Twelve 4-way p655 nodes and add more as needed
Six 8-way p655 nodes and add more as needed
Six 4-way p655 nodes with four processors CoD on each node in case of growth
Three 8-way p655 nodes with eight processors CoD on each node in case of growth
第1题:
A customer recently installed new SAN with an IBM System Storage DS8300 and several open systems servers to address a need for storage consolidation and still provide good response time. They have asked the Business Partner technical representative for the most complete IBM product that would allow them to do performance reporting of the new SAN environment. What is the best solution()
第2题:
The pSeries technical specialist is designing a two LPAR p5-570 with eight total processors. The system is a test system to run AIX 5.2. The customer has stated a preference for internal disks for the boot devices. The customer has said they may later need to run three or four LPARs without increasing the number of processors. What should the pSeries technical specialist tell the customer about the ability of the p5-570 to meet their requirements?()
第3题:
The pSeries technical specialist is discussing a proposed solution for a commercial application that contains the following options: p670, p690, and p5-570. The customer asks why a p655 was not considered as a solution. The customer’s requirements include the following: ? Eight 1.5 or 1.7GHz processors ? 64GB memory ? 12 fibre adapters ? 11 network adapters ? An estimated 25% growth in the next year What is the most appropriate response to the customer?()
第4题:
The account team is putting together a very complex solution for the customer. During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified. What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()
第5题:
Is there a need for a PKI Management System?
Is there a need for end-to-end encryption?
Do they currently have a Kerberos domain in place?
Which clients are installed on their desktops -- SSH, Telnet or both?
第6题:
The p655 is much more expensive than the other solutions.
The p655 would be at full capacity and would have no room for the growth.
The p655 is an HPC system and should never be used in a commercial situation.
The p655 does not support more than 20 adapters so could not accommodate the requirements.
第7题:
Twelve 4-way p655 nodes and add more as needed
Six 8-way p655 nodes and add more as needed
Six 4-way p655 nodes with four processors CoD on each node in case of growth
Three 8-way p655 nodes with eight processors CoD on each node in case of growth
第8题:
A
B
C
D
第9题:
IBM CPW
IBM rPerf
SPECint_rate2006
IDEAS International RPE2
第10题:
Use eConfig to configure and validate each pSeries and p5 system.
Engage Advanced Technical Support to review any outstanding technical issues.
Confirm with the customer that the solution design meets their requirements.
Perform a Pre-Install Solution Assurance Review to validate required power requirements.
第11题:
Begin with a dual DP x445 and scale in the same chassis
Begin with a dual MP x445 and scale in the same chassis
Begin with a dual DP x445 and scale out in an extra chassis
Begin with a dual MP x365 and scale to a different machine
第12题:
p650
p5-570
Two p630s
p5-570 Express
第13题:
A customer is putting together a high-performance computing cluster of p655 nodes. They need a total of 48 processors and want to get the best performance possible out of those systems. They are evaluating four options and have asked the pSeries technical specialist to recommend which one would provide the best performance based on total rPerf. Their workload may grow over time. Which of the following should the pSeries technical specialist recommend?()
第14题:
When designing a single tier AIX database solution for a customer, what other technical specialist would be most instrumental in putting together a total solution and why?()
第15题:
A customer is looking for a reliable well-performing, cost-effective solution to a growing commercial workload. Initially, they want to run 12 UDB partitions, each of which would need two processors and 8GB of memory. They are looking at the p655 and want to start with three LPARS on each p655 node using a total of four nodes. Each LPAR would need at least 4 x 6239 fibre cards and 2 x 5706 2-port 10/100/1000 Ethernet cards. At a later date, they want to add an additional LPAR to each node to expand to a total of 16 UDB partitions. Which of the following major limitations of this solution should be mentioned to the customer?()
第16题:
Due to the pricing of MP processors, a customer is evaluating DP processors. They have current budget constraints and do not want to discard obsolete hardware after a scaling step. It is calculated that two processors will meet their immediate needs. Their projected growth indicates they will need more than four processors. Which of the following recommendations will provide the best path for growth at the lowest cost?()
第17题:
xSeries specialist,as the customer may have some Intel-based systems.
Hardware customer engineer,as they will be installing the entire solution.
Services specialist,as they can provide education recommendations for the entire solution.
Storage specialist,as the customer may need disk to store the data and tape to backup the data.
第18题:
Disk Magic
TPC for Data
CLARiiON Procedure Generator
System Storage Interoperability Center
第19题:
Ask the customer to confirm which option is best for their environment.
Order the fibre channel option and purchase a converter later if necessary.
Order both SCSI and fibre channel adapters to cover both potential options.
Inform the customer that fibre channel was selected for performance reasons.
第20题:
p655 4-way nodes
p655 8-way nodes
p5-570 4-way nodes
p5-570 8-way nodes
第21题:
The p655 supports only two LPARs.
The p655 supports only four LPARs.
There are not enough available slots for three LPARs.
There are not enough available slots for four LPARs.
第22题:
rPerf
ROLTP
SPECfp
SPECint
第23题:
CSM
PSSP
GPFS
HACMP
第24题:
It will require additional SCSI adapters and I/O drawers or external disks to support more than two LPARs.
It has sufficient built-in SCSI controllers and disk enclosures to support four total LPARs by only adding the necessary additional disks.
It is unable to use internal disks for LPARs and therefore additional adapters I/O drawers or external disks must be used to support all LPARs.
It can support six LPARs with internal disks but will require special features, cables and an adapter to support the additional LPARs with internal disks.