单选题In order to support Live Partition Mobility (LPM) for a given LPAR between two Power servers, which type of backing device should be chosen for the storage devices presented from the VIO server to the LPAR?()A LUN-backed devicesB File-backed devicesC L

题目
单选题
In order to support Live Partition Mobility (LPM) for a given LPAR between two Power servers, which type of backing device should be chosen for the storage devices presented from the VIO server to the LPAR?()
A

LUN-backed devices

B

File-backed devices

C

Logical volume-backed devices

D

Network Filesystem-backed (NFS) devices


相似考题
更多“单选题In order to support Live Partition Mobility (LPM) for a given LPAR between two Power servers, which type of backing device should be chosen for the storage devices presented from the VIO server to the LPAR?()A LUN-backed devicesB File-backed devicesC L”相关问题
  • 第1题:

    What are two reasons a network administrator would use CDP (Choose two.)()。

    • A、to verify the type of cable interconnecting two devices
    • B、to determine the status of network services on a remote device
    • C、to obtain VLAN information from directly connected switches
    • D、to verify Layer 2 connectivity between two devices when Layer 3 fails
    • E、to obtain the IP address of a connected device in order to telnet to the device
    • F、to determine the status of the routing protocols between directly connected routers

    正确答案:D,E

  • 第2题:

    A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()

    • A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.
    • B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.
    • C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.
    • D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

    正确答案:D

  • 第3题:

    LPAR1 is configured to have the same 2 LUNs virtualized by a redundant pair of VIO servers.  Which command will validate that both storage paths are available?()

    • A、Lspath
    • B、sdd query adapter
    • C、pcmpath query adapter
    • D、datapath query device

    正确答案:A

  • 第4题:

    Best practices would have no single point of failure between mirrored resources. In setting up virtual, internal boot disks for two client LPARs, how would this be accomplished?()

    • A、Have one VIO server with striped disks for all LPARs
    • B、Have one VIO server with mirrored disks for all LPARs
    • C、Have two VIO servers with each LPAR accessing both VIO servers
    • D、Have two VIO servers with each LPAR accessing a different VIO server

    正确答案:C

  • 第5题:

    Company.com has two POWER5 servers. They want the two servers’ virtual Ethernets to appear on the same IP subnet. Which of the following will connect the client virtual Ethernet adapters to the physical Ethernet switch connecting the two servers?()

    • A、Configure a Shared Ethernet Adapter on the Virtual I/O Server.
    • B、Use the same virtual LAN ID on each LPAR.
    • C、Set up IP routing through an LPAR on each system.
    • D、Set up an IP firewall through an LPAR on each system.

    正确答案:A

  • 第6题:

    A customer is configuring Live Partition Mobility on two POWER6-based servers,  Which of the following is required on both the source and the destination VIO servers for the mobile partition to participate in an active partition migration?()

    • A、 IBM Director connection
    • B、 Dynamic LPAR Resource Manager (DLRM)
    • C、 Barrier Synchronization Register Device (BSR)
    • D、 Virtual Asynchronous Services Interface (VASI)

    正确答案:D

  • 第7题:

    单选题
    LPAR1 is configured to have the same 2 LUNs virtualized by a redundant pair of VIO servers. Which command will validate thatboth storage paths are available?()
    A

    lspath

    B

    sdd query adapter

    C

    pcmpath query adapter

    D

    datapath query device


    正确答案: C
    解析: 暂无解析

  • 第8题:

    单选题
    What does the "allow performance information collection" button do in the Hardware Management Console (HMC) GUI? ()
    A

     It allows you to get inter partition reports, or cross partition performance activity.

    B

     It will allow IBM remote technical support to get performance information from the machine.

    C

     It is effective only on POWER6 and when Live Partition Mobility operations are planned.

    D

     It will start standard performance monitoring tools when an LPAR boots up, the output will be saved to the /etc/perf directory by default.


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    What is an advantage of using an HMC rather than IVM for system management?()
    A

    Support for a single VIO Server environment

    B

    Adapters can be dedicated or virtual for each LPAR environment

    C

    Interfaces with Systems Director to manage the Power Systems servers

    D

    Supports multiple Power Systems servers from a single point of control


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    Best practices would have no single point of failure between mirrored resources. In setting up virtual, internal boot disks for two client LPARs, how would this be accomplished?()
    A

    Have one VIO server with striped disks for all LPARs

    B

    Have one VIO server with mirrored disks for all LPARs

    C

    Have two VIO servers with each LPAR accessing both VIO servers

    D

    Have two VIO servers with each LPAR accessing a different VIO server


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    In order to support Live Partition Mobility (LPM) for a given LPAR between two Power servers, which type of backing device should be chosen for the storage devices presented from the VIO server to the LPAR?()
    A

    LUN-backed devices

    B

    File-backed devices

    C

    Logical volume-backed devices

    D

    Network Filesystem-backed (NFS) devices


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()
    A

     Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.

    B

     Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.

    C

     Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.

    D

     Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.


    正确答案: D
    解析: 暂无解析

  • 第13题:

    What are two reasons a network administrator would use CDP?()

    • A、to verify the type of cable interconnecting two devices
    • B、to determine the status of network services on a remote device
    • C、to obtain VLAN information from directly connected switches
    • D、to verify Layer 2 connectivity between two devices when Layer 3 fails
    • E、to obtain the IP address of a connected device in order to telnet to the device
    • F、to determine the status of the routing protocols between directly connected routers

    正确答案:D,E

  • 第14题:

    Which of the following procedures will allow an operator to access an LPAR console session?()

    • A、Open a vterm from the VIO graphical interface to get the partition console.
    • B、Open a vterm from the ASMI graphical interface to get the partition console.
    • C、Start an ssh session to the HMC. Use the vtmenu command to select the desired LPAR.
    • D、Start an ssh session to the VIO. Use the vtmenu command to select the desired LPAR.

    正确答案:C

  • 第15题:

    What does the "allow performance information collection" button do in the Hardware Management Console (HMC) GUI? ()

    • A、 It allows you to get inter partition reports, or cross partition performance activity.
    • B、 It will allow IBM remote technical support to get performance information from the machine.
    • C、 It is effective only on POWER6 and when Live Partition Mobility operations are planned.
    • D、 It will start standard performance monitoring tools when an LPAR boots up, the output will be saved to the /etc/perf directory by default.

    正确答案:A

  • 第16题:

    ompany.com has a Micro-Partitioned p5-570 4-way with six application partitions and two VIO servers. Each VIO server has been allocated 0.5 CPU and the application servers have been allocated 0.4 CPUs. The marketing department wants to deploy a new Web server to support the release of a product. The systems architect has recommended that the Web server will require a whole CPU. Which of the following should the technical specialist suggest to provide the most cost-effective deployment?()

    • A、Remove one application server partition and apply its CPU resources to the Web server.
    • B、Reassign the CPU from one of the VIO servers and create the new partition.
    • C、Add 0.6 CPU to one of the application servers and run the Web service with the application. 
    • D、Reassign a total of 0.4 CPUs from the application servers and create a new partition with awhole CPU for new deployment.

    正确答案:D

  • 第17题:

    Companycom has a Linux LPAR on a p5 570 server. The 3rd party storage subsystem devices are not supported by Linux. How would access be provided to the storage subsystem devices for this Linux LPAR?()

    • A、Daisy chain the unsupported 3rd party storage subsystem devices with the local SCSI disk drive 
    • B、Assuming the 3rd party storage subsystem has AIX support, enable access through a Virtual IO Server 
    • C、Assuming the 3rd party storage subsystem has AIX support, implement the Linux partition within an AIX partition 
    • D、3rd party storage is not an option for p5 570 servers and therefore only IBM disk subsystems can be considered as a solution

    正确答案:B

  • 第18题:

    What is an advantage of using an HMC rather than IVM for system management?()

    • A、Support for a single VIO Server environment
    • B、Adapters can be dedicated or virtual for each LPAR environment
    • C、Interfaces with Systems Director to manage the Power Systems servers
    • D、Supports multiple Power Systems servers from a single point of control

    正确答案:D

  • 第19题:

    单选题
    Which of the following procedures will allow an operator to access an LPAR console session?()
    A

    Open a vterm from the VIO graphical interface to get the partition console.

    B

    Open a vterm from the ASMI graphical interface to get the partition console.

    C

    Start an ssh session to the HMC. Use the vtmenu command to select the desired LPAR.

    D

    Start an ssh session to the VIO. Use the vtmenu command to select the desired LPAR.


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()
    A

    Use shared memory and semaphores to transfer the data to the TSM LPAR

    B

    Provide gigabit Ethernet adapters in each LPAR and run a crossover cable

    C

    Create a Virtual Ethernet between the production server and the TSM LPARs

    D

    Create a Virtual Ethernet between the TSM server LPAR and the non-production LPARs


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    ompany.com has a Micro-Partitioned p5-570 4-way with six application partitions and two VIO servers. Each VIO server has been allocated 0.5 CPU and the application servers have been allocated 0.4 CPUs. The marketing department wants to deploy a new Web server to support the release of a product. The systems architect has recommended that the Web server will require a whole CPU. Which of the following should the technical specialist suggest to provide the most cost-effective deployment?()
    A

    Remove one application server partition and apply its CPU resources to the Web server.

    B

    Reassign the CPU from one of the VIO servers and create the new partition.

    C

    Add 0.6 CPU to one of the application servers and run the Web service with the application. 

    D

    Reassign a total of 0.4 CPUs from the application servers and create a new partition with awhole CPU for new deployment.


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    A customer is configuring Live Partition Mobility on two POWER6-based servers,  Which of the following is required on both the source and the destination VIO servers for the mobile partition to participate in an active partition migration?()
    A

     IBM Director connection

    B

     Dynamic LPAR Resource Manager (DLRM)

    C

     Barrier Synchronization Register Device (BSR)

    D

     Virtual Asynchronous Services Interface (VASI)


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    Company.com has two POWER5 servers. They want the two servers’ virtual Ethernets to appear on the same IP subnet. Which of the following will connect the client virtual Ethernet adapters to the physical Ethernet switch connecting the two servers?()
    A

    Configure a Shared Ethernet Adapter on the Virtual I/O Server.

    B

    Use the same virtual LAN ID on each LPAR.

    C

    Set up IP routing through an LPAR on each system.

    D

    Set up an IP firewall through an LPAR on each system.


    正确答案: B
    解析: 暂无解析

  • 第24题:

    单选题
    Companycom has a Linux LPAR on a p5 570 server. The 3rd party storage subsystem devices are not supported by Linux. How would access be provided to the storage subsystem devices for this Linux LPAR?()
    A

    Daisy chain the unsupported 3rd party storage subsystem devices with the local SCSI disk drive 

    B

    Assuming the 3rd party storage subsystem has AIX support, enable access through a Virtual IO Server 

    C

    Assuming the 3rd party storage subsystem has AIX support, implement the Linux partition within an AIX partition 

    D

    3rd party storage is not an option for p5 570 servers and therefore only IBM disk subsystems can be considered as a solution


    正确答案: D
    解析: 暂无解析