第1题:
PDM includes four types of dependencies or precedence relationships…(73),the initiation of the successor activity,depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
第2题:
● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.
(75)
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
第3题:
第4题:
PDM includes four types of dependencies or precedence relationships: ...(18). The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
第5题:
You are signing on a deck officer,who will be designated as one of the GMDSS operators,before sailing foreign.Which statement is TRUE ________.
A.He/she must have an STCW certificate endorsed as“Valid for Service on Vessels Operating in the GMDSS System”
B.He/she must present either an FCC-issued license or a Coast Guard-issued license
C.You must consult the“List of Qualifications”on the reverse of his/her FCC-issued license
D.His/her Merchant Mariners Document must have an added endorsement as “Radio Electronics Officer”
第6题: