单选题A customer is purchasing an IBM System Storage DS8700. What is the most important first step for the installation?()A verify configurationB conduct pre-install TDAC complete physical planningD verify the solution meets requirements

题目
单选题
A customer is purchasing an IBM System Storage DS8700. What is the most important first step for the installation?()
A

verify configuration

B

conduct pre-install TDA

C

complete physical planning

D

verify the solution meets requirements


相似考题
更多“单选题A customer is purchasing an IBM System Storage DS8700. What is the most important first step for the installation?()A verify configurationB conduct pre-install TDAC complete physical planningD verify the solution meets requirements”相关问题
  • 第1题:

    A customer is interested in purchasing a new IBM System Storage DS8000 solution to consolidateolder ESS and F20 storage systems. What should be done first, prior to final proposaldevelopment?()

    • A、perform a Disk Magic study 
    • B、review eConfig with a technical specialist 
    • C、confirm that the customer has enough ports available in the SAN infrastructure 
    • D、submit configuration to IBM System Storage Interoperability Center for validation

    正确答案:A

  • 第2题:

    An IBM Business Partner sells an IBM System Storage DS8700 to a customer.  Who is responsible for the installation and set up of the storage server()

    • A、purchasing customer
    • B、IBM Installation Readiness Team
    • C、IBM Customer Engineer
    • D、IBM Business Partner

    正确答案:C

  • 第3题:

    A customer has 6.5 TB with 146 GB 15k disk drives on an IBM System Storage DS8700. They want to add 15 TB using 300 GB 15k disk drives. The customer is concerned about performance and wants to know if the DS8700 has the performance capability.  What is the appropriate way to  model the performance()

    • A、Disk Magic
    • B、Capacity Magic
    • C、test the workload at an IBM Benchmark Center
    • D、test the solution with IBM Storage Performance Center

    正确答案:A

  • 第4题:

    A UNIX customer has a Symmetrix DMX that has crashed three times in the past six months, causing data loss. The customer is shopping for an enterprise storage solution to provide point-in- time copy functionality without a fixed relationship to its primaries.  Which IBM solution best meets this customer’s requirements()

    • A、IBM System Storage DS8700 andVolumeCopy
    • B、IBM System Storage DS8700 andFlashCopy
    • C、IBM System Storage DS8700 andFlashCopy with the NoCopy option
    • D、IBM System Storage DS8700 andFlashCopy with the Persistent option

    正确答案:B

  • 第5题:

    A customer RFP requires installation of an open system SAN and migration of 40 TB currently residing on ten UNIX servers (on internal server disk). The Service Level Agreement (SLA) requires no more than five minutes per week of planned downtime for backup.  Which IBM System Storage solution is the most cost effective()

    • A、an IBM System Storage DS8700 with LTO tape drive
    • B、an IBM System Storage DS8700 with FlashCopy Manager
    • C、an IBM XIV Storage System
    • D、an IBM XIV Storage System with SAN Volume Controller

    正确答案:C

  • 第6题:

    The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()

    • A、Use eConfig to configure and validate each pSeries and p5 system.
    • B、Engage Advanced Technical Support to review any outstanding technical issues.
    • C、Confirm with the customer that the solution design meets their requirements.
    • D、Perform a Pre-Install Solution Assurance Review to validate required power requirements.

    正确答案:C

  • 第7题:

    单选题
    A customer is looking at an Oracle eBusiness solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()
    A

    Configure a 2 node x3950 X5 

    B

    Customer needs a System p server to support Oracle applications 

    C

    Download the Oracle eBusiness sizing questionnaire from IBM, fill out with customer and submit to IBM for System x sizing 

    D

    Configure a system that meets the minimum requirements


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    A customer has 6.5 TB with 146 GB 15k disk drives on an IBM System Storage DS8700. They want to add 15 TB using 300 GB 15k disk drives. The customer is concerned about performance and wants to know if the DS8700 has the performance capability.  What is the appropriate way to  model the performance()
    A

    Disk Magic

    B

    Capacity Magic

    C

    test the workload at an IBM Benchmark Center

    D

    test the solution with IBM Storage Performance Center


    正确答案: C
    解析: 暂无解析

  • 第9题:

    单选题
    A customer has an IBM System Storage Enterprise Storage Server and several EMC CX3 systems installed in a data center, attached to IBM System p servers. As a step toward data consolidation, they intend to put all data on a new DS8700.  What would be the most important data migration factors to consider()
    A

    sector size and the amount of production data

    B

    existing RAID levels and the disk drive speed

    C

    sector size and existing RAID levels

    D

    amount of production data and the disk drive speed


    正确答案: D
    解析: 暂无解析

  • 第10题:

    单选题
    The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()
    A

    Use eConfig to configure and validate each pSeries and p5 system.

    B

    Engage Advanced Technical Support to review any outstanding technical issues.

    C

    Confirm with the customer that the solution design meets their requirements.

    D

    Perform a Pre-Install Solution Assurance Review to validate required power requirements.


    正确答案: D
    解析: 暂无解析

  • 第11题:

    单选题
    A customer would like to implement an IBM System Storage DS8000 solution. A Capacity Magic study has determined that 500 drives of 450 GB are required to meet the customer’s capacity requirements. Limited space is available for additional systems in the data center.  Which solution  best meets the customer’s requirements()
    A

    DS8800 system with three frames

    B

    DS8800 system with one frame

    C

    DS8700 system with two frames

    D

    DS8800 system with two frames


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    A Business Partner is proposing the installation an IBM XIV Storage System at a customer location.  What is the best time to discuss floor space requirements for the solution()
    A

    during the Technical Delivery and Assessment

    B

    during installation of the equipment

    C

    prior to delivery of the XIV

    D

    during the solution proposal


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A customer is purchasing an IBM System Storage DS8700. What is the most important first step for the installation?()

    • A、verify configuration
    • B、conduct pre-install TDA
    • C、complete physical planning
    • D、verify the solution meets requirements

    正确答案:B

  • 第14题:

    A customer is looking at an Oracle eBusiness solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()

    • A、Configure a 2 node x3950 X5 
    • B、Customer needs a System p server to support Oracle applications 
    • C、Download the Oracle eBusiness sizing questionnaire from IBM, fill out with customer and submit to IBM for System x sizing 
    • D、Configure a system that meets the minimum requirements

    正确答案:C

  • 第15题:

    A bank has requested proposals for a storage solution to upgrade their disaster recovery processes for their IBM System z, UNIX, and Microsoft Windows environment. The solution must simulate a multi-site environment and provide the customer the ability to evaluate Metro Mirror, Global Mirror, Global Mirror for z/OS, and FlashCopy. Floor space is limited.  Which solution best meets the specified requirements()

    • A、two IBM System Storage DS8100 systems
    • B、one IBM System Storage DS8300 with LPAR
    • C、two IBM System Storage DS6800 systems in a single rack
    • D、one IBM System Storage DS6800

    正确答案:B

  • 第16题:

    A customer would like to implement an IBM System Storage DS8000 solution. A Capacity Magic study has determined that 500 drives of 450 GB are required to meet the customer’s capacity requirements. Limited space is available for additional systems in the data center.  Which solution  best meets the customer’s requirements()

    • A、DS8800 system with three frames
    • B、DS8800 system with one frame
    • C、DS8700 system with two frames
    • D、DS8800 system with two frames

    正确答案:D

  • 第17题:

    A Business Partner is proposing the installation an IBM XIV Storage System at a customer location.  What is the best time to discuss floor space requirements for the solution()

    • A、during the Technical Delivery and Assessment
    • B、during installation of the equipment
    • C、prior to delivery of the XIV
    • D、during the solution proposal

    正确答案:A

  • 第18题:

    单选题
    A customer recently installed new SAN with an IBM System Storage DS8300 and several open systems servers to address a need for storage consolidation and still provide  good response time. They have asked the Business Partner technical representative for the most complete IBM product that would allow them to do performance reporting of the new SAN environment.  What is the best solution()
    A

    Tivoli Storage Manager

    B

    Total Productivity Productivity Center for Disk

    C

    Total Productivity Center Basic Edition

    D

    Total Storage Productivity Center Standard Edition


    正确答案: D
    解析: 暂无解析

  • 第19题:

    单选题
    A customer is interested in purchasing a new IBM System Storage TS3500 Tape Library. Which ofthe following documents should be used first to guide the Business Partner to verify theenvironment?()
    A

    TS3500 Redbook

    B

    TS3500 Operators Manual

    C

    Solution Assurance Product Review (SAPR) Guide

    D

    TS3500 Product Installation and Planning Guide


    正确答案: D
    解析: 暂无解析

  • 第20题:

    单选题
    A bank has requested proposals for a storage solution to upgrade their disaster recovery processes for their IBM System z, UNIX, and Microsoft Windows environment. The solution must simulate a multi-site environment and provide the customer the ability to evaluate Metro Mirror, Global Mirror, Global Mirror for z/OS, and FlashCopy. Floor space is limited.  Which solution best meets the specified requirements()
    A

    two IBM System Storage DS8100 systems

    B

    one IBM System Storage DS8300 with LPAR

    C

    two IBM System Storage DS6800 systems in a single rack

    D

    one IBM System Storage DS6800


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    A UNIX customer has a Symmetrix DMX that has crashed three times in the past six months, causing data loss. The customer is shopping for an enterprise storage solution to provide point-in- time copy functionality without a fixed relationship to its primaries.  Which IBM solution best meets this customer’s requirements()
    A

    IBM System Storage DS8700 andVolumeCopy

    B

    IBM System Storage DS8700 andFlashCopy

    C

    IBM System Storage DS8700 andFlashCopy with the NoCopy option

    D

    IBM System Storage DS8700 andFlashCopy with the Persistent option


    正确答案: C
    解析: 暂无解析

  • 第22题:

    单选题
    A customer is interested in purchasing a new IBM System Storage DS8000 solution to consolidateolder ESS and F20 storage systems. What should be done first, prior to final proposaldevelopment?()
    A

    perform a Disk Magic study 

    B

    review eConfig with a technical specialist 

    C

    confirm that the customer has enough ports available in the SAN infrastructure 

    D

    submit configuration to IBM System Storage Interoperability Center for validation


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    A customer RFP requires installation of an open system SAN and migration of 40 TB currently residing on ten UNIX servers (on internal server disk). The Service Level Agreement (SLA) requires no more than five minutes per week of planned downtime for backup.  Which IBM System Storage solution is the most cost effective()
    A

    an IBM System Storage DS8700 with LTO tape drive

    B

    an IBM System Storage DS8700 with FlashCopy Manager

    C

    an IBM XIV Storage System

    D

    an IBM XIV Storage System with SAN Volume Controller


    正确答案: A
    解析: 暂无解析