单选题A customer needs three 2-way application servers and is evaluating the purchase of three p5-520s versus one partitioned 6-way p5-570.  They like the benefits provided with dynamic processor sparing.  What information should the pSeries technical specia

题目
单选题
A customer needs three 2-way application servers and is evaluating the purchase of three p5-520s versus one partitioned 6-way p5-570.  They like the benefits provided with dynamic processor sparing.  What information should the pSeries technical specialist emphasize to the customer?()
A

The p5-570 offers CoD processors.

B

The p5-570 requires more rack space than the three p5-520s.

C

Redundant power is standard on the p5-570 and is optional on the p5-520.

D

Operating system charges will be less expensive with the p5-520 solution.


相似考题
更多“A customer needs three 2-way application servers and is eval”相关问题
  • 第1题:

    A company needs additional storage for a block I/O based database application. The application has low I/O bandwidth requirements across the campus. The customer has a TCP/IP infrastructure and is interested in low-cost products that are compatible with its environment. Which technology is most appropriate for this customer?()

    • A、SAN
    • B、FCoE
    • C、FCIP
    • D、iSCSI

    正确答案:D

  • 第2题:

    A customer needs to add three JS22 blade servers. The customer currently has three HS21 Blade servers and one LS41 4-socket Blade Server. Based upon this information,  what additional items does the customer need to purchase? ()

    • A、An IBM BladeCenter H chassis for the JS22 Blade servers
    • B、A concurrent KVM daughter card
    • C、A pair of IBM BladeCenter Power Supplies
    • D、A second Management Module

    正确答案:C

  • 第3题:

    A customer has two locations that host their pSeries servers.  Traffic is being routed through the public Internet.  The customer needs to exchange confidential financial data between the servers.  Which of the following solutions should the pSeries technical specialist propose to the customer to secure the data?()

    • A、A DCE domain
    • B、A Kerberos domain
    • C、A PPP tunnel between the servers
    • D、An IPSEC tunnel between the servers

    正确答案:D

  • 第4题:

    A customer is evaluating the purchase of a new p570 8-way Express to replace their current set of ten 2-way database and application servers that are more than five years old.  In addition to savings potential in the areas of operating system and database charges, what other significant savings component should be highlighted?()

    • A、Maintenance savings due to warranty on new machines
    • B、Reliability savings of using one machine versus ten
    • C、Financial savings due to cash outlays now versus later
    • D、Power savings even if the current power usage is unknown

    正确答案:A

  • 第5题:

    A customer needs to share large files across three Power Systems servers to create and validate complex automotive designs. What IBM solution should be recommended?()

    • A、PowerHA SystemMirror
    • B、Peer to Peer Remote Copy
    • C、General Parallel File Systems
    • D、Parallel Operating Environment

    正确答案:C

  • 第6题:

    A customer needs a test bed server to run 64-bit modeling, simulation, and other technical applications which require 2-way processors and 6GB RAM in a clustered mode.  They also indicated that this server might be used to run 32-bit applications.  Which of the following servers should be recommended to meet the requirements at the least cost?()

    • A、e326
    • B、x460
    • C、x306
    • D、x236

    正确答案:A

  • 第7题:

    A customer has six model H70s with dual processors and needs to reduce the current complexity of managing the systems. Which of the following solutions should be recommended?()

    • A、Six 2-way p610
    • B、8-way p670 with six LPARs
    • C、8-way p630 with six LPARs
    • D、Three p615s with two LPARs each

    正确答案:B

  • 第8题:

    A customer has six Windows 2003 servers, three RedHat Linux servers, and three Netware servers.  The current environment is direct attached storage.  The customer needs a 2Gb Fibre solution that can scale up to 64 partitions over the next three years and provide connectivity to all three platforms.  The customer also needs a fibre attached backup solution.  Which of the following solutions has the best combination of price and performance?()

    • A、A DS4300 Turbo with Fibre Attached Tape Library
    • B、A DS4500 with EXP700’s and Fibre Attached Tape Library
    • C、A DS4500 with EXP710’s and Fibre Attached Tape Library
    • D、A DS4300 with Additional EXP710’s and a SCSI Attached Tape Library

    正确答案:A

  • 第9题:

    单选题
    A customer needs to add three JS22 blade servers. The customer currently has three HS21 Blade servers and one LS41 4-socket Blade Server. Based upon this information,  what additional items does the customer need to purchase? ()
    A

    An IBM BladeCenter H chassis for the JS22 Blade servers

    B

    A concurrent KVM daughter card

    C

    A pair of IBM BladeCenter Power Supplies

    D

    A second Management Module


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    A customer needs a very small AIX system to run their new application and is considering a 1-way p615.  What key information should the pSeries technical specialist provide to the customer?()
    A

    The 1-way p615 cannot be upgraded to a 2-way p615.

    B

    The 1-way p615 can be upgraded to a 2-way p615 should additional capacity be required.

    C

    The p615 can be upgraded to a POWER5-based processor.

    D

    The p615 is not a good solution, as it does not take advantage of the Advanced POWER Virtualization features.


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    A customer needs a test bed server to run 64-bit modeling, simulation, and other technical applications which require 2-way processors and 6GB RAM in a clustered mode.  They also indicated that this server might be used to run 32-bit applications.  Which of the following servers should be recommended to meet the requirements at the least cost?()
    A

    e326

    B

    x460

    C

    x306

    D

    x236


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    A customer has six Windows 2003 servers, three RedHat Linux servers, and three Netware servers.  The current environment is direct attached storage.  The customer needs a 2Gb Fibre solution that can scale up to 64 partitions over the next three years and provide connectivity to all three platforms.  The customer also needs a fibre attached backup solution.  Which of the following solutions has the best combination of price and performance?()
    A

    A DS4300 Turbo with Fibre Attached Tape Library

    B

    A DS4500 with EXP700’s and Fibre Attached Tape Library

    C

    A DS4500 with EXP710’s and Fibre Attached Tape Library

    D

    A DS4300 with Additional EXP710’s and a SCSI Attached Tape Library


    正确答案: B
    解析: 暂无解析

  • 第13题:

    A customer is interested in reducing energy consumption and infrastructure consolidation for space. The customer needs a maximum of 14 servers in 7U rack.  Which IBM BladeCenter Chassis should be recommended? ()

    • A、BladeCenter E
    • B、BladeCenter H
    • C、BladeCenter T
    • D、BladeCenter HT

    正确答案:A

  • 第14题:

    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()

    • A、What are the plans for Disaster Recovery? 
    • B、What are the plans for data migration? 
    • C、Would iSCSI meet your needs? 
    • D、How much space is available in the current storage systems?

    正确答案:B

  • 第15题:

    A customer needs three 2-way application servers and is evaluating the purchase of three p5-520s versus one partitioned 6-way p5-570.  They like the benefits provided with dynamic processor sparing.  What information should the pSeries technical specialist emphasize to the customer?()

    • A、The p5-570 offers CoD processors.
    • B、The p5-570 requires more rack space than the three p5-520s.
    • C、Redundant power is standard on the p5-570 and is optional on the p5-520.
    • D、Operating system charges will be less expensive with the p5-520 solution.

    正确答案:A

  • 第16题:

    A customer runs an application on a supported 8-way x445.  The customer needs to monitor operations and wants to be alerted when problems arise.  Which TWO of the following can be configured in IBM Director Base Pack to monitor the customer’s operations?()

    • A、Fan operation
    • B、Bottleneck analysis
    • C、Power supply operations
    • D、Planned versus unplanned outages
    • E、Application predictive failure analysis

    正确答案:A,C

  • 第17题:

    A customer currently has a large group of older 1U servers. Each dedicated to aunique application. Quick provisioning of the servers is important to the customer. Which of the following approaches addresses this situation?()

    • A、Virtualization
    • B、Replace each server with energy efficient servers
    • C、Upgrade in place to improve performance
    • D、Implement BladeCenter

    正确答案:A

  • 第18题:

    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()

    • A、What are Disaster Recoveryplans
    • B、What are plans for datamigration
    • C、What storage system space isavailable
    • D、DoesiSCSI meet the needs

    正确答案:B

  • 第19题:

    A financial customer has three data centers that are four kilometers apart. Their SAP application data needs to be kept synchronized within 10 milliseconds.  Which solution satisfies the customer’s recovery time objective()

    • A、DS8700 systems at each site running Metro Mirror
    • B、DS8700 systems at each site running Global Mirror
    • C、DS5300 systems at each site running Global Mirror
    • D、XIV systems at each site running Remote Mirroring

    正确答案:A

  • 第20题:

    A financial customer has three data centers that are approximately five kilometers apart. Their SAP application data needs to be kept synchronized within 10 milliseconds between the three sites. Which of the following solutions satisfies the customer's recovery time objective?()

    • A、DS8700 systems at each site running Metro Mirror
    • B、DS5300 systems at each site running Metro Mirror
    • C、DS5100 systems at each site running Global Mirror
    • D、XIV systems at each site running synchronous mirroring

    正确答案:A

  • 第21题:

    多选题
    Which three customer needs are addressed by Cisco solutions?()
    A

    reducing TCO

    B

    reducing day one costs

    C

    obtaining A wide variety of point products

    D

    improving productivity

    E

    gaining competitive advantage

    F

    focusing on current needs


    正确答案: A,C
    解析: 暂无解析

  • 第22题:

    单选题
    A customer has two locations that host their pSeries servers.  Traffic is being routed through the public Internet.  The customer needs to exchange confidential financial data between the servers.  Which of the following solutions should the pSeries technical specialist propose to the customer to secure the data?()
    A

    A DCE domain

    B

    A Kerberos domain

    C

    A PPP tunnel between the servers

    D

    An IPSEC tunnel between the servers


    正确答案: A
    解析: 暂无解析

  • 第23题:

    多选题
    A customer needs to analyze an application that was developed for Oracle Application Server 10gR2 or 10gR3 (OC4J) in order to prepare to upgrade the infrastructure to WebLogic 12c. The customer wants understand the changes required to be made to the application and how to configure WebLogic in to support the newly upgraded application.    Which three actions would you recommend for upgrading the customer's application and server configuration?()
    A

    Use Oracle Upgrade Manager to create a new WebLogic domain template from an OAS/OC4J  installation and redeploy the application.

    B

    Use SmartUpgrade to analyze the OAS/OC4J server configuration and create WebLogic  configuration files.

    C

    Use SmartUpgrade to analyze the application archive (EAR/WAR/JAR) Source Directory or IDeveloper project and generate a report that describes the areas of the application that need to be updated.

    D

    Use the Configuration Wizard to extend an existing WebLogic domain with OAS/OC4J support  libraries and redeploy the application.

    E

    Use SmartUpgrade to generate application artifacts and deployment descriptors that can be deployed to WebLogic.


    正确答案: B,D,E
    解析: 暂无解析

  • 第24题:

    多选题
    What are three benefit that the Smart Business Architecture provides to customers?()
    A

    enables efficient customer serviceeffctiveness

    B

    provides anempowered fronline workforce

    C

    createsA more informed management.

    D

    generates customer-specific configurations

    E

    automatically matches customer needs to solutions

    F

    provides an ROI analysis for decision-makers


    正确答案: D,B
    解析: 暂无解析