单选题A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools.  What is the minimum PowerVM E

题目
单选题
A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools.  What is the minimum PowerVM Edition which provides this feature?()
A

Basic

B

Express

C

Standard

D

Enterprise


相似考题
更多“单选题A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools.  What is the minimum PowerVM E”相关问题
  • 第1题:

    A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools.  What is the minimum PowerVM Edition which provides this feature?()

    • A、Basic
    • B、Express
    • C、Standard
    • D、Enterprise

    正确答案:C

  • 第2题:

    On a POWER7 processor based server what is the minimum number of cores used by the Hypervisor to run four threads?()

    • A、1
    • B、2
    • C、4
    • D、8

    正确答案:A

  • 第3题:

    A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()

    • A、Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs
    • B、Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.
    • C、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.
    • D、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.

    正确答案:C

  • 第4题:

    A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools. What is the minimum PowerVM Edition which provides this feature?()

    • A、Basic
    • B、Express
    • C、Standard
    • D、Enterprise

    正确答案:C

  • 第5题:

    A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention. Which of the following meets the customer requirement?()

    • A、Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partition maximums to one core. Configure each partition to be capped.
    • B、Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partition maximums to one core. Configure each partition to be uncapped.
    • C、Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partitions to use no more than one core. Configure the HMC scheduler to  dynamically assign processors among the pools over a day.
    • D、Create a shared processor pool for each production partition, with the maximum processor limit set to the  licensing limit for the application in the pool. Assign the development and testing partitions to a processor  pool with a maximum of 1 core. Configure each partition to use uncapped processing.

    正确答案:D

  • 第6题:

    A customer wants to run a Domino e-mail application,a Business Intelligence database,and a batch processing application on Linux.The workloads have different behaviors and do not have peaks at the same time. What is a benefit of running these applications on a Power Systems server instead of running on separate x86 servers?()

    • A、Each Linux application can run in a Workload Partition, reducing the management efforts.
    • B、Total cost of Linux applications on Power Systems is more cost effective than on x86 because of platform licensing.
    • C、Memory cloning can be used on the Power Systems to have a single image of the Linux kernel shared by all partitions.
    • D、Using micro-partitions on Power Systems allow the workloads to share the processing resources, increasing the overall system utilization.

    正确答案:D

  • 第7题:

    单选题
    A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools.  What is the minimum PowerVM Edition which provides this feature?()
    A

    Basic

    B

    Express

    C

    Standard

    D

    Enterprise


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    On a POWER7 processor based server what is the minimum number of cores used by the Hypervisor to run four threads?()
    A

    1

    B

    2

    C

    4

    D

    8


    正确答案: C
    解析: 暂无解析

  • 第9题:

    单选题
    A customer wants to run DB2 on a Power 780 with uncapped partitions. They have licensed DB2 for 32 of the 64 active cores, and will use it in multiple partitions.   How can the customer ensure that the number of licenses purchased for DB2 is not exceeded?()
    A

    Create a 32-core shared processor pool for the DB2 partitions.

    B

    Limit the number of virtual processors on each DB2 partition to 32.

    C

    Use the IBM License Metric Tool to dynamically manage DB2 usage in the partitions.

    D

    Set the ‘Desired Processing Units’ in each DB2 partition profile so that the sum of all partitions equals 32.


    正确答案: D
    解析: 暂无解析

  • 第10题:

    单选题
    A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()
    A

     PowerVM Lx86

    B

     PowerVM Express Edition

    C

     PowerVM Standard Edition

    D

     PowerVM Enterprise Edition


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    What is an advantage of using an HMC rather than IVM for system management?()
    A

    Support for a single VIO Server environment

    B

    Adapters can be dedicated or virtual for each LPAR environment

    C

    Interfaces with Systems Director to manage the Power Systems servers

    D

    Supports multiple Power Systems servers from a single point of control


    正确答案: C
    解析: 暂无解析

  • 第12题:

    单选题
    A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()
    A

    Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs

    B

    Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.

    C

    Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.

    D

    Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.


    正确答案: A
    解析: 暂无解析

  • 第13题:

    Multicore can be described as which of the following?()

    • A、Multiple processors dedicated for individual tasks.
    • B、Multiple cores on a single die.
    • C、Multiple cores on multiple dies.
    • D、Multiple processors working together to increase processing power.

    正确答案:B

  • 第14题:

    A customer is evaluating PowerVM and VMware to run a data warehouse application. Which feature of PowerVM should be highlighted as a differentiator?()

    • A、PowerVM offers partition mobility.
    • B、PowerVM can virtualize network and SAN resources.
    • C、PowerVM supports multiple operating systems running concurrently.
    • D、PowerVM allows an LPAR to use activated cores and memory without limitation.

    正确答案:D

  • 第15题:

    Which POWER6 virtualization technology is the minimum to enable multiple shared processor pool functionality?() 

    • A、PowerHA Standard Edition
    • B、PowerVM Standard Edition
    • C、Power6 Management Edition
    • D、Power6 Virtualization Edition

    正确答案:B

  • 第16题:

    A customer wants to run DB2 on a Power 780 with uncapped partitions. They have licensed DB2 for 32 of the 64 active cores, and will use it in multiple partitions.   How can the customer ensure that the number of licenses purchased for DB2 is not exceeded?()

    • A、Create a 32-core shared processor pool for the DB2 partitions.
    • B、Limit the number of virtual processors on each DB2 partition to 32.
    • C、Use the IBM License Metric Tool to dynamically manage DB2 usage in the partitions.
    • D、Set the ‘Desired Processing Units’ in each DB2 partition profile so that the sum of all partitions equals 32.

    正确答案:A

  • 第17题:

    What is an advantage of using an HMC rather than IVM for system management?()

    • A、Support for a single VIO Server environment
    • B、Adapters can be dedicated or virtual for each LPAR environment
    • C、Interfaces with Systems Director to manage the Power Systems servers
    • D、Supports multiple Power Systems servers from a single point of control

    正确答案:D

  • 第18题:

    单选题
    Due to a recent change in government regulations, Company.com needs to create two  independent but synchronized copies of their data. These copies must be contained in separate storage device a minimum of 100 km apart. The customer has capacity in two systems that meet the criteria, one with SSA disk and the other is FAStT.  What facility can be used to manage this issue?()
    A

     Two independent copies of the data can be created and synchronized using the HACMP/XD://HAGeo

    B

     The existing disks can be incorporated a single storage unit using the optional product HACMP/XD://PPRC

    C

     AIX can create a mirrored logical volume across the two systems that would be accessible from either system

    D

     AIX can use the multi path IO subsystem to spread the information across the devices and keep the copies separated


    正确答案: D
    解析: 暂无解析

  • 第19题:

    单选题
    A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention. Which of the following meets the customer requirement?()
    A

    Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partition maximums to one core. Configure each partition to be capped.

    B

    Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partition maximums to one core. Configure each partition to be uncapped.

    C

    Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partitions to use no more than one core. Configure the HMC scheduler to  dynamically assign processors among the pools over a day.

    D

    Create a shared processor pool for each production partition, with the maximum processor limit set to the  licensing limit for the application in the pool. Assign the development and testing partitions to a processor  pool with a maximum of 1 core. Configure each partition to use uncapped processing.


    正确答案: C
    解析: 暂无解析

  • 第20题:

    单选题
    A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools. What is the minimum PowerVM Edition which provides this feature?()
    A

    Basic

    B

    Express

    C

    Standard

    D

    Enterprise


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    A customer would like to consolidate multiple database workloads to a single server to reduce TCO. What is the effect of PowerVM on TCO?()
    A

    Reduces SAN cost

    B

    Reduces network cost

    C

    Reduces administration costs

    D

    Reduces software licensing cost


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    A customer is evaluating PowerVM and VMware to run a data warehouse application. Which feature of PowerVM should be highlighted as a differentiator?()
    A

    PowerVM offers partition mobility.

    B

    PowerVM can virtualize network and SAN resources.

    C

    PowerVM supports multiple operating systems running concurrently.

    D

    PowerVM allows an LPAR to use activated cores and memory without limitation.


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    A customer wants to run a Domino e-mail application,a Business Intelligence database,and a batch processing application on Linux.The workloads have different behaviors and do not have peaks at the same time. What is a benefit of running these applications on a Power Systems server instead of running on separate x86 servers?()
    A

    Each Linux application can run in a Workload Partition, reducing the management efforts.

    B

    Total cost of Linux applications on Power Systems is more cost effective than on x86 because of platform licensing.

    C

    Memory cloning can be used on the Power Systems to have a single image of the Linux kernel shared by all partitions.

    D

    Using micro-partitions on Power Systems allow the workloads to share the processing resources, increasing the overall system utilization.


    正确答案: B
    解析: 暂无解析

  • 第24题:

    单选题
    What is the maximum number of Cisco Catalyst 3750 Series Switches that can be united into a single manageable unit using the Cisco StackWise technology?()
    A

    9

    B

    3

    C

    12

    D

    6


    正确答案: A