A test case normally consists of a unique identifier, requirement references from a design specification, events,aseries of stepsto follow, input,output, actual result, and() 。A.bug B.expected result C.test report D.traceability matrix

题目
A test case normally consists of a unique identifier, requirement references from a design specification, events,aseries of stepsto follow, input,output, actual result, and() 。

A.bug
B.expected result
C.test report
D.traceability matrix

相似考题

1.● Information systems design is defined as those tasks that focus on the specification of a detailed computer-based solution. Typically, there are four systems design tasks for in-house development.1) The first task is to specify (71) , which defines the technologies to be used by one, more, or all information systems in terms of their data, processes, interfaces, and network components. This task is accomplished by analyzing the data models and process models that are initially created during requirements analysis.2) The next systems design task is to develop the (72) . The purpose of this task is to prepare technical design specifications for a database that will be adaptable to future requirements and expansion.3) Once the database prototype has been built, the systems designer can work closely with system users to develop input, output and dialogue specifications. The (73) must be specified to ensure that the outputs are not lost, misrouted, misused, or incomplete.4) The fourth design task involves packaging all the specifications from the previous design tasks into a set of specifications that will guide the (74) activities during the following phases of the systems development methodology.Finally, we should (75) and update the project plan accordingly. The key deliverable should include a detailed plan for the construction phase that should follow.(71)A. an application architectureB. a distributed systemC. a system scopeD. a system physical model(72)A. database design specificationsB. database organization decisionsC. data structure specificationsD. data distribution decisions(73)A. format and layoutB. transaction detailsC. additional instructionsD. internal controls(74)A. system administrator’sB. system analyst’sC. computer programmer’sD. system designer’s(75)A. adjust the project scheduleB. reevaluate project feasibilityC. evaluate vendor proposalsD. select the best vendor proposal

更多“A test case normally consists of a unique identifier, requirement references from a design specification, events,aseries of stepsto follow, input,output, actual result, and() 。”相关问题
  • 第1题:

    ● Which statement about the preliminary design stage of a software development project is true? (75) .

    (75)

    A.The preliminary design is an internal document used only by programmers

    B.The preliminary design is the result of mapping product requirements info software and hardware functions

    C.The preliminary design of the product comes from the requirement specification

    D.The developers produce the preliminary design by defining the software structure in enough detail to permit coding


    正确答案:C

  • 第2题:

    Program( )describes program&39;s objectives, desired output, input data required, processing requirement, and documentation.

    A.specification B.flowchart C.structure D.address


    正确答案:C

  • 第3题:

    When steering by hand,which of the following may be a functional input to the steering gear as a result of turning the wheel ________.

    A.Non-follow-up

    B.Rudder adjustment

    C.Weather adjustment

    D.All the above may be activated


    正确答案:A

  • 第4题:

    Program( )describes program's objectives,desired output,input data required,processing requirement,and documentation.

    A.specification
    B.flowchart
    C.structure
    D.address

    答案:A
    解析:

  • 第5题:

    下列选项中属于过滤流Filter Input Stream的子类的是()。

    • A、Data Input Stream
    • B、Data Output Stream
    • C、Print Stream
    • D、Buffered Output Stream

    正确答案:A

  • 第6题:

    Which design phase service component includes the development and documentation of the test case or cases used to verify that a deployed infrastructure meets operational, functional, and interface requirements? Select exactly 1 answer(s) from the following:()。

    • A、Implementation Plan
    • B、Business Plan
    • C、Staging Plan
    • D、Detailed Design Development
    • E、Systems Acceptance Test Plan Development

    正确答案:E

  • 第7题:

    A system administrator used the savevg command to back up the testvg each night. There is now a requirement to exclude the /test/static filesystem from the backup. How can this be accomplished?()

    • A、Use the -X flag on the savevg command
    • B、Put an entry in the /etc/exclude.testvg file
    • C、Remove the /test/static entries from the /vgdata/testvg.data file
    • D、Use the touch command to create /test/static/.exclude before using savevg

    正确答案:B

  • 第8题:

    单选题
    The test of a towing vessel’s steering gear control system includes each item EXCEPT().
    A

    a test from the alternative power supply,if installed

    B

    timing the movement of the rudder from hard over to hard over

    C

    verification that the rudder angle indicator shows the actual position of the rudder(s)

    D

    visual inspection of the steering linkage


    正确答案: C
    解析: 暂无解析

  • 第9题:

    多选题
    Which of the following information will be gathered by the SQL Test Case Builder for the problems pertaining to SQL-related problems?()
    A

    ADR diagnostic files

    B

    all the optimizer statistics

    C

    initialization parameter settings

    D

    PL/SQL functions,procedures,and packages

    E

    the table and index definitions and actual data


    正确答案: A,C
    解析: 暂无解析

  • 第10题:

    单选题
    You are developing a Windows Presentation Foundation (WPF) application. You are implementing a test strategy for the application. You need to ensure that the test class can repeat user input. From which base class should the test class inherit?()
    A

     AutomationElementIdentifier

    B

     AutomationPeer

    C

     Keyboard

    D

     UICues


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    As the designated rudder angle is being achieved, as a result of the original command input, the steering gear follow-up mechanism is()
    A

    in motion, providing a null input

    B

    not in motion, thus providing a null input

    C

    in motion, providing an input to place the main pump on maximum stroke

    D

    in motion, providing an input to place the main pump at null stroke


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    You are designing a test plan for an existing Windows Azure .NET 4 application.  Method calls return incorrect results for certain input parameters.   You need to recommend an approach for debugging the method calls.  What should you recommend?()
    A

     Attach the remote debugger to the application.

    B

     Use the Microsoft Visual Studio 2010 Test Manager tool.

    C

     Use IntelliTrace to collect only eventsfrom the application.

    D

     Use IntelliTrace to collect events and call information from the application.


    正确答案: C
    解析: 暂无解析

  • 第13题:

    please draw the transistor level schematic of a cmos 2 input AND gate and

    explain which input has faster response for output rising edge.(less delay

    time)。(威盛笔试题circuit design-beijing-03.11.09)


    正确答案:
               

  • 第14题:

    ● Basically, a computer consists of five components: (71), memory, storage, input device and output device.

    (71)

    A.keyboard

    B.mouse

    C.monitor

    D.CPU


    正确答案:D

  • 第15题:

    Program(73)describes program's objectives, desired output, input data required, processing requirement, and documentation.

    A.specification
    B.flowchart
    C.structure
    D.address

    答案:C
    解析:
    程序规格说明书描述了程序的目标、预期的输出、所需的输入数据、处理的要求和文档。

  • 第16题:

    Software system test plan needs to be compiled in( )phase。
    软件系统测试计划需要在( )阶段编制。

    A.requirement analysis
    需求分析
    B.Outline design
    概要设计
    C.detailed design
    详细设计
    D.Coding phase
    编码阶段

    答案:A
    解析:
    软件测试计划作为软件项目计划的子计划,在项目启动初期是必须进行规划的。在软件开发中,软件质量日益受到重视,测试过程也从一个相对独立的步骤越来越紧密地被嵌套在软件的整个生命周期中。

  • 第17题:

    You are designing a test plan for an existing Windows Azure .NET 4 application.  Method calls return incorrect results for certain input parameters.   You need to recommend an approach for debugging the method calls.  What should you recommend?()  

    • A、 Attach the remote debugger to the application.
    • B、 Use the Microsoft Visual Studio 2010 Test Manager tool.
    • C、 Use IntelliTrace to collect only eventsfrom the application.
    • D、 Use IntelliTrace to collect events and call information from the application.

    正确答案:D

  • 第18题:

    Which design phase service component consists of developing a detailed, site-specific plan for implementing a new technology system or solution? Select exactly 1 answer(s) from the following:()。

    • A、Detailed Design Development
    • B、Systems Acceptance Test Plan Development
    • C、Staging Plan
    • D、Implementation Plan Development
    • E、Project Kick-off

    正确答案:D

  • 第19题:

    在自动驾驶的诊断页面中有哪些方式?

    • A、INPUT,OUTPUT,DIAGNOSTICS
    • B、INPUT,REPORT,DIAGNOSTICS
    • C、REPORT OUTPUT DIAGNOSTICS
    • D、REPORT,INPUT,OUTPUT

    正确答案:D

  • 第20题:

    单选题
    Which conditions will normally cause a SART to operate in the active mode?()
    A

    It will respond only to interrogation by 9-Ghz radar signals

    B

    A SART will normally respond to interrogation from a searching vessel's radar if the radar antenna is at least 15 meters high

    C

    A SART will normally respond to interrogation from a searching aircraft's radar if the radar's output power is at least 10,000 watts and the aircraft is at a height of 3000 feet and within 30 nautical miles

    D

    All of the above


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    The configuration of a Web Services Security management (WSSM) Partner allows for the specification of XSL mapping rules. What is the input and output of these XSL mapping rules?()
    A

    The input to the XSL mapping rules of a WSSM Partner is the binary security token as received on the Web Service request. The output of the mapping rules is a new security token ready for use by the Web Service application. 

    B

    The input to the XSL mapping rules of a WSSM Partner is an STSUniveralUser XML document created from the security token received on the Web Service request. The output of the mapping rules is an arbitrary collection of attributes that will be made available to the Web Services application. 

    C

    The input to the XSL mapping rules of a WSSM Partner is an STSUniveralUser XML document created from the security token received on the Web Service request. The output of the mapping rules is a new STSUniversalUser XML document that represents the security token required by the application. 

    D

    The input to the XSL mapping rules of a WSSM Partner is an STSUniveralUser XML document created from the security token received on the Web Service request. The output of the mapping rules is an IBM Tivoli Access Manager for e-business credential that will be used to authorize the partner's access to the Web Service application.


    正确答案: A
    解析: 暂无解析

  • 第22题:

    单选题
    Which implement phase service component consists of preparing for migration,excuting a network migration plan,and completing migration test cases?()
    A

    staging and system migration

    B

    post implementation support handoff meeting

    C

    detailed design development

    D

    staff training

    E

    migration plan development


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    Operational amplifiers, used primarily in analog circuits, are characterized by()
    A

    high input impedance, high gain and low output impedance

    B

    high input impedance, high gain and high output impedance

    C

    low input impedance, low gain and high output impedance

    D

    low input impedance, high gain and low output impedance