单选题A customer wants to upgrade their existing 6-way p650 to an 8-way.  The installed inventory shows the p650 as only a 4-way.  What should the pSeries technical specialist do in order to best correct IBMinventory records? ()A Submit an RPO-MES to add the

题目
单选题
A customer wants to upgrade their existing 6-way p650 to an 8-way.  The installed inventory shows the p650 as only a 4-way.  What should the pSeries technical specialist do in order to best correct IBMinventory records? ()
A

Submit an RPO-MES to add the missing 2-way processor card.

B

Submit an MES order to add the missing 2-way processor card.

C

Request VPD from the customer and then submit an RPO-MES request.

D

Request VPD from the customer and then submit an MES order to add the missing 2-way processor card.


相似考题
参考答案和解析
正确答案: D
解析: 暂无解析
更多“单选题A customer wants to upgrade their existing 6-way p650 to an 8-way.  The installed inventory shows the p650 as only a 4-way.  What should the pSeries technical specialist do in order to best correct IBMinventory records? ()A Submit an RPO-MES to add the”相关问题
  • 第1题:

    A customer is ordering a new p650 server to be placed into an existing OEM 42U 19-inch rack containing only two p630 servers.  This is the first p650 in the enterprise.  What is the most important question that the pSeries technical specialist should ask the customer before the order is placed?()

    • A、Have the PDU requirements been met?
    • B、Are there sufficient KVM connections?
    • C、Is there sufficient service clearance?
    • D、Is there sufficient space in the existing rack?

    正确答案:A

  • 第2题:

    A customer wants to upgrade their existing 6-way p650 to an 8-way.  The installed inventory shows the p650 as only a 4-way.  What should the pSeries technical specialist do in order to best correct IBMinventory records? ()

    • A、Submit an RPO-MES to add the missing 2-way processor card.
    • B、Submit an MES order to add the missing 2-way processor card.
    • C、Request VPD from the customer and then submit an RPO-MES request.
    • D、Request VPD from the customer and then submit an MES order to add the missing 2-way processor card.

    正确答案:C

  • 第3题:

    The pSeries technical specialist has been invited to a briefing on the latest POWER technology as a representative of their team.  What should the specialist offer to do upon return from class in order to best prepare the rest of the team for the introduction of the new technology?()

    • A、Archive the materials in the team’s library.
    • B、Act as the sole technical resource for the team.
    • C、Summarize the information and make it available to the team.
    • D、Evaluate the class and recommend attendance to other team members.

    正确答案:C

  • 第4题:

    A customer is ready to order a pSeries solution.  However, the pSeries technical specialist is unsure whether the customer preferred the fibre channel or the external SCSI disk attachment option.  What is the most appropriate action for the specialist to take next?()

    • A、Ask the customer to confirm which option is best for their environment.
    • B、Order the fibre channel option and purchase a converter later if necessary.
    • C、Order both SCSI and fibre channel adapters to cover both potential options.
    • D、Inform the customer that fibre channel was selected for performance reasons.

    正确答案:A

  • 第5题:

    The pSeries technical specialist is concerned that the installed inventory for a p670 does not match what the customer says is installed.  The specialist discovers that the customer has never updated their VPD.  Which of the following HMC applications is used to gather the current VPD information?()

    • A、Service Processor
    • B、Service Director
    • C、Inventory Scout Services
    • D、Service Focal Point

    正确答案:C

  • 第6题:

    A company has recently placed an order for a POWER4+ p650 server.   Their facilities manager has approached the pSeries technical specialist to gather information on the correct power receptacle for thenew server.   They have requested a picture of the power cord plug to show to their electrician.  Where would the pSeries technical specialist find the required information?()

    • A、Sales Manual
    • B、Announcement Letter
    • C、POWER4+ p650 Specification Sheet
    • D、Site and Hardware Planning Information Manual

    正确答案:D

  • 第7题:

    单选题
    Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()
    A

    Include a new HMC in the order to connect to the p5 595

    B

    Include a pair of new HMCs in the order to connect to the p5 595

    C

    Include a media set for POWER5 HMC in the order to upgrade one of the existing HMC’s to POWER5 capabilities

    D

    Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC to  POWER5 capabilities Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC? To POWER5 capabilities


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    The pSeries technical specialist has been invited to a briefing on the latest POWER technology as a representative of their team.  What should the specialist offer to do upon return from class in order to best prepare the rest of the team for the introduction of the new technology?()
    A

    Archive the materials in the team’s library.

    B

    Act as the sole technical resource for the team.

    C

    Summarize the information and make it available to the team.

    D

    Evaluate the class and recommend attendance to other team members.


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    A company has recently placed an order for a POWER4+ p650 server.   Their facilities manager has approached the pSeries technical specialist to gather information on the correct power receptacle for thenew server.   They have requested a picture of the power cord plug to show to their electrician.  Where would the pSeries technical specialist find the required information?()
    A

    Sales Manual

    B

    Announcement Letter

    C

    POWER4+ p650 Specification Sheet

    D

    Site and Hardware Planning Information Manual


    正确答案: A
    解析: 暂无解析

  • 第10题:

    单选题
    A customer with p615, p630 and p650 pSeries servers installed and running AIX is considering Linux as an additional environment. Which Linux capabilities can the pSeries Sales Specialist present as choices that are available to enhance the existing systems?()
    A

    Linux will be restricted to the p650 system, as it is not supported on the p630.

    B

    The customer can run Linux on all the existing systems with or without the presence of AIX.

    C

    Linux can run in LPARs on the existing systems but Linux will require the presence of AIX in at least one LPAR.

    D

    Linux can be installed on all existing systems but will require the AIX Linux Affinity libraries to boot the systems and run Linux.


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    A customer wants to upgrade their existing 6-way p650 to an 8-way.  The installed inventory shows the p650 as only a 4-way.  What should the pSeries technical specialist do in order to best correct IBMinventory records? ()
    A

    Submit an RPO-MES to add the missing 2-way processor card.

    B

    Submit an MES order to add the missing 2-way processor card.

    C

    Request VPD from the customer and then submit an RPO-MES request.

    D

    Request VPD from the customer and then submit an MES order to add the missing 2-way processor card.


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    A customer has ordered a rack, a p650, two p630s, and two p615s.  During a conversation on installation planning, the pSeries technical specialist recognizes that the customer expects the rack to arrive as one unit.  However, the specialist knows that the p650 will be racked, but the other systems will arrive separately.  In fact, the other systems are CSU (Customer Set Up). Why should the specialist immediately inform the customer that additional racking is the customer’s responsibility?()
    A

    Because additional systems would require more power receptacles

    B

    Because the customer may need to do additional facilities planning

    C

    Because the customer needs additional funding to cover the services

    D

    Because postponing the eventual discussion will likely lead to customer dissatisfaction


    正确答案: A
    解析: 暂无解析

  • 第13题:

    A customer wants to upgrade an existing pSeries system.  In addition to retrieving the IBM configuration records, what else should be done to ensure an accurate upgrade quote is provided?()

    • A、Request that the pSeries technical specialist provide the discount percentage to the customer.
    • B、Run both eConfig and PCRS6000 to ensure that both configurators provide the same upgrade quote.
    • C、Confirm with the customer that the installed inventory accurately reflects what is actually installed.
    • D、Provide options to the customer so they can choose the most appropriate upgrade for their environment.

    正确答案:C

  • 第14题:

    A customer is having problems after an AIX version upgrade from 5.2 to 5.3.  Which of the following should the pSeries technical specialist recommend that the customer call?()

    • A、IBM Techline
    • B、IBM Supportline
    • C、IBM Software Distribution
    • D、IBM Hardware Support

    正确答案:B

  • 第15题:

    A customer with p615, p630 and p650 pSeries servers installed and running AIX is considering Linux as an additional environment. Which Linux capabilities can the pSeries Sales Specialist present as choices that are available to enhance the existing systems?()

    • A、Linux will be restricted to the p650 system, as it is not supported on the p630.
    • B、The customer can run Linux on all the existing systems with or without the presence of AIX.
    • C、Linux can run in LPARs on the existing systems but Linux will require the presence of AIX in at least one LPAR.
    • D、Linux can be installed on all existing systems but will require the AIX Linux Affinity libraries to boot the systems and run Linux.

    正确答案:B

  • 第16题:

    Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()

    • A、Include a new HMC in the order to connect to the p5 595
    • B、Include a pair of new HMCs in the order to connect to the p5 595
    • C、Include a media set for POWER5 HMC in the order to upgrade one of the existing HMC’s to POWER5 capabilities
    • D、Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC to  POWER5 capabilities Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC? To POWER5 capabilities

    正确答案:B

  • 第17题:

    A customer currently has five partitioned POWER4 systems and is adding new systems.  When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()

    • A、Order a new HMC to support the p5 system.
    • B、Attach the new p5 system to the existing HMC.
    • C、Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.
    • D、Do nothing.  This system does not require an HMC.

    正确答案:A

  • 第18题:

    单选题
    A customer asks the pSeries technical specialist to recommend which remote access (SSH or Telnet) method to use.  What question should the customer be asked to best determine the proper recommendation?()
    A

    Is there a need for a PKI Management System?

    B

    Is there a need for end-to-end encryption?

    C

    Do they currently have a Kerberos domain in place?

    D

    Which clients are installed on their desktops -- SSH, Telnet or both?


    正确答案: D
    解析: 暂无解析

  • 第19题:

    单选题
    The pSeries technical specialist is concerned that the installed inventory for a p670 does not match what the customer says is installed.  The specialist discovers that the customer has never updated their VPD.  Which of the following HMC applications is used to gather the current VPD information?()
    A

    Service Processor

    B

    Service Director

    C

    Inventory Scout Services

    D

    Service Focal Point


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    A customer is having problems after an AIX version upgrade from 5.2 to 5.3.  Which of the following should the pSeries technical specialist recommend that the customer call?()
    A

    IBM Techline

    B

    IBM Supportline

    C

    IBM Software Distribution

    D

    IBM Hardware Support


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    A customer is looking for a low-cost pSeries solution.  The pSeries technical specialist is recommending several p650 Express Configurations.  When reviewing the options with the customer, the pSeries technical specialist should emphasize which of the following limitations?()
    A

    Some Express Configurations limit the amount of maximum memory at order time.

    B

    The customer must meet minimum system requirements to obtain Express Configuration pricing. 

    C

    The Express Configurations offer less than the maximum number of processors.

    D

    The Express Configurations are only offered through the QuickShip Program.


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    A customer wants to upgrade an existing pSeries system.  In addition to retrieving the IBM configuration records, what else should be done to ensure an accurate upgrade quote is provided?()
    A

    Request that the pSeries technical specialist provide the discount percentage to the customer.

    B

    Run both eConfig and PCRS6000 to ensure that both configurators provide the same upgrade quote.

    C

    Confirm with the customer that the installed inventory accurately reflects what is actually installed.

    D

    Provide options to the customer so they can choose the most appropriate upgrade for their environment.


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    A customer is ordering a new p650 server to be placed into an existing OEM 42U 19-inch rack containing only two p630 servers.  This is the first p650 in the enterprise.  What is the most important question that the pSeries technical specialist should ask the customer before the order is placed?()
    A

    Have the PDU requirements been met?

    B

    Are there sufficient KVM connections?

    C

    Is there sufficient service clearance?

    D

    Is there sufficient space in the existing rack?


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    The customer has recently installed a pSeries p5-570 with EMC attached disk storage.  After installation, the customer complained that the disk access appeared to be too slow.  How should the pSeries technical specialist best assist the customer?()
    A

    Recommend the customer call EMC.

    B

    Recommend the customer call IBM hardware support.

    C

    Recommend the customer contact SupportLine.

    D

    Recommend the customer re-creates the volume groups.


    正确答案: D
    解析: 暂无解析