单选题A customer has a p650 on order and plans to put it in a current OEM rack.  They are concerned that the p650 power supply may demand more current than the OEM PDU can provide.  Which planning guide specification would provide the necessary requirements?

题目
单选题
A customer has a p650 on order and plans to put it in a current OEM rack.  They are concerned that the p650 power supply may demand more current than the OEM PDU can provide.  Which planning guide specification would provide the necessary requirements?()
A

Voltage

B

Frequency

C

Power Source Loading (max)

D

Power Source Loading (typical)


相似考题
更多“单选题A customer has a p650 on order and plans to put it in a current OEM rack.  They are concerned that the p650 power supply may demand more current than the OEM PDU can provide.  Which planning guide specification would provide the necessary requirements?”相关问题
  • 第1题:

    A customer wants to install a pSeries system into an OEM rack.  What critical information is provided in the Site and Hardware Planning Information manual?()

    • A、System dimensions and weight, system power and cooling requirements, and list of supported OEM racks
    • B、System dimensions and weight, list of supported OEM racks, and requirements for installing IBM systems into OEM racks
    • C、System performance specs, system power and cooling requirements, and requirements for installing IBM systems into OEM racks
    • D、System dimensions and weight, system power and cooling requirements, and requirements for installingIBM systems into OEM racks

    正确答案:D

  • 第2题:

    A customer is ordering a new p650 server to be placed into an existing OEM 42U 19-inch rack containing only two p630 servers.  This is the first p650 in the enterprise.  What is the most important question that the pSeries technical specialist should ask the customer before the order is placed?()

    • A、Have the PDU requirements been met?
    • B、Are there sufficient KVM connections?
    • C、Is there sufficient service clearance?
    • D、Is there sufficient space in the existing rack?

    正确答案:A

  • 第3题:

    A customer plans to order several new pSeries systems and is concerned that the additional heat load may overwhelm the current air-handling system.  How might the pSeries technical specialist aid the customer in addressing their concern?()

    • A、Direct the customer to the Installation Guide for each system to identify the power requirements.
    • B、Direct the customer to engage their site personnel to ensure the proper power connectors are provided to support the systems.
    • C、Direct the customer to the Site and Hardware Planning Information and review the system requirements for each new pSeries system.
    • D、Direct the customer to the Site and Hardware Planning Information to confirm that enough space is available in the rack to allow for proper airflow.

    正确答案:C

  • 第4题:

    A company has recently placed an order for a POWER4+ p650 server.   Their facilities manager has approached the pSeries technical specialist to gather information on the correct power receptacle for thenew server.   They have requested a picture of the power cord plug to show to their electrician.  Where would the pSeries technical specialist find the required information?()

    • A、Sales Manual
    • B、Announcement Letter
    • C、POWER4+ p650 Specification Sheet
    • D、Site and Hardware Planning Information Manual

    正确答案:D

  • 第5题:

    Companycom is moving their application to a p5 590 and at the same time moving to a new version of the application. The customer knows only about the resource requirements of the old version. Which of the following is the best method to migrate their application to POWER5?()

    • A、Add CPU and memory COD so they have room to grow if required
    • B、Make the server configuration twice as large as the current requirement
    • C、Configure the server for the current capacity requirements
    • D、Make the server configuration a little larger than the current capacity requirements

    正确答案:A

  • 第6题:

    单选题
    A company has recently placed an order for a POWER4+ p650 server.   Their facilities manager has approached the pSeries technical specialist to gather information on the correct power receptacle for thenew server.   They have requested a picture of the power cord plug to show to their electrician.  Where would the pSeries technical specialist find the required information?()
    A

    Sales Manual

    B

    Announcement Letter

    C

    POWER4+ p650 Specification Sheet

    D

    Site and Hardware Planning Information Manual


    正确答案: A
    解析: 暂无解析

  • 第7题:

    单选题
    A customer has a p650 on order and plans to put it in a current OEM rack.  They are concerned that the p650 power supply may demand more current than the OEM PDU can provide.  Which planning guide specification would provide the necessary requirements?()
    A

    Voltage

    B

    Frequency

    C

    Power Source Loading (max)

    D

    Power Source Loading (typical)


    正确答案: D
    解析: 暂无解析

  • 第8题:

    单选题
    A customer plans to order several new pSeries systems and is concerned that the additional heat load may overwhelm the current air-handling system.  How might the pSeries technical specialist aid the customer in addressing their concern?()
    A

    Direct the customer to the Installation Guide for each system to identify the power requirements.

    B

    Direct the customer to engage their site personnel to ensure the proper power connectors are provided to support the systems.

    C

    Direct the customer to the Site and Hardware Planning Information and review the system requirements for each new pSeries system.

    D

    Direct the customer to the Site and Hardware Planning Information to confirm that enough space is available in the rack to allow for proper airflow.


    正确答案: A
    解析: 暂无解析

  • 第9题:

    单选题
    Why would you use WebLogic Diagnostics Framework (WLDF) instead of Oracle Enterprise Manager (OEM) ()
    A

     WLDF has better performance than OEM 

    B

     my organization already has a solution for unified management and monitoring; we need to supplement that with some specific WLS-related capabilities

    C

     OEM is not certified with latest version of WLS

    D

     OEM is really focused on the database tier, is not meant to address JEE management and monitoring


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A customer has an 8-way p650 running an application for about 200 users.  In the past, the requiredamount of memory and processors has increased proportionally to the number of new users.  The customer plans to increase users by 10% each year for the next three years.  Next year, a database will be added to the workload to support the users directly rather than being on a separate machine. What is the most likely result of this projected growth?()
    A

    Disk usage will increase in proportion to memory.

    B

    The new database will demand much more memory.

    C

    Memory demand will increase 10% for the next year.

    D

    Processor demand will increase about 10% for the next year.


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    Companycom is moving their application to a p5 590 and at the same time moving to a new version of the application. The customer knows only about the resource requirements of the old version. Which of the following is the best method to migrate their application to POWER5?()
    A

    Add CPU and memory COD so they have room to grow if required

    B

    Make the server configuration twice as large as the current requirement

    C

    Configure the server for the current capacity requirements

    D

    Make the server configuration a little larger than the current capacity requirements


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    A customer has ordered a rack, a p650, two p630s, and two p615s.  During a conversation on installation planning, the pSeries technical specialist recognizes that the customer expects the rack to arrive as one unit.  However, the specialist knows that the p650 will be racked, but the other systems will arrive separately.  In fact, the other systems are CSU (Customer Set Up). Why should the specialist immediately inform the customer that additional racking is the customer’s responsibility?()
    A

    Because additional systems would require more power receptacles

    B

    Because the customer may need to do additional facilities planning

    C

    Because the customer needs additional funding to cover the services

    D

    Because postponing the eventual discussion will likely lead to customer dissatisfaction


    正确答案: A
    解析: 暂无解析

  • 第13题:

    Which of the following would be the BEST location to research current physical layout?()

    • A、Remote management software
    • B、Rack diagrams
    • C、OEM documentation
    • D、Pre-installation plans

    正确答案:B

  • 第14题:

    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()

    • A、What are the plans for Disaster Recovery? 
    • B、What are the plans for data migration? 
    • C、Would iSCSI meet your needs? 
    • D、How much space is available in the current storage systems?

    正确答案:B

  • 第15题:

    A space-constrained customer is currently running AIX 5.2 on a number of p650 servers and a pair of new p5-550 servers.  They have four identical new applications each requiring a minimum of seven processors and 96GB of memory.  Which solution would best meet the customer’s requirements?()

    • A、Two p670 servers
    • B、Four p650 servers
    • C、Two p5-570 servers
    • D、Four p5-550 servers

    正确答案:C

  • 第16题:

    A customer has several small AIX applications that are expected to grow over the next several years.  The biggest challenge facing the customer is determining the growth rate of the applications and the I/T requirements needed to support the growth.  They are also concerned about the under-utilization of their IT resources.  What should the pSeries technical specialist recommend to address this challenge?()

    • A、Install a p615 per application.
    • B、Install a p650 with AIX 5.2 and dynamic LPAR and CUoD.
    • C、Install the appropriate solution once the requirements are understood.
    • D、Install a POWER5 system with AIX 5.3, Advanced POWER Virtualization, and CoD.

    正确答案:D

  • 第17题:

    单选题
    A customer server has the maximum local storage installed. The customer plans to share this new storage with other servers. Which of the following provides that server additional storage?()
    A

    Add External Storage via EXP3000

    B

    Replace current storage with more dense drives

    C

    Add External Storage via SAN

    D

    Add storage expansion blade


    正确答案: D
    解析: 暂无解析

  • 第18题:

    单选题
    A space-constrained customer is currently running AIX 5.2 on a number of p650 servers and a pair of new p5-550 servers.  They have four identical new applications each requiring a minimum of seven processors and 96GB of memory.  Which solution would best meet the customer’s requirements?()
    A

    Two p670 servers

    B

    Four p650 servers

    C

    Two p5-570 servers

    D

    Four p5-550 servers


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    Which of the following would provide the BEST reference of normal server performance for a company’s environment?()
    A

     OEM website

    B

     Software logs

    C

     Baseline documentation

    D

     Pre-installation plans


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    A customer wants to install a pSeries system into an OEM rack.  What critical information is provided in the Site and Hardware Planning Information manual?()
    A

    System dimensions and weight, system power and cooling requirements, and list of supported OEM racks

    B

    System dimensions and weight, list of supported OEM racks, and requirements for installing IBM systems into OEM racks

    C

    System performance specs, system power and cooling requirements, and requirements for installing IBM systems into OEM racks

    D

    System dimensions and weight, system power and cooling requirements, and requirements for installingIBM systems into OEM racks


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A customer is ordering a new p650 server to be placed into an existing OEM 42U 19-inch rack containing only two p630 servers.  This is the first p650 in the enterprise.  What is the most important question that the pSeries technical specialist should ask the customer before the order is placed?()
    A

    Have the PDU requirements been met?

    B

    Are there sufficient KVM connections?

    C

    Is there sufficient service clearance?

    D

    Is there sufficient space in the existing rack?


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()
    A

    What are the plans for Disaster Recovery? 

    B

    What are the plans for data migration? 

    C

    Would iSCSI meet your needs? 

    D

    How much space is available in the current storage systems?


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    A customer wants to know what version of DirectX the current workstation has installed. Which of the following command line tools would the customer use?()
    A

    edit

    B

    systeminfo

    C

    gpedit.msc

    D

    dxdiag


    正确答案: B
    解析: 暂无解析

  • 第24题:

    单选题
    A customer has several small AIX applications that are expected to grow over the next several years.  The biggest challenge facing the customer is determining the growth rate of the applications and the I/T requirements needed to support the growth.  They are also concerned about the under-utilization of their IT resources.  What should the pSeries technical specialist recommend to address this challenge?()
    A

    Install a p615 per application.

    B

    Install a p650 with AIX 5.2 and dynamic LPAR and CUoD.

    C

    Install the appropriate solution once the requirements are understood.

    D

    Install a POWER5 system with AIX 5.3, Advanced POWER Virtualization, and CoD.


    正确答案: C
    解析: 暂无解析