单选题The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical spec

题目
单选题
The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()
A

Use eConfig to configure and validate each pSeries and p5 system.

B

Engage Advanced Technical Support to review any outstanding technical issues.

C

Confirm with the customer that the solution design meets their requirements.

D

Perform a Pre-Install Solution Assurance Review to validate required power requirements.


相似考题
更多“单选题The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical spec”相关问题
  • 第1题:

    A customer is very concerned about maintaining a competitive advantage through the use of state-of-the-art technology.  Assuming all solutions meet the customer’s technical requirements, which solution should the IBM team propose to maximize customer satisfaction?()

    • A、p690 with Dynamic LPAR
    • B、Grid of SP switch-attached p5-550s
    • C、p690 with Advanced POWER Virtualization
    • D、p5-570 with Advanced POWER Virtualization

    正确答案:D

  • 第2题:

    After putting together a configuration that meets customer’s requirements, a TDA is suggested. The customer is not familiar with the TDA process and asks why this should be done. This of the following is the benefit of TDA?()

    • A、 A TDA are recommended only for high end hardware and very large or complex business opportunities
    • B、 A TDA will ensure the solution and configuration are complete and technically sound and meet customer requirements
    • C、 A TDA will guarantee that the hardware will work in customer’s environment at the volumes projected
    • D、 A TDA brings an IBM technician onsite to properly inspect and installed hardware and related software

    正确答案:B

  • 第3题:

    When designing a single tier AIX database solution for a customer, what other technical specialist would be most instrumental in putting together a total solution and why?()

    • A、xSeries specialist,as the customer may have some Intel-based systems.
    • B、Hardware customer engineer,as they will be installing the entire solution.
    • C、Services specialist,as they can provide education recommendations for the entire solution. 
    • D、Storage specialist,as the customer may need disk to store the data and tape to backup the data.

    正确答案:D

  • 第4题:

    The sales team has just sold the first pSeries solution to a Windows NT customer.   The team has identified concerns with a non-existent backup strategy and some workable environmental issues.   In addition to these concerns,what other major concern should be considered?()

    • A、Customer skill level
    • B、Hardware availability
    • C、Lack of executive sponsorship
    • D、Hardware and software compatibility

    正确答案:A

  • 第5题:

    An IBM technician specialist has a prospective customer who is excited about eX5 and is working on configuration for a very large complex opportunity. During the engagement the customer has changed the design several times and has significantly increased the scope. The customers recently selected a Business Partner who has been involved in the last few design changes. What steps should the IBM technician specialist take to make sure the customer is satisfied with the solution?()

    • A、Turn over current design to Techline to create configurations
    • B、Perform knowledge transfer of design requirements to Business partner then disengage
    • C、Work with Business Partner to engage Techline to assist with configuration and request technical and Delivery Assessment (TDA)
    • D、Work with business partner to engage Techline to create configurations

    正确答案:C

  • 第6题:

    The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()

    • A、Use eConfig to configure and validate each pSeries and p5 system.
    • B、Engage Advanced Technical Support to review any outstanding technical issues.
    • C、Confirm with the customer that the solution design meets their requirements.
    • D、Perform a Pre-Install Solution Assurance Review to validate required power requirements.

    正确答案:C

  • 第7题:

    单选题
    Upon announcement,the specific details surrounding the Virtual I/O Server requirements and performance are still being defined.  The customer has engaged IBM to provide a server consolidation solution and would like to take advantage of the VIO Server benefits. How should the pSeries technical specialist best address this?()
    A

    Design the solution and present it confidently so the customer does not question it.

    B

    Design the solution and ensure the customer understands the unknowns with the new technology.

    C

    Explain to the customer that the VIO Server does not benefit them when doing server consolidation so it has not been configured.

    D

    Explain to the customer that the details surrounding the VIO Server have not been clearly defined so designing a solution is premature.


    正确答案: A
    解析: 暂无解析

  • 第8题:

    单选题
    You need to recommend a solution for managing GPOs.The solution must meet the company’s technical requirements. What should you include in the recommendation?()
    A

    Desktop Optimization Pack

    B

    Forefront EndPoint Protection

    C

    System Center Configuration Manager

    D

    System Center Operations Manager


    正确答案: A
    解析: 暂无解析

  • 第9题:

    单选题
    A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()
    A

    Design the least-cost solution to prevent the competition from winning the business.

    B

    Design a disaster recovery (DR) solution and convince the customer why DR is important to their business.

    C

    Use the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.

    D

    Design a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    The account team designed a p5-570 solution to strategically position the customer for future IBM announcements.  The customer was dissatisfied upon implementing the solution.  An AIX v5.1 partition was added to the requirements halfway through the solution design process and it was not considered in the final design. What should the pSeries technical specialist have done to prevent this situation?()
    A

    Submitted an RPQ (Request for Quote) for AIX v5.1 support on a p5-570

    B

    Designed a p670 because it supports AIX 5.1 partitions

    C

    Initially designed a solution supporting AIX 5.1 partitions

    D

    Gained customer approval for the final design prior to ordering the system


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    A solution provider has proposed a pSeries solution to a new customer.  The solution is complex with a number of technologies that are new to the customer. They have a tight timeline for implementation.  The solution provider has not been able to get a clear understanding as to how the customer will backup the system.  What would be the most appropriate action to address the risks with this solution?()
    A

    Sell Sysback

    B

    Conduct a SAR

    C

    Sell Supportline

    D

    Provide a project timeline


    正确答案: C
    解析: 暂无解析

  • 第12题:

    单选题
    A customer is very concerned about maintaining a competitive advantage through the use of state-of-the-art technology.  Assuming all solutions meet the customer’s technical requirements, which solution should the IBM team propose to maximize customer satisfaction?()
    A

    p690 with Dynamic LPAR

    B

    Grid of SP switch-attached p5-550s

    C

    p690 with Advanced POWER Virtualization

    D

    p5-570 with Advanced POWER Virtualization


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()

    • A、Design the least-cost solution to prevent the competition from winning the business.
    • B、Design a disaster recovery (DR) solution and convince the customer why DR is important to their business.
    • C、Use the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.
    • D、Design a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.

    正确答案:D

  • 第14题:

    A solution provider has proposed a pSeries solution to a new customer.  The solution is complex with a number of technologies that are new to the customer. They have a tight timeline for implementation.  The solution provider has not been able to get a clear understanding as to how the customer will backup the system.  What would be the most appropriate action to address the risks with this solution?()

    • A、Sell Sysback
    • B、Conduct a SAR
    • C、Sell Supportline
    • D、Provide a project timeline

    正确答案:B

  • 第15题:

    The account team designed a p5-570 solution to strategically position the customer for future IBM announcements.  The customer was dissatisfied upon implementing the solution.  An AIX v5.1 partition was added to the requirements halfway through the solution design process and it was not considered in the final design. What should the pSeries technical specialist have done to prevent this situation?()

    • A、Submitted an RPQ (Request for Quote) for AIX v5.1 support on a p5-570
    • B、Designed a p670 because it supports AIX 5.1 partitions
    • C、Initially designed a solution supporting AIX 5.1 partitions
    • D、Gained customer approval for the final design prior to ordering the system

    正确答案:D

  • 第16题:

    An IBM System x Technical Expert has a prospective customer who is very excited about X5 and they are working on configurations.   During the process the customer has changed the design numerous times and has significantly increased the scope.  They recently selected a Business Partner who has been involved in the last few design changes. What steps should be taken to make sure the customer is satisfied with the solution?()

    • A、Turn over current design to Techline to create configurations 
    • B、Perform knowledge transfer of design requirements to Business Partner then disengage 
    • C、Work with business partner to engage Techline to assist with configurations and request Technical and Delivery Assessment (TDA) 
    • D、Work with business partner to engage Techline to create configurations

    正确答案:C

  • 第17题:

    A Business Partner is proposing the installation an IBM XIV Storage System at a customer location.  What is the best time to discuss floor space requirements for the solution()

    • A、during the Technical Delivery and Assessment
    • B、during installation of the equipment
    • C、prior to delivery of the XIV
    • D、during the solution proposal

    正确答案:A

  • 第18题:

    单选题
    When designing a single tier AIX database solution for a customer, what other technical specialist would be most instrumental in putting together a total solution and why?()
    A

    xSeries specialist,as the customer may have some Intel-based systems.

    B

    Hardware customer engineer,as they will be installing the entire solution.

    C

    Services specialist,as they can provide education recommendations for the entire solution. 

    D

    Storage specialist,as the customer may need disk to store the data and tape to backup the data.


    正确答案: D
    解析: 暂无解析

  • 第19题:

    单选题
    An IBM technician specialist has a prospective customer who is excited about eX5 and is working on configuration for a very large complex opportunity. During the engagement the customer has changed the design several times and has significantly increased the scope. The customers recently selected a Business Partner who has been involved in the last few design changes. What steps should the IBM technician specialist take to make sure the customer is satisfied with the solution?()
    A

    Turn over current design to Techline to create configurations

    B

    Perform knowledge transfer of design requirements to Business partner then disengage

    C

    Work with Business Partner to engage Techline to assist with configuration and request technical and Delivery Assessment (TDA)

    D

    Work with business partner to engage Techline to create configurations


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    You need to recommend a solution for monitoring the servers. The solution must meet the  company’s technical requirements    What should you include in the recommendation?()
    A

    Data Collector Sets (DCSs)

    B

    event subscriptions

    C

    Reliability Monitor

    D

    Windows System Resource Manager (WSRM)


    正确答案: A
    解析: 暂无解析

  • 第21题:

    单选题
    An IBM System x Technical Expert has a prospective customer who is very excited about X5 and they are working on configurations.   During the process the customer has changed the design numerous times and has significantly increased the scope.  They recently selected a Business Partner who has been involved in the last few design changes. What steps should be taken to make sure the customer is satisfied with the solution?()
    A

    Turn over current design to Techline to create configurations 

    B

    Perform knowledge transfer of design requirements to Business Partner then disengage 

    C

    Work with business partner to engage Techline to assist with configurations and request Technical and Delivery Assessment (TDA) 

    D

    Work with business partner to engage Techline to create configurations


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    After putting together a configuration that meets customer’s requirements, a TDA is suggested. The customer is not familiar with the TDA process and asks why this should be done. This of the following is the benefit of TDA?()
    A

     A TDA are recommended only for high end hardware and very large or complex business opportunities

    B

     A TDA will ensure the solution and configuration are complete and technically sound and meet customer requirements

    C

     A TDA will guarantee that the hardware will work in customer’s environment at the volumes projected

    D

     A TDA brings an IBM technician onsite to properly inspect and installed hardware and related software


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    A sales specialist is presented with a very large, complex opportunity. The customer is in the process of identifying business requirements.  Which of the following tasks is most important to position IBM as the leader to capture this opportunity?()
    A

    Call the IBM Client Representative and ask the rep to influence the company’s executives.

    B

    Develop a strategy to better understand and possibly influence the customer’s success criteria.

    C

    Using IBM’s opportunity management system, request a technical team be formed to design a solution.

    D

    Nominate the customer for a funded IBM Server Consolidation study.


    正确答案: C