单选题A customer is running Microsoft Windows 2003, Sun Solaris, and IBM AIX with a total capacity of20 TB. This customer needs high availability for e-business applications. The servers are currently connected to two EMC Symmetrix subsystems that are runnin

题目
单选题
A customer is running Microsoft Windows 2003, Sun Solaris, and IBM AIX with a total capacity of20 TB. This customer needs high availability for e-business applications. The servers are currently connected to two EMC Symmetrix subsystems that are running RAID 1. The customer wants to consolidate all storage into an IBM System Storage DS8700. How many Fibre Channel drive sets are needed to satisfy the total capacity for this customer?()
A

8 drive sets of 300 GB drives

B

4 drive sets of 300 GB drives

C

14 drive sets of 146 GB drives

D

18 drive sets of 146 GB drives


相似考题
更多“单选题A customer is running Microsoft Windows 2003, Sun Solaris, and IBM AIX with a total capacity of20 TB. This customer needs high availability for e-business applications. The servers are currently connected to two EMC Symmetrix subsystems that are runnin”相关问题
  • 第1题:

    A customer needs 2 TB of high availability storage for eBusiness applications. Their servers arecurrently connected to two EMC Symmetrix subsystems that are running RAID 1. They want toconsolidate all of the RAID 1 storage into an IBM System Storage DS6800. Which configurationsatisfies these capacity requirements?()

    • A、Two disk drive sets of 300 GB drives
    • B、Four disk drive sets of 146 GB drives
    • C、Eight disk drive sets of 73 GB drives
    • D、Nine disk drive sets of 146 GB drives

    正确答案:D

  • 第2题:

    A pharmaceutical company has a requirement for 8.5 TB of usable storage for a new data center. The customer has multiple host applications running on Solaris, Windows 2003, HP-U/X, Linux, and IBM System i platforms.  Which IBM System Storage DS8000 volume configuration providesthe best performance and highest availability for this customer()

    • A、RAID 3
    • B、RAID 5
    • C、RAID 6
    • D、RAID 10

    正确答案:D

  • 第3题:

    An IBM Business Partner suggests an IBM System Storage DS8000 to a customer with a SAN   that is now configured with an EMC Symmetrix subsystem disk.  The customer wants to determine if new HBAs and software upgrades are needed on the servers if the EMC storage is replaced by the DS8000 What document must be carefully read to help address the customer’s concerns()

    • A、IBM System Storage DS8000: Host Systems Attachment Guide
    • B、DS8000 Interoperability Matrix
    • C、IBM System Storage DS8000: Introduction and Planning Guide
    • D、IBM System Storage Solution Handbook

    正确答案:B

  • 第4题:

    A customer currently buys HP ProLiant servers and EMC storage. The customer has encountered various problems getting certain servers to work with their storage.  Which of the following arguments can the Sales Specialist present to best position IBM? ()

    • A、IBM’s ServerProven program is a reference that assures a customer of compatibility with specific third-party products.
    • B、IBM sells other vendors’ products and will test compatibility with the customer’s products. 
    • C、B IBM’s storage division regularly tests their products with other vendors’ server products.  
    • D、IBM’s server division regularly tests their products with other vendors’ storage products.

    正确答案:A

  • 第5题:

    A space-constrained customer is currently running AIX 5.2 on a number of p650 servers and a pair of new p5-550 servers.  They have four identical new applications each requiring a minimum of seven processors and 96GB of memory.  Which solution would best meet the customer’s requirements?()

    • A、Two p670 servers
    • B、Four p650 servers
    • C、Two p5-570 servers
    • D、Four p5-550 servers

    正确答案:C

  • 第6题:

    A customer is adding a new p5 machine to their environment.  The machine will host several DB2 partitions running AIX 5.2.  They currently have two SAN directors and an IBM ESS.  The SAN design allows for concurrent maintenance.  What is required on each partition to attach to the SAN?()

    • A、A minimum of two HBAs; the customer will need to download SDD
    • B、A minimum of four HBAs; the customer will need to download SDD
    • C、A minimum of two HBAs; the customer will need to configure MPIO
    • D、A minimum of four HBAs; the customer will need to configure MPIO

    正确答案:A

  • 第7题:

    单选题
    A customer plans to install ten Microsoft Windows servers, three Linux servers, and five AIX servers, with two Fibre Channel host bus adapters each as part of an IBM DS8700 implementation. What multipathing driver is required to build a redundant solution?()
    A

    RDAC

    B

    MPIO

    C

    SSPC

    D

    SDDPCM


    正确答案: C
    解析: 暂无解析

  • 第8题:

    单选题
    A customer needs 2 TB of high availability storage for eBusiness applications. Their servers arecurrently connected to two EMC Symmetrix subsystems that are running RAID 1. They want toconsolidate all of the RAID 1 storage into an IBM System Storage DS6800. Which configurationsatisfies these capacity requirements?()
    A

    Two disk drive sets of 300 GB drives

    B

    Four disk drive sets of 146 GB drives

    C

    Eight disk drive sets of 73 GB drives

    D

    Nine disk drive sets of 146 GB drives


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    A customer is running Microsoft Windows 2003, Sun Solaris, and IBM AIX with a total capacity of20 TB. This customer needs high availability for e-business applications. The servers are currently connected to two EMC Symmetrix subsystems that are running RAID 1. The customer wants to consolidate all storage into an IBM System Storage DS8700. How many Fibre Channel drive sets are needed to satisfy the total capacity for this customer?()
    A

    8 drive sets of 300 GB drives

    B

    4 drive sets of 300 GB drives

    C

    14 drive sets of 146 GB drives

    D

    18 drive sets of 146 GB drives


    正确答案: D
    解析: 暂无解析

  • 第10题:

    单选题
    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()
    A

    What are the plans for Disaster Recovery? 

    B

    What are the plans for data migration? 

    C

    Would iSCSI meet your needs? 

    D

    How much space is available in the current storage systems?


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    A customer has an EMC Symmetrix DMX3000 that is at the end of lease. The environment consists of IBM System p, IBM System i, and IBM System z. The customer is evaluating EMC,   HDS, and IBM storage as possible replacements. They are interested in comparing the performance of all three disk subsystems.  Which tool compares performance()
    A

    Capacity Magic

    B

    eConfig

    C

    TPC for Disk

    D

    Disk Magic


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    A pharmaceutical company has a requirement for 8.5 TB of usable storage for a new data center. The customer has multiple host applications running on Solaris, Windows 2003, HP-U/X, Linux, and IBM System i platforms.  Which IBM System Storage DS8000 volume configuration providesthe best performance and highest availability for this customer()
    A

    RAID 3

    B

    RAID 5

    C

    RAID 6

    D

    RAID 10


    正确答案: A
    解析: 暂无解析

  • 第13题:

    A customer is running system management software on one of their Windows xSeries servers, and the software seems to slow down their database application over time.  The customer is running IBM Director in their environment.  Which IBM Director tool can they utilize to guarantee processor time for the different applications and optimize the server performance?()

    • A、Software Rejuvenation
    • B、Capacity Manager
    • C、Capacity Workload Manager
    • D、Aurema Application Workload Manager

    正确答案:D

  • 第14题:

    A customer plans to install ten Microsoft Windows servers, three Linux servers, and five AIX servers, with two Fibre Channel host bus adapters each as part of an IBM DS8700 implementation. What multipathing driver is required to build a redundant solution?()

    • A、RDAC
    • B、MPIO
    • C、SSPC
    • D、SDDPCM

    正确答案:B

  • 第15题:

    In addition to AIX, which of the following operating systems is supported in a pSeries LPAR environment?()

    • A、z/OS
    • B、Linux
    • C、Sun Solaris 9
    • D、Microsoft Windows 2003

    正确答案:B

  • 第16题:

    An IBM Business Partner has sold a DS5020 and new IBM SAN switches to replace a customer EMC storage infrastructure. The customer dissatisfaction has arisen during the installation because according to the DS5020 interoperability matrix, two HP Proliant servers running Exchange have FC HBAs that are not supported. Which of the following is the most probable cause of the customer dissatisfaction()

    • A、The EMC storage specialist has not participated in the TDA meeting
    • B、The FC HBAs are 4 Gbps technology
    • C、The Technical and Delivery Assessment review actions were not executed
    • D、The customer should have checked that the HBAs are supported according to the HP storage interoperability matrix

    正确答案:C

  • 第17题:

    The customer has an older storage array and is looking to migrate data that currently exists onover 100 73 GB FC drives to a new IBM System Storage DS5020. The customer states that theyhave only 3 TB of data and wants to consolidate on to fewer higher capacity drives. There are sixapplication servers running multiple applications and operating systems utilizing the storagesystem. What would be the next step to accurately identify the new storage configuration?()

    • A、initiate a Disk Magic study
    • B、initiate a Capacity Magic study
    • C、runiometer on the current environment
    • D、utilize the IBM Disk capacity planner toolkit

    正确答案:A

  • 第18题:

    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()

    • A、What are Disaster Recoveryplans
    • B、What are plans for datamigration
    • C、What storage system space isavailable
    • D、DoesiSCSI meet the needs

    正确答案:B

  • 第19题:

    单选题
    A customer is adding a new p5 machine to their environment.  The machine will host several DB2 partitions running AIX 5.2.  They currently have two SAN directors and an IBM ESS.  The SAN design allows for concurrent maintenance.  What is required on each partition to attach to the SAN?()
    A

    A minimum of two HBAs; the customer will need to download SDD

    B

    A minimum of four HBAs; the customer will need to download SDD

    C

    A minimum of two HBAs; the customer will need to configure MPIO

    D

    A minimum of four HBAs; the customer will need to configure MPIO


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    An IBM Business Partner suggests an IBM System Storage DS8000 to a customer with a SAN   that is now configured with an EMC Symmetrix subsystem disk.  The customer wants to determine if new HBAs and software upgrades are needed on the servers if the EMC storage is replaced by the DS8000 What document must be carefully read to help address the customer’s concerns()
    A

    IBM System Storage DS8000: Host Systems Attachment Guide

    B

    DS8000 Interoperability Matrix

    C

    IBM System Storage DS8000: Introduction and Planning Guide

    D

    IBM System Storage Solution Handbook


    正确答案: A
    解析: 暂无解析

  • 第21题:

    单选题
    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700. They would like to upgrade and plan for 40 TB capacity. The customer needs to move to a more scalable storage system to include all servers. Which of the following would be most appropriate to ask first?()
    A

    What are Disaster Recoveryplans

    B

    What are plans for datamigration

    C

    What storage system space isavailable

    D

    DoesiSCSI meet the needs


    正确答案: A
    解析: 暂无解析

  • 第22题:

    单选题
    A customer is running business-critical applications on a few SQL servers in their environment.  The customer needs to know if and when the SQL server stops, so the service can be restarted immediately.  Which of the following will accomplish this?()
    A

    Use the Capacity Manager to monitor the processes on the servers.Log the events to the event log and use the resource monitor to restart the SQL process.

    B

    Use the System Availability tool that comes with IBM Director to improve the availability of the SQL applications.

    C

    Use the IBM Director Application PING function to watch the SQL service. When the SQL service goes down, restart the service remotely on the managed server using the software distribution function.

    D

    Utilize Process Management and create a threshold to monitor the SQL process.Create an Event Action Plan and set the task to restart the SQL process when stopped and apply it to the managed SQL servers.


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    An IBM Business Partner has sold a DS5020 and new IBM SAN switches to replace a customer EMC storage infrastructure. The customer dissatisfaction has arisen during the installation because according to the DS5020 interoperability matrix, two HP Proliant servers running Exchange have FC HBAs that are not supported. Which of the following is the most probable cause of the customer dissatisfaction()
    A

    The EMC storage specialist has not participated in the TDA meeting

    B

    The FC HBAs are 4 Gbps technology

    C

    The Technical and Delivery Assessment review actions were not executed

    D

    The customer should have checked that the HBAs are supported according to the HP storage interoperability matrix


    正确答案: D
    解析: 暂无解析

  • 第24题:

    单选题
    The customer has an older storage array and is looking to migrate data that currently exists onover 100 73 GB FC drives to a new IBM System Storage DS5020. The customer states that theyhave only 3 TB of data and wants to consolidate on to fewer higher capacity drives. There are sixapplication servers running multiple applications and operating systems utilizing the storagesystem. What would be the next step to accurately identify the new storage configuration?()
    A

    initiate a Disk Magic study

    B

    initiate a Capacity Magic study

    C

    runiometer on the current environment

    D

    utilize the IBM Disk capacity planner toolkit


    正确答案: C
    解析: 暂无解析