第1题:
The following reports are normally developed during the project closure phase?
A Communications Management Plan and Lessons Learned
B Records Archive, Closure Report, lessons learned & Formal Acceptance Report
C Records Archive, Closure Report, & Specifications Document
D Communications Management Plan and Closure report
E None of the above
第2题:
39 You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:
A. The project is operating at a favorable cost efficiency ratio.
B. the project is spending more than planned
C. the project is behind schedule
D. the project is ahead of schedule
E. B and C
第3题:
● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).
(75)
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第4题:
A.has been put
B.have been put
C.being put in
D.to.be put in
第5题:
The most crucial time for project risk assessment is (75) .
A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
第6题:
The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.
A.project charter
B.project scope goal
C.project budget
D.project scope statement
第7题:
第8题:
第9题:
第10题:
Why is it important to have a final meeting on a project that has been cancelled?()
第11题:
when a problem surfaces
during the planning phase
during the close-out phase
after the project schedule has been published
第12题:
Sell Sysback
Conduct a SAR
Sell Supportline
Provide a project timeline
第13题:
112 Of the following, who has the ultimate responsibility for meeting project quality objectives?
A. Project Engineer
B. Project Manager
C. Functional Manager
D. Quality Assurance Manager
E. Project Owner
第14题:
97 The following reports are normally developed during the project closure phase?
A. Communications Management Plan and Lessons Learned
B. Records Archive, Closure Report, lessons learned & Formal Acceptance Report
C. Records Archive, Closure Report, & Specifications Document
D. Communications Management Plan and Closure report
E. None of the above
第15题:
A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
第16题:
●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.
(75) A. Resource assignment matrix
B. Change control plan
C. Project charter
D. Client organization chart
第17题:
The most crucial time for project risk assessment is ( ).
A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
第18题:
The project requires more labor than ________.
[A] has been put in
[B] have been put in
[C] being put in
[D] to be put in
第19题:
第20题:
第21题:
The most crucial time for project risk assessment is ( ).
第22题:
Document lessons learned
Assign responsibility
Close budget
Begin new project