单选题A customer needs to achieve a very aggressive RTO of 30 minutes or less. A critical requirement is a continuous availability and disaster recovery solution for the mainframe environment. What IBM solution should be recommended to this customer?()A Metr

题目
单选题
A customer needs to achieve a very aggressive RTO of 30 minutes or less. A critical requirement is a continuous availability and disaster recovery solution for the mainframe environment. What IBM solution should be recommended to this customer?()
A

Metro Mirror

B

Metro/Global Mirror

C

Geographically Dispersed Open Servers (GDOS)

D

Geographically Dispersed ParallelSysplex (GDPS)


相似考题
参考答案和解析
正确答案: C
解析: 暂无解析
更多“单选题A customer needs to achieve a very aggressive RTO of 30 minutes or less. A critical requirement is a continuous availability and disaster recovery solution for the mainframe environment. What IBM solution should be recommended to this customer?()A Metr”相关问题
  • 第1题:

    A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()

    • A、Design the least-cost solution to prevent the competition from winning the business.
    • B、Design a disaster recovery (DR) solution and convince the customer why DR is important to their business.
    • C、Use the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.
    • D、Design a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.

    正确答案:D

  • 第2题:

    The customer is planning a new IBM System Storage DS5020 using iSCSI and direct attachedfibre channel connectivity in a redundant configuration. The customer is planning to set up adisaster recovery solution in the near future by using Enhanced Remote Mirroring. Which of thefollowing considerations are critical for this customer?()

    • A、customer must reconfigure aniSCSI port for mirroring
    • B、customer must set up a fabric and dedicate port 4 for disaster recovery
    • C、customer must set up a fabric and dedicate port 2 for disaster recovery
    • D、replication is not possible with the DS5020, they must consider the DS5300

    正确答案:C

  • 第3题:

    A customer is looking at an Oracle eBusiness solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()

    • A、Configure a 2 node x3950 X5 
    • B、Customer needs a System p server to support Oracle applications 
    • C、Download the Oracle eBusiness sizing questionnaire from IBM, fill out with customer and submit to IBM for System x sizing 
    • D、Configure a system that meets the minimum requirements

    正确答案:C

  • 第4题:

    A Technical and Delivery Assessment (TDA) is a structured technical inspection of a completed solution design. After the inspection is complete, what deliverable can the customer expect?()

    • A、Verification of the expected performance of the new solution.
    • B、A document used by IBM manufacturing to build and ship the system solution.
    • C、An IBM Quality Assurance Certificate which is supplied to the customer with the system.
    • D、A list of actions that are recommended to reduce risk and create a successful implementation.

    正确答案:D

  • 第5题:

    A bank has requested proposals for a storage solution to upgrade their disaster recovery processes for their IBM System z, UNIX, and Microsoft Windows environment. The solution must simulate a multi-site environment and provide the customer the ability to evaluate Metro Mirror, Global Mirror, Global Mirror for z/OS, and FlashCopy. Floor space is limited.  Which solution best meets the specified requirements()

    • A、two IBM System Storage DS8100 systems
    • B、one IBM System Storage DS8300 with LPAR
    • C、two IBM System Storage DS6800 systems in a single rack
    • D、one IBM System Storage DS6800

    正确答案:B

  • 第6题:

    单选题
    A large enterprise customer needs a standardized way to backup user data from multiple systems to tape. What solution will meet this need?()
    A

    backup command

    B

    Tivoli Storage Manager

    C

    Tivoli Disaster Recovery Manager

    D

    Store mksysb images on a NIM server


    正确答案: D
    解析: 暂无解析

  • 第7题:

    单选题
    A customer is looking at an Oracle eBusiness solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()
    A

    Configure a 2 node x3950 X5 

    B

    Customer needs a System p server to support Oracle applications 

    C

    Download the Oracle eBusiness sizing questionnaire from IBM, fill out with customer and submit to IBM for System x sizing 

    D

    Configure a system that meets the minimum requirements


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    A customer needs to achieve a very aggressive RTO of 30 minutes or less. A critical requirement is a continuous availability and disaster recovery solution for the mainframe environment. What IBM solution should be recommended to this customer?()
    A

    Metro Mirror

    B

    Metro/Global Mirror

    C

    Geographically Dispersed Open Servers (GDOS)

    D

    Geographically Dispersed ParallelSysplex (GDPS)


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    A bank has requested proposals for a storage solution to upgrade their disaster recovery processes for their IBM System z, UNIX, and Microsoft Windows environment. The solution must simulate a multi-site environment and provide the customer the ability to evaluate Metro Mirror, Global Mirror, Global Mirror for z/OS, and FlashCopy. Floor space is limited.  Which solution best meets the specified requirements()
    A

    two IBM System Storage DS8100 systems

    B

    one IBM System Storage DS8300 with LPAR

    C

    two IBM System Storage DS6800 systems in a single rack

    D

    one IBM System Storage DS6800


    正确答案: B
    解析: 暂无解析

  • 第10题:

    单选题
    A customer is interested in obtaining an AIX solution from IBM.  They have two primary global requirements:   ? Availability (although HACMP is not required)   ? Low cost   Which of the following approaches should the pSeries technical specialist use to meet the customer’s requirements and ensure customer satisfaction?()
    A

    Design the least-cost solution to prevent the competition from winning the business.

    B

    Design a disaster recovery (DR) solution and convince the customer why DR is important to their business.

    C

    Use the HACMP specialist to design the solution and include HA SmoothStart services as part of the proposal.

    D

    Design a solution with redundant parts and explain to the customer the incremental cost associated with the redundancy.


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    A customer has two data centers, 500 kilometers apart. The customer requests a proposal for new storage subsystems and a disaster recovery solution that provides consistent data in the event of a disaster at the local site.  Which IBM System Storage DS8000 solution should the storage  specialist propose to the client()
    A

    Metro/Global Mirror

    B

    Metro Mirror

    C

    Global Copy

    D

    Global Mirror


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    A customer has a requirement for Disaster Recovery for compliance within their industry. Theyhave an RPO of 4 hours and an RTO of 24 hours. Cost is a consideration. What is the most costeffective DR implementation?()
    A

    a disk-to-disk backup solution keeping all storage in the data center

    B

    a backup solution that includes magnetic tape that is shipped to an off-site storage facility

    C

    a less powerful copy environment at a hot site with asynchronous mirroring and cluster technology

    D

    an exact copy of the primary environment at a hot site with remote mirroring and cluster technology


    正确答案: C
    解析: 暂无解析

  • 第13题:

    A customer has a requirement for Disaster Recovery for compliance within their industry. Theyhave an RPO of 4 hours and an RTO of 24 hours. Cost is a consideration. What is the most costeffective DR implementation?()

    • A、a disk-to-disk backup solution keeping all storage in the data center
    • B、a backup solution that includes magnetic tape that is shipped to an off-site storage facility
    • C、a less powerful copy environment at a hot site with asynchronous mirroring and cluster technology
    • D、an exact copy of the primary environment at a hot site with remote mirroring and cluster technology

    正确答案:B

  • 第14题:

    A customer has two data centers, 500 kilometers apart. The customer requests a proposal for new storage subsystems and a disaster recovery solution that provides consistent data in the event of a disaster at the local site.  Which IBM System Storage DS8000 solution should the storage  specialist propose to the client()

    • A、Metro/Global Mirror
    • B、Metro Mirror
    • C、Global Copy
    • D、Global Mirror

    正确答案:D

  • 第15题:

    A customer needs to share large files across three Power Systems servers to create and validate complex automotive designs. What IBM solution should be recommended?()

    • A、PowerHA SystemMirror
    • B、Peer to Peer Remote Copy
    • C、General Parallel File Systems
    • D、Parallel Operating Environment

    正确答案:C

  • 第16题:

    A customer has a large amount of data stored on three database servers and is concerned that at present there is no disaster recovery plan in place.  They have an existing tape backup solution that meets their backup window.  In order to analyze potential disaster recovery plans, which of the following questions is the most important?()

    • A、What is the minimum critical backup window?
    • B、Which server is handling the most critical data?
    • C、How much data is stored on each server?
    • D、What is the throughput of the hard drives?

    正确答案:B

  • 第17题:

    A large enterprise customer needs a standardized way to backup user data from multiple systems to tape. What solution will meet this need?()

    • A、backup command
    • B、Tivoli Storage Manager
    • C、Tivoli Disaster Recovery Manager
    • D、Store mksysb images on a NIM server

    正确答案:B

  • 第18题:

    单选题
    The customer is planning a new IBM System Storage DS5020 using iSCSI and direct attachedfibre channel connectivity in a redundant configuration. The customer is planning to set up adisaster recovery solution in the near future by using Enhanced Remote Mirroring. Which of thefollowing considerations are critical for this customer?()
    A

    customer must reconfigure aniSCSI port for mirroring

    B

    customer must set up a fabric and dedicate port 4 for disaster recovery

    C

    customer must set up a fabric and dedicate port 2 for disaster recovery

    D

    replication is not possible with the DS5020, they must consider the DS5300


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    The pSeries technical specialist just finished reviewing the system configurations with the customer. The customer requested that many of the availability options,initially configured,be removed due to budgetary constraints.   What should be done next?()
    A

    Remove the availability options,as requested, and place the systems on order.

    B

    Keep the availability options in the configurations and engage the pricer to provide deep discounting on the solution.

    C

    Remove the availability options and review the new configurations with the customer,highlighting the potential exposures.

    D

    Keep the availability options in the configurations, knowing that these options may prevent a critical situation in the future.


    正确答案: C
    解析: 暂无解析

  • 第20题:

    单选题
    A Technical and Delivery Assessment (TDA) is a structured technical inspection of a completed solution design. After the inspection is complete, what deliverable can the customer expect?()
    A

    Verification of the expected performance of the new solution.

    B

    A document used by IBM manufacturing to build and ship the system solution.

    C

    An IBM Quality Assurance Certificate which is supplied to the customer with the system.

    D

    A list of actions that are recommended to reduce risk and create a successful implementation.


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    The pSeries sales representative has done an excellent job in educating the customer on the benefits of working with IBM.  The customer is planning to implement their first ERP application.  This new application will be critical to running their business.  The customer has only a competitor’s UNIX systemcurrently installed.  They are interested in obtaining a proposal from IBM. In addition to the AIX hardware and HACMP software, what else should be included in the IBM proposal for the new ERP solution?()
    A

    I/T services and education to help with the implementation of the hardware and software

    B

    A Supportline specialist to work directly with the customer to manage any issues that arise

    C

    The services required to move the currently installed applications from the competitor’s systems to the IBM systems

    D

    A slimmed down solution to ensure that the IBM solution is less expensive than the competitor’s solution


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    A customer needs to achieve a very aggressive RTO of 30 minutes or less. A critical requirement is a continuous availability and disaster recovery solution for the mainframe environment. What IBM solution should be recommended to this customer?()
    A

    Metro Mirror

    B

    Metro/Global Mirror

    C

    Geographically Dispersed Open Servers (GDOS)

    D

    Geographically Dispersed ParallelSysplex (GDPS)


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    A customer needs to share large files across three Power Systems servers to create and validate complex automotive designs. What IBM solution should be recommended?()
    A

    PowerHA SystemMirror

    B

    Peer to Peer Remote Copy

    C

    General Parallel File Systems

    D

    Parallel Operating Environment


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    A customer is planning a combined solution of a 2 node SVC and DS8700 with 128x300 GB FC disks. During the TDA the reviewer compares the machine configuration with the customer’s expectations.  Which of the following customer requirements must be considered()
    A

    the number of SAN ports required by the solution

    B

    thin provisioning is mandatory

    C

    the solution needs to support RAID 0

    D

    the solution needs to be supported by the VMware Site Recovery Manager


    正确答案: D
    解析: 暂无解析