单选题A Power 770 customer needs to add additional I/O adapters.  There is no room for the cards, so an I/O drawer must be added. What resource will help identify supported I/O drawers and the maximum number of drawers permitted per loop?()A I/O Planning Gui

题目
单选题
A Power 770 customer needs to add additional I/O adapters.  There is no room for the cards, so an I/O drawer must be added. What resource will help identify supported I/O drawers and the maximum number of drawers permitted per loop?()
A

I/O Planning Guide

B

Power Systems data sheet

C

Power Systems Facts and Features

D

Run FLRT to recommend I/O features


相似考题
更多“单选题A Power 770 customer needs to add additional I/O adapters.  There is no room for the cards, so an I/O drawer must be added. What resource will help identify supported I/O drawers and the maximum number of drawers permitted per loop?()A I/O Planning Gui”相关问题
  • 第1题:

    An HP customer would like to discuss IBM system advantages. Their current system platform is a partitioned HP rp8400. Which of the following pSeries systems and advantages should be discussed?()

    • A、p630. Maximum partitions, maximum storage, I/O bus speed
    • B、p670. Maximum partitions, maximum memory, number of I/O slots
    • C、p655. Maximum number of CPUs, processor speed, number of I/O slots
    • D、p690. Maximum number of CPUs, peak system bandwidth, peak I/O bandwidth

    正确答案:B

  • 第2题:

    The storage specialist needs to prepare an IBM System Storage DS8800 proposal including 64 host ports. The offer needs to meet the lowest possible price.  What is the minimum number of I/O Enclosure Pairs PCI-E for this configuration()

    • A、one I/O enclosure pair PCI-E
    • B、two I/O enclosure pairs PCI-E
    • C、four I/O-enclosure pairs PCI-E
    • D、eight I/O-enclosure pairs PCI-E

    正确答案:B

  • 第3题:

    The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors.  The system is a test system to run AIX 5.2.  The customer has stated a preference for internal disks for the boot devices.  The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()

    • A、It will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.
    • B、It has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.
    • C、It is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.
    • D、It can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.

    正确答案:B

  • 第4题:

    A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750. Which action allows the most efficient use of existing equipment?()

    • A、Populate the Power 750 first then add a GX+ adapter to support PCI-X andPCIe I/O drawer loops.
    • B、Populate the Power 750 first then add 2 GX+ adapters to support PCI-X andPCIe I/O drawer loops.
    • C、Populate the Power 750 first then add a GX++ adapter to support PCI-X andPCIe I/O drawer loops.
    • D、Populate the Power 750 first then add GX+ and GX++ adapters to support PCI-X andPCIe I/O drawer  loops.

    正确答案:D

  • 第5题:

    Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()

    • A、Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adapters
    • B、Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cards
    • C、Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after reboot
    • D、Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure

    正确答案:D

  • 第6题:

    单选题
    Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()
    A

    Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adapters

    B

    Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cards

    C

    Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after reboot

    D

    Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure


    正确答案: B
    解析: 暂无解析

  • 第7题:

    单选题
    When considering migrating a POWER6 server with PCI-X and PCIe adapters to a Power 720, which statement is true?()
    A

    PCIe adapters are supported only in I/O drawers

    B

    PCI-X adapters are supported in both the CEC and in I/O drawers

    C

    PCI-X adapters are supported in the CEC; PCIe adapters are supported in 12X I/O drawers

    D

    PCIe adapters are supported in the CEC; PCI-X adapters are supported in 12X I/O drawers


    正确答案: D
    解析: 暂无解析

  • 第8题:

    单选题
    A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached One 4-port 1Gbps IVE adapter PowerVM Standard Edition. They need to add a GX++ adapter and cable it to an I/O drawer. Which of the following must also be ordered?()
    A

    A second IVE adapter

    B

    A second processor card

    C

    PowerVM Enterprise Edition

    D

    An additional cable-management arm


    正确答案: B
    解析: 暂无解析

  • 第9题:

    单选题
    An HP customer would like to discuss IBM system advantages. Their current system platform is a partitioned HP rp8400. Which of the following pSeries systems and advantages should be discussed?()
    A

    p630. Maximum partitions, maximum storage, I/O bus speed

    B

    p670. Maximum partitions, maximum memory, number of I/O slots

    C

    p655. Maximum number of CPUs, processor speed, number of I/O slots

    D

    p690. Maximum number of CPUs, peak system bandwidth, peak I/O bandwidth


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()
    A

    Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs

    B

    Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.

    C

    Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.

    D

    Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    A customer would like to buy a new Power 750 and attach 2 PCIe I/O drawers. What is the minimum configuration which will support this?()
    A

    One processor card and one GX+ expansion card

    B

    Two processor cards and one GX++ expansion card

    C

    One processor card, one GX+ expansion card, and one GX++ expansion card

    D

    Two processor cards, one GX+ expansion card, and one GX++ expansion card


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors.  The system is a test system to run AIX 5.2.  The customer has stated a preference for internal disks for the boot devices.  The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()
    A

    It will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.

    B

    It has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.

    C

    It is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.

    D

    It can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.


    正确答案: A
    解析: 暂无解析

  • 第13题:

    A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()

    • A、Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs
    • B、Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.
    • C、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.
    • D、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.

    正确答案:C

  • 第14题:

    Which of the following configuration is valid for expansion drawers on a Power 750 with 2 processor board sinstalled?()

    • A、3 PCI-e I/O drawers and 1 PCI-X I/O drawer
    • B、4 PCI-e I/O drawers and 4 RIO-2 I/O drawers
    • C、2 PCI-e I/O drawers and 4 PCI-x I/O drawers
    • D、4 PCI-e I/O drawers and 2 PCI-X I/O drawers

    正确答案:C

  • 第15题:

    A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer. Which of the following must also be ordered?()

    • A、A second IVE adapter
    • B、A second processor card
    • C、PowerVM Enterprise Edition
    • D、An additional cable-management arm

    正确答案:B

  • 第16题:

    A Power 770 customer needs to add additional I/O adapters.  There is no room for the cards, so an I/O drawer must be added. What resource will help identify supported I/O drawers and the maximum number of drawers permitted per loop?()

    • A、I/O Planning Guide
    • B、Power Systems data sheet
    • C、Power Systems Facts and Features
    • D、Run FLRT to recommend I/O features

    正确答案:C

  • 第17题:

    A customer is upgrading from a 16-core POWER6 570 with two enclosures to a 16-core Power 770 with only one enclosure. There are 22 PCI-X adapters and 19 PCIe adapters spread across the current CECs and I/O drawers. How many and what kind of drawers are needed to connect these adapters?()

    • A、2 PCI-X drawers and 2 PCIe drawers
    • B、3 PCI-X drawers and 4 PCIe drawers
    • C、4 PCI-X drawers and 3 PCIe drawers
    • D、4 PCI-X drawers and 2 PCIe drawers

    正确答案:D

  • 第18题:

    单选题
    A Power 770 customer needs to add additional I/O adapters.  There is no room for the cards, so an I/O drawer must be added. What resource will help identify supported I/O drawers and the maximum number of drawers permitted per loop?()
    A

    I/O Planning Guide

    B

    Power Systems data sheet

    C

    Power Systems Facts and Features

    D

    Run FLRT to recommend I/O features


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    A customer is upgrading from a 16-core POWER6 570 with two enclosures to a 16-core Power 770 with only one enclosure. There are 22 PCI-X adapters and 19 PCIe adapters spread across the current CECs and I/O drawers. How many and what kind of drawers are needed to connect these adapters?()
    A

    2 PCI-X drawers and 2 PCIe drawers

    B

    3 PCI-X drawers and 4 PCIe drawers

    C

    4 PCI-X drawers and 3 PCIe drawers

    D

    4 PCI-X drawers and 2 PCIe drawers


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750. Which action allows the most efficient use of existing equipment?()
    A

    Populate the Power 750 first then add a GX+ adapter to support PCI-X and PCIe I/O drawer loops.

    B

    Populate the Power 750 first then add 2 GX+ adapters to support PCI-X and PCIe I/O drawer loops.

    C

    Populate the Power 750 first then add a GX++ adapter to support PCI-X and PCIe I/O drawer loops.

    D

    Populate the Power 750 first then add GX+ and GX++ adapters to support PCI-X and PCIe I/O drawer loops.


    正确答案: A
    解析: 暂无解析

  • 第21题:

    单选题
    Which of the following configuration is valid for expansion drawers on a Power 750 with 2 processor board sinstalled?()
    A

    3 PCI-e I/O drawers and 1 PCI-X I/O drawer

    B

    4 PCI-e I/O drawers and 4 RIO-2 I/O drawers

    C

    2 PCI-e I/O drawers and 4 PCI-x I/O drawers

    D

    4 PCI-e I/O drawers and 2 PCI-X I/O drawers


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    The storage specialist needs to prepare an IBM System Storage DS8800 proposal including 64 host ports. The offer needs to meet the lowest possible price.  What is the minimum number of I/O Enclosure Pairs PCI-E for this configuration()
    A

    one I/O enclosure pair PCI-E

    B

    two I/O enclosure pairs PCI-E

    C

    four I/O-enclosure pairs PCI-E

    D

    eight I/O-enclosure pairs PCI-E


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    When doing capacity planning for the Virtual I/O Server,what is the most important  consideration?()
    A

    The I/O workload needs of the client LPARs

    B

    The processing requirements of the client LPARs

    C

    The memory requirements of the client LPARs

    D

    The virtual Ethernet requirements between client LPARs


    正确答案: A