单选题A media customer has an IBM BladeCenter E with ten HS22 Blade server installed. Currently only one Ethernet port is available for each server. What is required to enable the second port on eachserver?()A Fiber Channel Switch ModuleB Gb Ethernet expansi

题目
单选题
A media customer has an IBM BladeCenter E with ten HS22 Blade server installed. Currently only one Ethernet port is available for each server. What is required to enable the second port on eachserver?()
A

Fiber Channel Switch Module

B

Gb Ethernet expansion card

C

Myrinet Cluster expansion card

D

Ethernet Switch Module


相似考题
更多“单选题A media customer has an IBM BladeCenter E with ten HS22 Blade server installed. Currently only one Ethernet port is available for each server. What is required to enable the second port on eachserver?()A Fiber Channel Switch ModuleB Gb Ethernet expansi”相关问题
  • 第1题:

    A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch. Which of the following should be mentioned to the customer regarding the NPIV switch?()

    • A、Youcan not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch
    • B、Using blade servers with the NPIV switch will require morefibre ports on the external fibre switch
    • C、Storage devices likeFibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch.
    • D、The NPIV switch will count against the number of domains in a fabric

    正确答案:C

  • 第2题:

    A customer needs to add three JS22 blade servers. The customer currently has three HS21 Blade servers and one LS41 4-socket Blade Server. Based upon this information,  what additional items does the customer need to purchase? ()

    • A、An IBM BladeCenter H chassis for the JS22 Blade servers
    • B、A concurrent KVM daughter card
    • C、A pair of IBM BladeCenter Power Supplies
    • D、A second Management Module

    正确答案:C

  • 第3题:

    A project requires a new server to be set up with the ability to automatically fail over its Ethernet connection to a second connection if a network failure occurs. Which of the following provides greatest resiliency?()

    • A、Two switch ports will be needed on a switch, two Ethernet cables will be needed for the server each connecting to two different Ethernet cards, and one IP address will be needed.
    • B、Two switch ports will be needed on two different switches, two Ethernet cables will be needed for the server each connecting to two different Ethernet cards, and one IP address will be needed.
    • C、Two switch ports will be needed on two different switches, two Ethernet cables will be needed for the server each connecting to two different Ethernet cards, two different IP addresses will be needed.
    • D、One switch port will be needed on one switch, a splitter will be needed to split the connection, two ethernet cables will be needed for the server each connecting to two different Ethernet cards, and two different IP addresses will be needed.

    正确答案:B

  • 第4题:

    A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()

    • A、Configure 2CFFh combination fibre channel / gigabit Ethernet adapters
    • B、Configure 1CFFh 2-port fibre channel adapter and 1 CIOv 2-port gigabit Ethernet adapter
    • C、Configure 1CIOv 2-port fibre channel adapter and 1 CFFh combination fibre channel / gigabit Ethernet  adapter
    • D、Configure 1CIOv 2-port gigabit Ethernet adapter and 1 CFFh combination fibre channel / gigabit Ethernet  adapter

    正确答案:C

  • 第5题:

    A media customer has an IBM BladeCenter E with ten HS22 Blade server installed. Currently only one Ethernet port is available for each server. What is required to enable the second port on eachserver?()

    • A、Fiber Channel Switch Module
    • B、Gb Ethernet expansion card
    • C、Myrinet Cluster expansion card
    • D、Ethernet Switch Module

    正确答案:D

  • 第6题:

    A banking customer deployed an IBM BladeCenter chassis with one Brocade 8Gb SAN switch module. The customer requires an 8Gb uplink or higher. Which configuration will meet this request of the following?()

    • A、Brocade Enterprise 20-port 8Gb SAN switch module
    • B、Brocade 20-port8Gb SAN switch module and Brocade Advanced Performance Monitoring for IBM BladeCenter
    • C、Brocade Enterprise 10-port 8Gb SAN switch module
    • D、Brocade 10-port8Gb SAN switch module and Brocade Advanced Performance Monitoring for IBM BladeCenter

    正确答案:A

  • 第7题:

    单选题
    A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch. Which of the following should be mentioned to the customer regarding the NPIV switch?()
    A

    Youcan not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch

    B

    Using blade servers with the NPIV switch will require morefibre ports on the external fibre switch

    C

    Storage devices likeFibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch.

    D

    The NPIV switch will count against the number of domains in a fabric


    正确答案: A
    解析: 暂无解析

  • 第8题:

    单选题
    A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()
    A

    Configure 2 CFFh combination fibre channel / gigabit Ethernet adapters

    B

    Configure 1 CFFh 2-port fibre channel adapter and 1 CIOv 2-port gigabit Ethernet adapter

    C

    Configure 1 CIOv 2-port fibre channel adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter

    D

    Configure 1 CIOv 2-port gigabit Ethernet adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    A customer wants to boot from SAN with their IBM BladeCenter infrastructure.  What is required for the customer to be able to perform this? ()
    A

    4GB Modular Flash Drive for each Blade Server and Dual 15.8GB 2.5 Solid State Drive for each Blade Server 

    B

    Cisco Intelligent Gb Ethernet Switch Module and IBM BladeCenter Copper Pass-thru Module 

    C

    Fibre Channel Expansion Card for each Blade Server and Fibre Channel SAN Switch Module 

    D

    Cisco Intelligent Gb Ethernet Switch Module and Dual 15.8GB 2.5 Solid State Drive for each Blade Server


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    A banking customer deployed an IBM BladeCenter chassis with one Brocade 8Gb SAN switch module. The customer requires an 8Gb uplink or higher. Which configuration will meet this request of the following?()
    A

    Brocade Enterprise 20-port 8Gb SAN switch module

    B

    Brocade 20-port8Gb SAN switch module and Brocade Advanced Performance Monitoring for IBM BladeCenter

    C

    Brocade Enterprise 10-port 8Gb SAN switch module

    D

    Brocade 10-port8Gb SAN switch module and Brocade Advanced Performance Monitoring for IBM BladeCenter


    正确答案: D
    解析: 暂无解析

  • 第11题:

    单选题
    A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()
    A

    Configure 2CFFh combination fibre channel / gigabit Ethernet adapters

    B

    Configure 1CFFh 2-port fibre channel adapter and 1 CIOv 2-port gigabit Ethernet adapter

    C

    Configure 1CIOv 2-port fibre channel adapter and 1 CFFh combination fibre channel / gigabit Ethernet  adapter

    D

    Configure 1CIOv 2-port gigabit Ethernet adapter and 1 CFFh combination fibre channel / gigabit Ethernet  adapter


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    A customer wants to boot from an iSCSI SAN with their IBM BladeCenter infrastructure running Microsoft Windows Server 2000.  What is required for the customer to be able to perform this?()
    A

    Fibre Channel Expansion Card for each Blade Server

    B

    cKVM Card for each Blade Server

    C

    iSCSI Expansion Card for each Blade Server

    D

    4Gb Modular Flash Drive


    正确答案: B
    解析: 暂无解析

  • 第13题:

    A banking customer deployed an IBM BladeCenter chassis with one Brocade 8Gb SAN switch module. The customer requires an 8Gb uplink or higher. Which configuration will meet this request?()

    • A、Brocade Enterprise 20-port 8Gb SAN switch module 
    • B、Brocade 20-port 8Gb SAN switch module and Brocade Advanced Performance Monitoring for IBM BladeCenter share 
    • C、Brocade Enterprise 10-port 8Gb SAN switch module 
    • D、Brocade 10-port 8Gb SAN switch module and Brocade Advanced Performance Monitoring for IBM BladeCenter

    正确答案:A

  • 第14题:

    A customer wants to boot from an iSCSI SAN with their IBM BladeCenter infrastructure running Microsoft Windows Server 2000.  What is required for the customer to be able to perform this?()

    • A、Fibre Channel Expansion Card for each Blade Server
    • B、cKVM Card for each Blade Server
    • C、iSCSI Expansion Card for each Blade Server
    • D、4Gb Modular Flash Drive

    正确答案:C

  • 第15题:

    A prospect is considering a BladeCenter H chassis with the Multi-Switch Interconnect Modules. The number of Ethernet ports is important to them. What is the maximum number of Ethernet ports an HS22 blade server can support if the blade does not have any expansion blades attached?()

    • A、8 
    • B、6 
    • C、4 
    • D、2

    正确答案:A

  • 第16题:

    A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch.Which of the following should be mentioned to the customer regarding the NPIV switch?()

    • A、You can not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch 
    • B、Using blade servers with the NPIV switch will require more fibre ports on the external fibre switch 
    • C、Storage devices like Fibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch
    • D、The NPIV switch will count against the number of domains in a fabric

    正确答案:C

  • 第17题:

    A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()

    • A、Configure 2 CFFh combination fibre channel / gigabit Ethernet adapters
    • B、Configure 1 CFFh 2-port fibre channel adapter and 1 CIOv 2-port gigabit Ethernet adapter
    • C、Configure 1 CIOv 2-port fibre channel adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter
    • D、Configure 1 CIOv 2-port gigabit Ethernet adapter and 1 CFFh combination fibre channel / gigabit Ethernet adapter

    正确答案:C

  • 第18题:

    单选题
    A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch.Which of the following should be mentioned to the customer regarding the NPIV switch?()
    A

    You can not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch 

    B

    Using blade servers with the NPIV switch will require more fibre ports on the external fibre switch 

    C

    Storage devices like Fibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch

    D

    The NPIV switch will count against the number of domains in a fabric


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    A customer needs to add three JS22 blade servers. The customer currently has three HS21 Blade servers and one LS41 4-socket Blade Server. Based upon this information,  what additional items does the customer need to purchase? ()
    A

    An IBM BladeCenter H chassis for the JS22 Blade servers

    B

    A concurrent KVM daughter card

    C

    A pair of IBM BladeCenter Power Supplies

    D

    A second Management Module


    正确答案: C
    解析: 暂无解析

  • 第20题:

    单选题
    A project requires a new server to be set up with the ability to automatically fail over its Ethernet connection to a second connection if a network failure occurs. Which of the following provides greatest resiliency?()
    A

    Two switch ports will be needed on a switch,two Ethernet cables will be needed for theserver each connecting to two different Ethernet cards,and one IP address will be needed

    B

    Two switch ports will be needed on two different switches two Ethernet cables will beneeded for the server each connecting to two different Ethernet cards,and one IP address will be needed

    C

    Two switch ports will be needed on two different switches,two Ethernet cables will be needed for the server each connecting to two different Ethernet cards,two different IP addresses will be needed

    D

    One switch port will be needed on one switch,a splitter will be needed to split the connection,two Ethernet cables will be needed for the server each connecting to two different Ethernet cards,and two different IP addresses will be needed


    正确答案: C
    解析: 暂无解析

  • 第21题:

    单选题
    A banking customer deployed an IBM BladeCenter chassis with one Brocade 8Gb SAN switch module. The customer requires an 8Gb uplink or higher. Which configuration will meet this request?()
    A

    Brocade Enterprise 20-port 8Gb SAN switch module 

    B

    Brocade 20-port 8Gb SAN switch module and Brocade Advanced Performance Monitoring for IBM BladeCenter share 

    C

    Brocade Enterprise 10-port 8Gb SAN switch module 

    D

    Brocade 10-port 8Gb SAN switch module and Brocade Advanced Performance Monitoring for IBM BladeCenter


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    Companycom wants to reduce the number of copper, Ethernet adapters on their 4 way p5 570 running AIX 5.3 used in each of the four LPARs. Companycom has one database LPAR, two application LPARs, and one web LPAR. Only the Web LPAR needs to communicate with the outside world. What is the minimum number of Ethernet adapters that should be provided to ensure redundancy and no single point of failure?()
    A

    One single port Ethernet adapter

    B

    Four dual port Ethernet adapters

    C

    Two single port Ethernet adapters

    D

    Eight single port Ethernet adapters


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    A manufacturing customer has an IBM BladeCenter H chassis with four, HX5 with MAX5 4-socket blades installed. Each blade has the optional Fibre Channel Expansion card. The customer wants redundancy and is going to install the following configuration:  (1)two Brocade 20-Port SAN Switch Modules  (2)two Nortel Networks 1/10 GB Uplink ESM  (3)a redundant AMM  What is the minimum number of power supplies needed for this configuration to have full redundancy?()
    A

    4

    B

    3

    C

    2

    D

    8


    正确答案: D