单选题A customer has purchased an IBM BladeCenter H chassis and needs the following servers:  --Two HS21 blade servers each with 8GB memory and 2 drives   --Two HS21 blade servers each with 24GB memory and 2 drives   --Two LS21 blade servers each with 2GB me

题目
单选题
A customer has purchased an IBM BladeCenter H chassis and needs the following servers:  --Two HS21 blade servers each with 8GB memory and 2 drives   --Two HS21 blade servers each with 24GB memory and 2 drives   --Two LS21 blade servers each with 2GB memory and 2 Hot-Swap SCSI drives   How many total server bays will be required for this configuration?()
A

6

B

8

C

10

D

12


相似考题
更多“单选题A customer has purchased an IBM BladeCenter H chassis and needs the following servers:  --Two HS21 blade servers each with 8GB memory and 2 drives   --Two HS21 blade servers each with 24GB memory and 2 drives   --Two LS21 blade servers each with 2GB me”相关问题
  • 第1题:

    Which of the following would be an advantage to using a blade(刀片) server(服务器) as opposed to a rack(机架式) mount server?()

    • A、 Blade servers allow for internal tape drives
    • B、 Blade servers offer more rack density
    • C、 Blade servers are typically faster
    • D、 Blade servers allow for more RAM

    正确答案:B

  • 第2题:

    A customer needs to add three JS22 blade servers. The customer currently has three HS21 Blade servers and one LS41 4-socket Blade Server. Based upon this information,  what additional items does the customer need to purchase? ()

    • A、An IBM BladeCenter H chassis for the JS22 Blade servers
    • B、A concurrent KVM daughter card
    • C、A pair of IBM BladeCenter Power Supplies
    • D、A second Management Module

    正确答案:C

  • 第3题:

    A customer wants to boot from an iSCSI SAN with their IBM BladeCenter infrastructure running Microsoft Windows Server 2000.  What is required for the customer to be able to perform this?()

    • A、Fibre Channel Expansion Card for each Blade Server
    • B、cKVM Card for each Blade Server
    • C、iSCSI Expansion Card for each Blade Server
    • D、4Gb Modular Flash Drive

    正确答案:C

  • 第4题:

    Company.com has two POWER5 servers. They want the two servers’ virtual Ethernets to appear on the same IP subnet. Which of the following will connect the client virtual Ethernet adapters to the physical Ethernet switch connecting the two servers?()

    • A、Configure a Shared Ethernet Adapter on the Virtual I/O Server.
    • B、Use the same virtual LAN ID on each LPAR.
    • C、Set up IP routing through an LPAR on each system.
    • D、Set up an IP firewall through an LPAR on each system.

    正确答案:A

  • 第5题:

    Which of the following would be an advantage to using a blade server as opposed to a rack mount server?()

    • A、Blade servers allow for internal tape drives
    • B、Blade servers offer more rack density
    • C、Blade servers are typically faster
    • D、Blade servers allow for more RAM

    正确答案:B

  • 第6题:

    单选题
    A customer needs to add three JS22 blade servers. The customer currently has three HS21 Blade servers and one LS41 4-socket Blade Server. Based upon this information,  what additional items does the customer need to purchase? ()
    A

    An IBM BladeCenter H chassis for the JS22 Blade servers

    B

    A concurrent KVM daughter card

    C

    A pair of IBM BladeCenter Power Supplies

    D

    A second Management Module


    正确答案: C
    解析: 暂无解析

  • 第7题:

    单选题
    Which of the following Blade servers offer hot swap internal hard drives?()
    A

    HS21

    B

    HS22

    C

    HS22V

    D

    HX5


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    A customer has purchased an IBM BladeCenter H chassis and needs the following servers:  --Two HS21 blade servers each with 8GB memory and 2 drives   --Two HS21 blade servers each with 24GB memory and 2 drives   --Two LS21 blade servers each with 2GB memory and 2 Hot-Swap SCSI drives   How many total server bays will be required for this configuration?()
    A

    6

    B

    8

    C

    10

    D

    12


    正确答案: A
    解析: 暂无解析

  • 第9题:

    单选题
    There is a power outage and all servers are shut down properly by the uninterruptible power supply(UPS) software. When one of the servers starts up it displays a logical drive failed error. This server has two processors,16GB of memory, and a RAID 5 array with 10 drives.  Which of the following is the MOST likely cause?()
    A

     A failed RAID controller

    B

     Two failed processors

    C

     Two failed sticks of memory

    D

     Two failed drives


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    You are designing a DHCP strategy to meet the business and technical requirements.  What should you do?()
    A

     Install one DHCP server in each branch office and one DHCP server in Los Angeles.

    B

     Install one DHCP server in each branch office and two DHCP servers in Los Angeles.

    C

     Install two DHCP servers in each branch office and one DHCP server in Los Angeles.

    D

     Install two DHCP servers in each branch office and two DHCP servers in Los Angeles.


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    A customer wants to boot from an iSCSI SAN with their IBM BladeCenter infrastructure running Microsoft Windows Server 2000.  What is required for the customer to be able to perform this?()
    A

    Fibre Channel Expansion Card for each Blade Server

    B

    cKVM Card for each Blade Server

    C

    iSCSI Expansion Card for each Blade Server

    D

    4Gb Modular Flash Drive


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    Company.com has two POWER5 servers. They want the two servers’ virtual Ethernets to appear on the same IP subnet. Which of the following will connect the client virtual Ethernet adapters to the physical Ethernet switch connecting the two servers?()
    A

    Configure a Shared Ethernet Adapter on the Virtual I/O Server.

    B

    Use the same virtual LAN ID on each LPAR.

    C

    Set up IP routing through an LPAR on each system.

    D

    Set up an IP firewall through an LPAR on each system.


    正确答案: B
    解析: 暂无解析

  • 第13题:

    There is a power outage and all servers are shut down properly by the uninterruptible power supply(UPS) software. When one of the servers starts up it displays a logical drive failed error. This server has two processors,16GB of memory, and a RAID 5 array with 10 drives.  Which of the following is the MOST likely cause?()

    • A、 A failed RAID controller
    • B、 Two failed processors
    • C、 Two failed sticks of memory
    • D、 Two failed drives

    正确答案:D

  • 第14题:

    A customer needs to deploy ten dual processor Xeon servers.  Six servers will be running Linux and Apache, and the other four will be Citrix presentation servers.  The customer’s main concerns are the rack space and the option to have SATA drives.  The maximum memory required is 8GB.  Which of the following options will provide the best price and performance?()

    • A、Ten x306’s with internal SATA drives
    • B、Five x346’s with internal SATA drives and VMWare ESX Server
    • C、Five x366’s partitioned into two VMs each with VMWare ESX Server
    • D、Ten x336’s with internal SATA drives

    正确答案:D

  • 第15题:

    A customer has purchased an IBM BladeCenter H chassis and needs the following servers:  --Two HS21 blade servers each with 8GB memory and 2 drives   --Two HS21 blade servers each with 24GB memory and 2 drives   --Two LS21 blade servers each with 2GB memory and 2 Hot-Swap SCSI drives   How many total server bays will be required for this configuration?()

    • A、6
    • B、8
    • C、10
    • D、12

    正确答案:C

  • 第16题:

    A banking customer has the following requirements for an IBM BladeCenter solution with high speed fibre channel: (1)four 4-socket Microsoft SQL servers with two hot swap SAS drives  (2)two physical Microsoft Active Directory Servers  (3)twenty-two physical Citrix servers  (4)three physical Web servers (5)one physical vCenter server   (6)eight vSphere hosts  Which configuration minimally satisfies these requirements?()

    • A、Three IBMBladeCenter S chassis, three Brocade Fibre modules, six Ethernet modules
    • B、Three IBMBladeCenter E chassis, three Brocade Fibre modules, six Ethernet modules
    • C、Four IBMBladeCenter H chassis, four QLogic Fibre Channel modules, eight Ethernet modules
    • D、Three IBMBladeCenter H chassis, three QLogic Fibre Channel modules, six Ethernet modules

    正确答案:D

  • 第17题:

    单选题
    A customer plans to install ten Microsoft Windows servers, three Linux servers, and five AIX servers, with two Fibre Channel host bus adapters each as part of an IBM DS8700 implementation. What multipathing driver is required to build a redundant solution?()
    A

    RDAC

    B

    MPIO

    C

    SSPC

    D

    SDDPCM


    正确答案: C
    解析: 暂无解析

  • 第18题:

    单选题
    A customer has two different applications, each requiring two processors.  They are evaluating the following three alternatives:   1) Two p5-520s each with two processors and 4GB memory   2) One partitioned p5-550 with four processors and 8GB memory   3) One partitioned p5-570 with four processors and 8GB memory   All three solutions will work.  However, when helping the customer decide which solution is best for their environment, the pSeries technical specialist should convey which of the following pieces of information?()
    A

    A

    B

    B

    C

    C

    D

    D


    正确答案: A
    解析: 暂无解析

  • 第19题:

    单选题
    A banking customer has the following requirements for an IBM BladeCenter solution with high speed fibre channel: (1)four 4-socket Microsoft SQL servers with two hot swap SAS drives  (2)two physical Microsoft Active Directory Servers  (3)twenty-two physical Citrix servers  (4)three physical Web servers (5)one physical vCenter server   (6)eight vSphere hosts  Which configuration minimally satisfies these requirements?()
    A

    Three IBMBladeCenter S chassis, three Brocade Fibre modules, six Ethernet modules

    B

    Three IBMBladeCenter E chassis, three Brocade Fibre modules, six Ethernet modules

    C

    Four IBMBladeCenter H chassis, four QLogic Fibre Channel modules, eight Ethernet modules

    D

    Three IBMBladeCenter H chassis, three QLogic Fibre Channel modules, six Ethernet modules


    正确答案: C
    解析: 暂无解析

  • 第20题:

    单选题
    A customer wants to boot from SAN with their IBM BladeCenter infrastructure.  What is required for the customer to be able to perform this? ()
    A

    4GB Modular Flash Drive for each Blade Server and Dual 15.8GB 2.5 Solid State Drive for each Blade Server 

    B

    Cisco Intelligent Gb Ethernet Switch Module and IBM BladeCenter Copper Pass-thru Module 

    C

    Fibre Channel Expansion Card for each Blade Server and Fibre Channel SAN Switch Module 

    D

    Cisco Intelligent Gb Ethernet Switch Module and Dual 15.8GB 2.5 Solid State Drive for each Blade Server


    正确答案: C
    解析: 暂无解析

  • 第21题:

    单选题
    Which of the following would be an advantage to using a blade(刀片) server(服务器) as opposed to a rack(机架式) mount server?()
    A

     Blade servers allow for internal tape drives

    B

     Blade servers offer more rack density

    C

     Blade servers are typically faster

    D

     Blade servers allow for more RAM


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    A manufacturing customer has an IBM BladeCenter H chassis with four, HX5 with MAX5 4-socket blades installed. Each blade has the optional Fibre Channel Expansion card. The customer wants redundancy and is going to install the following configuration:  (1)two Brocade 20-Port SAN Switch Modules  (2)two Nortel Networks 1/10 GB Uplink ESM  (3)a redundant AMM  What is the minimum number of power supplies needed for this configuration to have full redundancy?()
    A

    4

    B

    3

    C

    2

    D

    8


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    A medical customer has a rack with four BladeCenter H chassis that have been operating normally for several months. After installing a new rack of servers in the data center, the system administrator notices the blowers in the BladeCenters have increased their speed. Which of the following caused this problem? ()
    A

    The room temperature has reached 23C (73.4F). 

    B

    A Blade within the chassis has been shut down. 

    C

    The ambient temperature in the data center has increased 

    D

    One of the additional System X servers in the BladeCenter rack has failed.


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    A customer needs to deploy ten dual processor Xeon servers.  Six servers will be running Linux and Apache, and the other four will be Citrix presentation servers.  The customer’s main concerns are the rack space and the option to have SATA drives.  The maximum memory required is 8GB.  Which of the following options will provide the best price and performance?()
    A

    Ten x306’s with internal SATA drives

    B

    Five x346’s with internal SATA drives and VMWare ESX Server

    C

    Five x366’s partitioned into two VMs each with VMWare ESX Server

    D

    Ten x336’s with internal SATA drives


    正确答案: C
    解析: 暂无解析