单选题A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use t

题目
单选题
A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()
A

Design the least-cost solution to prevent the competition from winning the business.

B

Design a disaster recovery (DR) solution and convince the customer why DR is important to their business.

C

Use the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.

D

Design a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.


相似考题
更多“单选题A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use t”相关问题
  • 第1题:

    A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()

    • A、Design the least-cost solution to prevent the competition from winning the business.
    • B、Design a disaster recovery (DR) solution and convince the customer why DR is important to their business.
    • C、Use the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.
    • D、Design a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.

    正确答案:D

  • 第2题:

    A customer has requested the most cost-effective p5 solution allowing for growth.  Which of the following should the pSeries technical specialist consider doing when configuring each p5 system using eConfig?()

    • A、Implementing CoD
    • B、Using Express Configurations with processor upgrades
    • C、Meeting the minimum Value Pak rules
    • D、Engaging the pSeries representative to identify appropriate discounts

    正确答案:C

  • 第3题:

    A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them.  Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()

    • A、The technical support specialist has completed a UNIX course at college.
    • B、The technical specialist has supported several similar projects and has earned an IBM AIX certification.
    • C、The technical support specialist’s company sells $3M of UNIX computer systems every year.
    • D、The technical support specialist has sold and installed at least a dozen Apple and iSeries systems with POWER processors.

    正确答案:B

  • 第4题:

    A customer requires a deskside solution that they will rack-mount in the future.  Space is at a premium.  The solution must support two AIX 5.2 applications that require two processors each.  Which of the following deskside configurations should the pSeries Technical Specialist recommend?()

    • A、One p5-550 4-way
    • B、Two 2-way p5-520s
    • C、One p630 4-way
    • D、Two 2-way p615s

    正确答案:A

  • 第5题:

    A large customer is consolidating their pSeries systems onto a p5 590. They will have a requirement for a single device (disk, lun) to have multiple paths through different  adapters in a single LPAR. The primary applications were written for AIX 5.2. Which of the following would be the recommended solution to satisfy this requirement?()

    • A、Assign the adapters to a Virtual IO partition
    • B、Use the MPIO function included in AIX 5.2
    • C、Migrate the application to AIX 5.3 and use the MPIO function
    • D、Set up two Virtual IO partitions and attach both partitions to the device

    正确答案:B

  • 第6题:

    The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()

    • A、Use eConfig to configure and validate each pSeries and p5 system.
    • B、Engage Advanced Technical Support to review any outstanding technical issues.
    • C、Confirm with the customer that the solution design meets their requirements.
    • D、Perform a Pre-Install Solution Assurance Review to validate required power requirements.

    正确答案:C

  • 第7题:

    单选题
    The sales team has brought in the pSeries technical specialist to recommend the best solution to win the business.   The customer wants the lowest purchase cost four-disk solution using an external I/O solution.  Which of the following offerings provides the required base function at the lowest cost?()
    A

    2104

    B

    ESS800

    C

    FAStT600

    D

    SSA 7133


    正确答案: D
    解析: 暂无解析

  • 第8题:

    单选题
    A large customer is consolidating their pSeries systems onto a p5 590. They will have a requirement for a single device (disk, lun) to have multiple paths through different  adapters in a single LPAR. The primary applications were written for AIX 5.2. Which of the following would be the recommended solution to satisfy this requirement?()
    A

    Assign the adapters to a Virtual IO partition

    B

    Use the MPIO function included in AIX 5.2

    C

    Migrate the application to AIX 5.3 and use the MPIO function

    D

    Set up two Virtual IO partitions and attach both partitions to the device


    正确答案: C
    解析: 暂无解析

  • 第9题:

    单选题
    The pSeries sales representative has done an excellent job in educating the customer on the benefits of working with IBM.  The customer is planning to implement their first ERP application.  This new application will be critical to running their business.  The customer has only a competitor’s UNIX systemcurrently installed.  They are interested in obtaining a proposal from IBM. In addition to the AIX hardware and HACMP software, what else should be included in the IBM proposal for the new ERP solution?()
    A

    I/T services and education to help with the implementation of the hardware and software

    B

    A Supportline specialist to work directly with the customer to manage any issues that arise

    C

    The services required to move the currently installed applications from the competitor’s systems to the IBM systems

    D

    A slimmed down solution to ensure that the IBM solution is less expensive than the competitor’s solution


    正确答案: D
    解析: 暂无解析

  • 第10题:

    单选题
    The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()
    A

    Use eConfig to configure and validate each pSeries and p5 system.

    B

    Engage Advanced Technical Support to review any outstanding technical issues.

    C

    Confirm with the customer that the solution design meets their requirements.

    D

    Perform a Pre-Install Solution Assurance Review to validate required power requirements.


    正确答案: D
    解析: 暂无解析

  • 第11题:

    单选题
    A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()
    A

    Design the least-cost solution to prevent the competition from winning the business.

    B

    Design a disaster recovery (DR) solution and convince the customer why DR is important to their business.

    C

    Use the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.

    D

    Design a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.


    正确答案: C
    解析: 暂无解析

  • 第12题:

    单选题
    A customer requires a deskside solution that they will rack-mount in the future.  Space is at a premium.  The solution must support two AIX 5.2 applications that require two processors each.  Which of the following deskside configurations should the pSeries Technical Specialist recommend?()
    A

    One p5-550 4-way

    B

    Two 2-way p5-520s

    C

    One p630 4-way

    D

    Two 2-way p615s


    正确答案: D
    解析: 暂无解析

  • 第13题:

    A bank is interested in technology that will enhance competitiveness and flexibility in the financial trading market by harnessing the typically unused power of idle machines.  The pSeries technical specialist should make the customer aware of which IBM offering?()

    • A、IBM Grid Toolbox
    • B、IBM Capacity on Demand
    • C、IBM Cluster Systems Management
    • D、IBM Global Solutions Directory

    正确答案:A

  • 第14题:

    A customer is having problems after an AIX version upgrade from 5.2 to 5.3.  Which of the following should the pSeries technical specialist recommend that the customer call?()

    • A、IBM Techline
    • B、IBM Supportline
    • C、IBM Software Distribution
    • D、IBM Hardware Support

    正确答案:B

  • 第15题:

    A global customer’s IT strategy is based upon two DS8000 systems and an N series gateway. They want to protect their  business by implementing a disaster recovery solution. The storage specialist has recommended cascaded mirroring.  Which of the following is the business benefit of cascaded replication()

    • A、it is cost efficient, as a single N series or DS8000 can have its controllers split between the  primary and secondary site and use semi- synchronousmirroring while using asynchronous mirroring to a third site
    • B、the second site acts as a repeater station so that greater geographical distances can be achieved
    • C、ITprovides high availability together with disaster recovery by implementing Metro/Global Mirror across three geographically dispersed systems
    • D、it guarantees data protection by implementing two synchronous copies of the primary site data

    正确答案:C

  • 第16题:

    The account team designed a p5-570 solution to strategically position the customer for future IBM announcements.  The customer was dissatisfied upon implementing the solution.  An AIX v5.1 partition was added to the requirements halfway through the solution design process and it was not considered in the final design. What should the pSeries technical specialist have done to prevent this situation?()

    • A、Submitted an RPQ (Request for Quote) for AIX v5.1 support on a p5-570
    • B、Designed a p670 because it supports AIX 5.1 partitions
    • C、Initially designed a solution supporting AIX 5.1 partitions
    • D、Gained customer approval for the final design prior to ordering the system

    正确答案:D

  • 第17题:

    The sales team has brought in the pSeries technical specialist to recommend the best solution to win the business.   The customer wants the lowest purchase cost four-disk solution using an external I/O solution.  Which of the following offerings provides the required base function at the lowest cost?()

    • A、2104
    • B、ESS800
    • C、FAStT600
    • D、SSA 7133

    正确答案:A

  • 第18题:

    单选题
    A storage specialist is discussing the customer’s high availability plan and discovers that they areonly 80 kilometers (50 miles) from the intended site. They require 7 x 24 x 365 data availability in aUNIX environment with an RPO of two minutes. They have two DS5300 systems located at bothsites. Which of the following IBM storage functions best meets the customer’s businesscontinuance requirements?()
    A

    HACMP

    B

    Volume copy

    C

    Metro Mirror

    D

    Global Mirror


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    A customer is having problems after an AIX version upgrade from 5.2 to 5.3.  Which of the following should the pSeries technical specialist recommend that the customer call?()
    A

    IBM Techline

    B

    IBM Supportline

    C

    IBM Software Distribution

    D

    IBM Hardware Support


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    A customer has requested the most cost-effective p5 solution allowing for growth.  Which of the following should the pSeries technical specialist consider doing when configuring each p5 system using eConfig?()
    A

    Implementing CoD

    B

    Using Express Configurations with processor upgrades

    C

    Meeting the minimum Value Pak rules

    D

    Engaging the pSeries representative to identify appropriate discounts


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A customer is looking for a low-cost pSeries solution.  The pSeries technical specialist is recommending several p650 Express Configurations.  When reviewing the options with the customer, the pSeries technical specialist should emphasize which of the following limitations?()
    A

    Some Express Configurations limit the amount of maximum memory at order time.

    B

    The customer must meet minimum system requirements to obtain Express Configuration pricing. 

    C

    The Express Configurations offer less than the maximum number of processors.

    D

    The Express Configurations are only offered through the QuickShip Program.


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    A bank is interested in technology that will enhance competitiveness and flexibility in the financial trading market by harnessing the typically unused power of idle machines.  The pSeries technical specialist should make the customer aware of which IBM offering?()
    A

    IBM Grid Toolbox

    B

    IBM Capacity on Demand

    C

    IBM Cluster Systems Management

    D

    IBM Global Solutions Directory


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    The account team designed a p5-570 solution to strategically position the customer for future IBM announcements.  The customer was dissatisfied upon implementing the solution.  An AIX v5.1 partition was added to the requirements halfway through the solution design process and it was not considered in the final design. What should the pSeries technical specialist have done to prevent this situation?()
    A

    Submitted an RPQ (Request for Quote) for AIX v5.1 support on a p5-570

    B

    Designed a p670 because it supports AIX 5.1 partitions

    C

    Initially designed a solution supporting AIX 5.1 partitions

    D

    Gained customer approval for the final design prior to ordering the system


    正确答案: A
    解析: 暂无解析

  • 第24题:

    单选题
    A global customer’s IT strategy is based upon two DS8000 systems and an N series gateway. They want to protect their  business by implementing a disaster recovery solution. The storage specialist has recommended cascaded mirroring.  Which of the following is the business benefit of cascaded replication()
    A

    it is cost efficient, as a single N series or DS8000 can have its controllers split between the  primary and secondary site and use semi- synchronousmirroring while using asynchronous mirroring to a third site

    B

    the second site acts as a repeater station so that greater geographical distances can be achieved

    C

    ITprovides high availability together with disaster recovery by implementing Metro/Global Mirror across three geographically dispersed systems

    D

    it guarantees data protection by implementing two synchronous copies of the primary site data


    正确答案: A
    解析: 暂无解析