeon MP attached to an EXP400 and running VMWare ESX Server.
    • D、Four x346 2-ways running VMWare ESX Server.

    正确答案:B

  • 第16题:

    A banking customer has the following requirements for an IBM BladeCenter solution with high speed fibre channel: (1)four 4-socket Microsoft SQL servers with two hot swap SAS drives  (2)two physical Microsoft Active Directory Servers  (3)twenty-two physical Citrix servers  (4)three physical Web servers (5)one physical vCenter server   (6)eight vSphere hosts  Which configuration minimally satisfies these requirements?()

    • A、Three IBMBladeCenter S chassis, three Brocade Fibre modules, six Ethernet modules
    • B、Three IBMBladeCenter E chassis, three Brocade Fibre modules, six Ethernet modules
    • C、Four IBMBladeCenter H chassis, four QLogic Fibre Channel modules, eight Ethernet modules
    • D、Three IBMBladeCenter H chassis, three QLogic Fibre Channel modules, six Ethernet modules

    正确答案:D

  • 第17题:

    A customer has six model H70s with dual processors and needs to reduce the current complexity of managing the systems. Which of the following solutions should be recommended?()

    • A、Six 2-way p610
    • B、8-way p670 with six LPARs
    • C、8-way p630 with six LPARs
    • D、Three p615s with two LPARs each

    正确答案:B

  • 第18题:

    A Customer has a proprietary server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible for deployment with their provisioning system. Which of the following methods can achieve this?()

    • A、UseServerGuide to install Windows 2003rchase PowerVM Standard Edition for the entire system
    • B、Install Windows 2003 using the F6 supply Mass Storage Controller option
    • C、Replace Customer’s deployment solution with Tivoli Provisioning Manager for OS Deployment Director Edition
    • D、Deploy Customer’s existing image and useUXSPi to update IBM specific drivers

    正确答案:A

  • 第19题:

    Your company purchases 15 new 64-bit servers as follows: èFive of the servers have a single processor.    èFive of the servers have a single dual core processor. èFive of the servers have two quad core processors.   You plan to deploy Windows Server 2008 R2 on the new servers by using Windows Deployment Services (WDS).  You need to recommend a WDS install image strategy that meets the following requirements: Minimizes the number of install images   Supports the deployment of Windows Server 2008 R2 What should you recommend?()

    • A、one install image file that contains three install images
    • B、one install image file that contains a single install image
    • C、two install image files that each contain a single install image
    • D、three install image files that each contain a single install image

    正确答案:B

  • 第20题:

    Your company has an Active Directory domain. You have a server named KMS1 that runs Windows Server 2008. You install and configure Key Management Service (KMS) on KMS1.  You plan to deploy Windows Server 2008 on 10 new servers. You install the first two servers. The servers fail to activate by using KMS1.  You need to activate the new servers by using the KMS server. What should you do?()

    • A、Complete the installation of the remaining eight servers.
    • B、Configure Windows Management Instrumentation (WMI) exceptions in Windows Firewall on the new servers.
    • C、Install Volume Activation Management Tool (VAMT) on the KMS server and configure Multiple Activation Key (MAK) Proxy Activation.
    • D、Install Volume Activation Management Tool (VAMT) on the KMS server and configure Multiple Activation Key (MAK) Independent Activation.

    正确答案:A

  • 第21题:

    单选题
    A Customer has a functional server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible. What method can achieve this?()
    A

    Install Windows 2003 using the F6 supply Mass Storage Controller option

    B

    Replace Customer’s deployment solution with Tivoli Provisioning Manager for OS Deployment Director Edition

    C

    Deploy Customer’s existing image and use UXSPi to update IBM specific drivers

    D

    Use ServerGuide to install Windows 2003


    正确答案: A
    解析: 暂无解析

  • 第22题:

    单选题
    You have an Exchange Server 2003 organization. All servers have 32-bit hardware. You plan to transition to Exchange Server 2010 and deploy new Mailbox servers.  You need to evaluate the current servers to provide recommendations for the deployment of the new Mailbox servers.  What should you include in the evaluation?()
    A

    .number of concurrent connections to Outlook Web App .number of mailbox databases.memory utilization

    B

    .number of concurrent connections to Outlook Web App .RPC latency.disk I/O latency

    C

    .number of concurrent MAPI connections.size of mailbox databases.number of mailboxes

    D

    .number of mailboxes.disk I/O latency.RPC latency


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    A banking customer has the following requirements for an IBM BladeCenter solution with high speed fibre channel: (1)four 4-socket Microsoft SQL servers with two hot swap SAS drives  (2)two physical Microsoft Active Directory Servers  (3)twenty-two physical Citrix servers  (4)three physical Web servers (5)one physical vCenter server   (6)eight vSphere hosts  Which configuration minimally satisfies these requirements?()
    A

    Three IBMBladeCenter S chassis, three Brocade Fibre modules, six Ethernet modules

    B

    Three IBMBladeCenter E chassis, three Brocade Fibre modules, six Ethernet modules

    C

    Four IBMBladeCenter H chassis, four QLogic Fibre Channel modules, eight Ethernet modules

    D

    Three IBMBladeCenter H chassis, three QLogic Fibre Channel modules, six Ethernet modules


    正确答案: C
    解析: 暂无解析

  • 第24题:

    多选题
    A customer has just purchased six x346 servers running Windows 2003 Web Edition.They are expecting to add six additional x346’s in three months.They have a requirement to automatically deploy the current server image upon the new servers. What TWO actions are required to complete this task?()
    A

    Ensure Director Agent is installed on the new servers.

    B

    Ensure a DHCP Sever is installed and configured in the environment.

    C

    Ensure Server Plus Pack option has been installed and configured.

    D

    Ensure Software Distribution has been installed on the IBM Director Server and an image has been created.

    E

    Ensure Remote Deployment Manager has been installed on the IBM Director Server and an image has been created.


    正确答案: A,C
    解析: 暂无解析