第1题:
A customer wants to integrate an x445 running SuSE with their existing EMC storage infrastructure. Which of the following tasks needs to be done to ensure that the solution will work properly?()
第2题:
A p5-570 8-way 32GB system has been proposed to a customer as a new test system with four LPARs. The current applications are certified on AIX 5.2 but not yet on AIX 5.3. The customer wants to understand the advantages and disadvantages of this solution versus a pair of 4-way p5-550s with 16GB each in testing their current applications. Which of the following points should the pSeries technical specialist highlight?()
第3题:
Companycom wants to manage multiple partitions for a p5 590 server using Partition Load Manager (PLM). Some of the partitions are dedicated processors and some of them are shared processors. What information about PLM limitations should be expressed to the customer?()
第4题:
A large customer is consolidating their pSeries systems onto a p5 590. They will have a requirement for a single device (disk, lun) to have multiple paths through different adapters in a single LPAR. The primary applications were written for AIX 5.2. Which of the following would be the recommended solution to satisfy this requirement?()
第5题:
Companycom is considering a partitioned solution with one of the LPARs utilizing 12 CPUs. Multiple applications will be loaded on this large LPAR. However, the customer wants to ensure some tasks will have higher priority access to the CPU and memory resources. Which of the following solutions would best satisfy the requirement?()
第6题:
Use nodes of equal size.
Create multiple resource groups and use loadlever.
Use dynamic node priority to manage resource groups.
Use an ordered list to manage resource group fallover.
第7题:
A
B
C
D
第8题:
Dispute the vendor's claims that these pre-built workflows even exist.
Inform the organization that workflow is an unimportant component in asset .
Inform the organization that all vendors have the same pre-built workflows incorporated in their products.
Inform the customer that if current business processes do not exactly match these workflows, customization is required.
第9题:
The Power 550 is licensed for three LPARs only.
There is not enough memory to meet the minimum dedicated memory requirement for the fourth LPAR. A faulty memory DIMM is detected in the POWER5 550.
There is not enough memory to meet the minimum dedicated memory requirement for the fourth LPAR. The HMC reserves some memory to perform logical partition tasks.
There is not enough memory to meet the minimum dedicated memory requirement for the fourth LPAR. The hypervisor reserves some memory to perform logical partition tasks.
第10题:
The customer requires Layer 3 roaming.
The customer requires immediate wire line integration with a catalyst 6500 switch.
The customer needs an outdoor-ready access point.
The customer wants the option to migrate to LWAPP.
第11题:
All of the partitions can be managed in one group mixing dedicated and shared processors. PLM will move resources in the group as setup in the PLM profiles.
PLM handles memory, dedicated and shared processor partitions. All the partitions in a group must be of the same processor type. PLM moves I/O resources between partitions based on PLM policy files.
PLM handles memory, dedicated and shared processor partitions. The policy file, once loaded, is static and has no knowledge of workload on the managed partitions. PLM is supported for partitions that are running AIX 5.2 or i5OS.
All of the partitions in a group must be the same type, either all dedicated processor partitions or shared processor partitions. One PLM Server can manage multiple groups of partitions. PLM does not move resources between groups.
第12题:
4 processors 8GB of memory
5 processors 8GB of memory
4 processors 10GB of memory
5 processors 10GB of memory
第13题:
A solution for two batch applications was proposed in Companycom meeting. They are currently running in two LPARs on a p690. On a daily basis, both applications use 15% of the machine for their workload, and increase to 100% when their weekly reports are run. Since the reports are not run on the same day, what is the best solution?()
第14题:
A competitor in the IBM Maximo Asset Management (IMAM) domain claims that their product contains pre-built workflows and common tasks that span and integrate across asset applications. What should a solution advisor do when a customer is considering such a solution?()
第15题:
The customer has an older storage array and is looking to migrate data that currently exists onover 100 73 GB FC drives to a new IBM System Storage DS5020. The customer states that theyhave only 3 TB of data and wants to consolidate on to fewer higher capacity drives. There are sixapplication servers running multiple applications and operating systems utilizing the storagesystem. What would be the next step to accurately identify the new storage configuration?()
第16题:
An HACMP cluster has three nodes of unequal size. The largest node is Node ’A’. The primary application on Node ’A’ has two components. One component is memory intensive, the other is IO intensive. Nodes ’B’ and ’C’ are running web servers and databases that access information produced by applications on Node ’A’. The customer requires the most performance from the primary application and wants all nodes available for fallover processing. Which of the following is the best solution for meeting the customer requirements?()
第17题:
Companycom wants to buy a new p5 570 running AIX 5.3. The applications require 4 processors and 8GB of memory. There is a requirement to have a Virtual IO Server. What is the smallest p5 570 that should be sold to this customer?()
第18题:
Assign the adapters to a Virtual IO partition
Use the MPIO function included in AIX 5.2
Migrate the application to AIX 5.3 and use the MPIO function
Set up two Virtual IO partitions and attach both partitions to the device
第19题:
Set up the server in SMP mode and use WLM to manage resources effectively
Set up eight dedicated LPARs and use DLPAR to manage resources effectively
Set up a shared pool with eight capped LPARs including production and test/dev
Set up a shared pool with eight uncapped LPARs with priority weight to Production
第20题:
One single port Ethernet adapter
Four dual port Ethernet adapters
Two single port Ethernet adapters
Eight single port Ethernet adapters
第21题:
Reboot the source LPAR.
Remove the resource from the source LPAR.
Rediscover the managed system from the HMC.
Add the resource to the profile of the LPAR.
第22题:
The p5-570 would save rack space over a pair of p5-550 servers.
The p5-570 allows for more CPU and memory resources to be dynamically allocated to any LPAR for performance testing.
The p5-570 can only be upgraded to 64GB of RAM without replacing memory.
The p5-570 supports advanced features such as Micro-Partitioning and Virtual I/O allowing more LPARs of the customer’s applications with fewer processors and fewer I/O adapters.
第23题:
initiate a Disk Magic study
initiate a Capacity Magic study
runiometer on the current environment
utilize the IBM Disk capacity planner toolkit