单选题Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Whic

题目
单选题
Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()
A

An 8-port adapter to the HMC

B

A hub for the private network

C

An additional Ethernet card to the HMC

D

An additional Ethernet card for each partition


相似考题
参考答案和解析
正确答案: A
解析: 暂无解析
更多“单选题Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Whic”相关问题
  • 第1题:

    One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()

    • A、Two p5 570 16 way 1.9 MHz machines
    • B、One p5 590 32 way 1.65 MHz machines
    • C、One p5 595 32 way 1.65 MHz machines
    • D、Two p5 570 16 way 1.65 MHz machines

    正确答案:D

  • 第2题:

    Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()

    • A、Free up one HMC and update the software for use with the p5 570
    • B、Connect the new p5 570 server to an existing HMC and manage the p690s and p5 570 from that HMC
    • C、Order a new HMC to support the new p5 570 server since the CR3 HMC is not supported for a p5 570
    • D、Backup the HMC to DVD-RAM and select HMC migrate to move all the profile data to the new HMC software

    正确答案:A

  • 第3题:

    A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()

    • A、Implement a proxy server to provide multiple sources to one destination 
    • B、Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two 
    • C、Purchase a network hub or switch so both p5 570s can connect to the single HMC 
    • D、Purchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used

    正确答案:C

  • 第4题:

    Companycom wants to buy a new p5 570 running AIX 5.3. The applications require 4 processors and 8GB of memory. There is a requirement to have a Virtual IO Server. What is the smallest p5 570 that should be sold to this customer?()

    • A、4 processors 8GB of memory
    • B、5 processors 8GB of memory
    • C、4 processors 10GB of memory
    • D、5 processors 10GB of memory

    正确答案:D

  • 第5题:

    单选题
    Companycom purchased a new p5 570 without a HMC. The customer does not know how to power the full frame/system off since there does not appear to be an on/off button. What can be done to accomplish this task?()
    A

    Telnet into the machine and do a shutdown -Fr

    B

    Log into ASMI as Administrator and use ASMI menus

    C

    Log into the service processor using WebSM and use ASMI menus

    D

    Use the off button which is located to the left below the LEDs


    正确答案: B
    解析: 暂无解析

  • 第6题:

    单选题
    One of the key decision making factors in a very competitive opportunity will be cost. Companycom needs an aggregate rPerf rating of 120. What is the best solution?()
    A

    Two p5 570 16 way 1.9 MHz machines

    B

    One p5 590 32 way 1.65 MHz machines

    C

    One p5 595 32 way 1.65 MHz machines

    D

    Two p5 570 16 way 1.65 MHz machines


    正确答案: D
    解析: 暂无解析

  • 第7题:

    单选题
    A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()
    A

    Implement a proxy server to provide multiple sources to one destination 

    B

    Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two 

    C

    Purchase a network hub or switch so both p5 570s can connect to the single HMC 

    D

    Purchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    Companycom is planning on upgrading from a pSeries S85 running AIX 4.3.3 to a p5 570 with an HMC. The new server will run AIX 5L 5.2. What should be performed prior to the migration?()
    A

    Verify the ISV application runs on AIX 5.2

    B

    Power4 to POWER5 upgrades are not supported without a application recompile

    C

    Check the placement and size of the boot logical volume and disk space requirements on the S85

    D

    AIX 4.3.3 to AIX 5L 5.2 migrations are perfectly compatible so nothing needs to be checked


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    Which server houses the database partitions in the AIX BCU V2.1? ()
    A

     IBM System p5 570  

    B

     IBM System p5 575  

    C

     IBM System p5 590  

    D

     IBM System p5 595


    正确答案: D
    解析: 暂无解析

  • 第10题:

    单选题
    Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()
    A

    Free up one HMC and update the software for use with the p5 570

    B

    Connect the new p5 570 server to an existing HMC and manage the p690s and p5 570 from that HMC

    C

    Order a new HMC to support the new p5 570 server since the CR3 HMC is not supported for a p5 570

    D

    Backup the HMC to DVD-RAM and select HMC migrate to move all the profile data to the new HMC software


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    A system administrator is installing a p5 590 server with an HMC. After pulling the websm client down, it is not possible to connect to the HMC. The HMC can be pinged from the client. Which of the following settings should be verified next?()
    A

    The routes on the HMC

    B

    The firewall setting of the LAN adapter

    C

    The name resolution protocol on the p5 590 server

    D

    The subnet mask settings on the Ethernet adapters


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    Companycom is migrating from a p690 to a p5 595 utilizing APV Virtual IO features. They have created their profiles for their two Virtual IO Servers. The first Virtual IO Server is installed and running. When trying to DLPAR the DVD/ROM the task fails on the HMC. What is the probable cause?()
    A

    APV key is not registered

    B

    Networking and DNS are not configured

    C

    /etc/hosts table on HMC is not configured

    D

    Virtual IO Server dose not support DLPAR


    正确答案: D
    解析: 暂无解析

  • 第13题:

    Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()

    • A、An 8-port adapter to the HMC
    • B、A hub for the private network
    • C、An additional Ethernet card to the HMC
    • D、An additional Ethernet card for each partition

    正确答案:B

  • 第14题:

    A system administrator is installing a p5 590 server with an HMC. After pulling the websm client down, it is not possible to connect to the HMC. The HMC can be pinged from the client. Which of the following settings should be verified next?()

    • A、The routes on the HMC
    • B、The firewall setting of the LAN adapter
    • C、The name resolution protocol on the p5 590 server
    • D、The subnet mask settings on the Ethernet adapters

    正确答案:B

  • 第15题:

    A customer currently has five partitioned POWER4 systems and is adding new systems.  When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()

    • A、Order a new HMC to support the p5 system.
    • B、Attach the new p5 system to the existing HMC.
    • C、Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.
    • D、Do nothing.  This system does not require an HMC.

    正确答案:A

  • 第16题:

    Which server houses the database partitions in the AIX BCU V2.1? ()

    • A、 IBM System p5 570  
    • B、 IBM System p5 575  
    • C、 IBM System p5 590  
    • D、 IBM System p5 595

    正确答案:B

  • 第17题:

    单选题
    An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
    A

    An additional switch for the new HMC

    B

    Asynchronous adapters on the new HMC

    C

    The two 570 servers are directly connected to the new HMC

    D

    One 570 is directly connected to the new HMC and the other is directly connected to the existing HMC


    正确答案: B
    解析: 暂无解析

  • 第18题:

    单选题
    Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()
    A

    An 8-port adapter to the HMC

    B

    A hub for the private network

    C

    An additional Ethernet card to the HMC

    D

    An additional Ethernet card for each partition


    正确答案: A
    解析: 暂无解析

  • 第19题:

    单选题
    Companycom has a requirement to consolidate six web application servers. There is unused capacity of 2 CPUs on their new p5 570. Which operating systems and or features are required?()
    A

    APV, AIX5.2ML4

    B

    AIX5.3 or i5/OS

    C

    APV, i5/OS, AIX5.3

    D

    APV, AIX5.3 or SuSE9


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()
    A

    Free up one HMC and update the software for use with the p5 570

    B

    Connect the new p5 570 server to an existing HMC and manage the p690s and p5 570 from that HMC

    C

    Order a new HMC to support the new p5 570 server since the CR3 HMC is not supported for a p5 570

    D

    Backup the HMC to DVD-RAM and select HMC migrate to move all the profile data to the new HMC software


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()
    A

    An 8-port adapter to the HMC

    B

    A hub for the private network

    C

    An additional Ethernet card to the HMC

    D

    An additional Ethernet card for each partition


    正确答案: B
    解析: 暂无解析

  • 第22题:

    单选题
    Companycom is buying an application solution that bases its software licensing on the number of CPUs per machine. They will be running two instances of this application and will require 8 CPUs each. A second application is priced based on CPUs per LPAR as well as the class of machine. That application will require 8 CPUs. What is the best hardware to propose to keep the software cost low?()
    A

    A 24 way p5 595 with 3 LPARs

    B

    A 24 way p5 595 with 2 LPARs

    C

    One p5 570s 16 way and one p5 570 8 way

    D

    One p5 595 12 way active and 12 way inactive, and one p5 570 8 way


    正确答案: A
    解析: 暂无解析

  • 第23题:

    单选题
    An administrator has an existing HMC and POWER6 570 connected to a network switch.  The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
    A

    An additional switch for the new HMc  

    B

    Asynchronous adapters on the new HMc

    C

    The two 570 servers are directly connected to the new HMc  

    D

    One 570 is directly connected to the new HMC and the other is directly connected to the existing HMc


    正确答案: C
    解析: 暂无解析

  • 第24题:

    单选题
    Companycom wants to buy a new p5 570 running AIX 5.3. The applications require 4 processors and 8GB of memory. There is a requirement to have a Virtual IO Server. What is the smallest p5 570 that should be sold to this customer?()
    A

    4 processors 8GB of memory

    B

    5 processors 8GB of memory

    C

    4 processors 10GB of memory

    D

    5 processors 10GB of memory


    正确答案: B
    解析: 暂无解析