Verify the ISV application runs on AIX 5.2
Power4 to POWER5 upgrades are not supported without a application recompile
Check the placement and size of the boot logical volume and disk space requirements on the S85
AIX 4.3.3 to AIX 5L 5.2 migrations are perfectly compatible so nothing needs to be checked
第1题:
Companycom is migrating from p670 systems running AIX 5.2 to p5 595 systems running AIX 5.3. They will be changing out only the system units. They will re-use the existing 61D drawers and adapters with the new p5 595 systems. What compatibility issue must be considered?()
第2题:
Companycom is migrating their application that was built on AIX 4.3, to a new p5 590 system that is running AIX 5.3. The application was a 32-bit program. What will need to be done with the application to allow it to run on the new system?()
第3题:
Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()
第4题:
A customer has a pSeries that needs to be upgraded from AIX Version 5.1 to AIX Version 5.2. The customer wants to retain /etc/passwd. Which of the following installation types should be used?()
第5题:
Companycom wants to buy a new p5 570 running AIX 5.3. The applications require 4 processors and 8GB of memory. There is a requirement to have a Virtual IO Server. What is the smallest p5 570 that should be sold to this customer?()
第6题:
Increase memory
Add more adapters
Increase both processors and adapters
Increase the number of processors by 20 - 30%
第7题:
Verify the ISV application runs on AIX 5.2
Power4 to POWER5 upgrades are not supported without a application recompile
Check the placement and size of the boot logical volume and disk space requirements on the S85
AIX 4.3.3 to AIX 5L 5.2 migrations are perfectly compatible so nothing needs to be checked
第8题:
Apply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required.
Purchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required.
Verify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262.
Verify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.
第9题:
Upgrade OS to AIX 5.2.
Implement Micro-Partitioning.
Upgrade HMC to support POWER5.
Install Partition Load Manager.
第10题:
Assign the adapter to an IO Hosting partition
Use AIX 5L affinity to move the application from SUSE to AIX
Use AIX 5.3 drivers to install the adapter in the Linux LPAR
Assign the adapter to an AIX 5.3 partition running Linux Affinity
第11题:
Use base media to restore system to AIX 5.1.
Use an alt_disk_install and boot back to the AIX 5.1 rootvg.
Make a mksysb of the original AIX to restore back to the AIX 5.1 level.
Perform the AIX 5.2 upgrade using update_all with the commit option and reject filesets to return to AIX 5.1.
第12题:
IBM pSeries servers support Oracle on both POWER4 and Itanium
AIX has Itanium affinity with any ISV application including Oracle
Oracle and thousands of other ISV applications are already available for AIX on pSeries
IBM Data Migration Services can migrate the HP UNIX operating system to a pSeries solution
第13题:
A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications. The pSeries technical specialist should recommend purchasing which of the following?()
第14题:
Companycom is planning on upgrading from a pSeries S85 running AIX 4.3.3 to a p5 570 with an HMC. The new server will run AIX 5L 5.2. What should be performed prior to the migration?()
第15题:
Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()
第16题:
Companycom has a requirement for an LPAR in their p5 595 to run SUSE Linux. They also require an adapter that is not currently supported in Linux. Which of the following would be the best solution to recommend?()
第17题:
An HP UNIX server customer running Oracle is interested in knowing more about IBM’s future direction because of the uncertainty of HP hardware platforms changing to Itanium. Which of the following advantages should be communicated as a compelling reason to consider a pSeries server solution?()
第18题:
APV, AIX5.2ML4
AIX5.3 or i5/OS
APV, i5/OS, AIX5.3
APV, AIX5.3 or SuSE9
第19题:
Apply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required.
Purchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required.
Verify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262.
Verify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.
第20题:
APV features are not supported for some legacy POWER4 adapters
APV will require the most current maintenance level for AIX 5.2
APV features will require that legacy POWER4 adapters be updated with new microcode
The Virtual IO Server must run AIX 5.3 and the LPARs can run either AIX 5.2 or AIX 5.3
第21题:
Use rsync to synchronize the data across servers.
Use exportvg and importvg to move the data to the target system.
Use NFS to copy the data from the source system to the target system.
Backup the data from the source system and restore to the target system.
第22题:
Increase memory
Add more adapters
Increase both processors and adapters
Increase the number of processors by 20 - 30%
第23题:
Run without recompiling on AIX 5.3
Relink to the 32-bit kernel in order to run the application
Recompile to run on AIX 5.3 because the libraries are in different locations
Recompile 32-bit applications because the compiler flags and versions have changed
第24题:
4 processors 8GB of memory
5 processors 8GB of memory
4 processors 10GB of memory
5 processors 10GB of memory