A customer is planning to upgrade two VMware ESX servers from 3.5 to 4.1 after recently installing a new XIV Storage System. Each server has 4 HBAs connected to redundant fabrics for a total of 4 paths per server to storage. The customer wants to increase the throughput available to the ESX servers.What configuration setting does the storage specialist need to highlight?()
A. increase the buffer credits on the HBAs
B. increase the number of device logins on the ESX servers
C. additional paths will be required between the servers and storage
D. multipath option on the ESX servers should be changed to round-robin
第1题:
Your network includes the following elements: - VMware ESX 3.5 servers - Windows Server 2008 R2 Hyper-V servers - Microsoft System Center Virtual Machine Manager (VMM) 2008 R2 with the Subsystem for UNIX-based Applications feature installed. You run several ESX-hosted virtual machines (VMs) from an NFS share, and you run several Hyper-V VMs from a Windows file share. You need to migrate the ESX-hosted VMs to Hyper-V. Which two actions should you perform?()
第2题:
What are two benefits for the Cisco Partner, derived from the Cisco SBR Methodology?()
第3题:
A customer is planning to upgrade two VMware ESX servers from 3.5 to 4.1 after recently installing a new XIV Storage System. Each server has 4 HBAs connected to redundant fabrics for a total of 4 paths per server to storage. The customer wants to increase the throughput available to the ESX servers. What configuration setting does the storage specialist need to highlight?()
第4题:
A customer wants to deploy VMWare ESX on four-way Intel systems. They are considering IBM and Dell.Which of the following is an advantage IBM has over the competition?()
第5题:
A customer has a mixed Dell and IBM server environment. They want to implement a system management solution for all their Windows, Linux, and VMWare ESX Intel based servers. Which TWO features of IBM Director will be an advantage for this customer?()
第6题:
A customer has four 2-way 2U front-end web servers that are currently running at 15% CPU utilization. These servers provide points of access for users worldwide, and volume is expected to triple in the next six months and aggressively grow thereafter. They want to upgrade these systems to newer technology and stay within the 8U of rack space that they are replacing. Which solution would fit the customer’s requirements?()
第7题:
A customer needs to deploy a SAN and connect nine servers running a mix of Windows and Linux. They currently need 12TB, but their growth requirements will be tripled in the near future. They will also consolidate 18 legacy Windows servers onto one system using virtualization software and connect that server to the storage solution. A DS4000 series backup solution needs to be included in the design. Which of the following solutions will satisfy these requirements?()
第8题:
Your network includes the following elements: VMware ESX 3.5 serversWindows Server 2008 R2 Hyper-V serversMicrosoft System Center Virtual Machine Manager (VMM) 2008 R2 with the Subsystem for UNIX-based Applications feature installed You run several ESX-hosted virtual machines (VMs) from an NFS share, and you run several Hyper-V VMs from a Windows file share. You need to migrate the ESX-hosted VMs to Hyper-V. Which two actions should you perform?()
第9题:
Shut down the VMs, and then perform a physical-to-virtual (P2V) conversion
Shut down the VMs, and then perform a virtual-to-virtual (V2V) conversion
Perform a physical-to-virtual (P2V) conversion while the VMs are running
Perform a physical-to-virtual (P2V) conversion while the VMs are shutdown
第10题:
Reduction in operating system software licensing and application costs
Reduction in floor space and hardware cost saving
VMWare is licensed per system so no extra charge for SMP support
No single point of failure, reducing downtime
第11题:
Three x366 4-ways running VMWare ESX Server.
An x445 8-way Xeon MP attached to a DS4300 and running VMWare ESX Server.
An x445 16-way Xeon MP attached to an EXP400 and running VMWare ESX Server.
Four x346 2-ways running VMWare ESX Server.
第12题:
IBM provides optional Remote Technical Support for hardware, NOS, and VMWare.
The IBM xSeries EXA chipset has extensions to provide better efficiency for the VMFS file system.
IBM servers can address larger LUNs on SAN storage than Dell.
IBM provided VMWare with the majority of their internal drivers for ESX.
第13题:
A customer is considering replacement of twenty older 4U and 6U rack-based servers with one IBM x366 Server running VMWare ESX attached to one DS4300. Which of the following represents a reduction in Total Cost of Ownership (TCO) for the customer?()
第14题:
A community hospital has expressed interest in consolidating their legacy Intel servers onto virtual machines with VMWare ESX. They will migrate most of their 2-way processor servers to two x366’s and have confirmed they would like to use a SAN. The IBM specialist visited their datacenter to verify their environment and met with the Systems Admin. Which of the following questions is most critical to verify the solution can be implemented?()
第15题:
A customer needs to deploy ten dual processor Xeon servers. Six servers will be running Linux and Apache, and the other four will be Citrix presentation servers. The customer’s main concerns are the rack space and the option to have SATA drives. The maximum memory required is 8GB. Which of the following options will provide the best price and performance?()
第16题:
A customer is having problems after an AIX version upgrade from 5.2 to 5.3. Which of the following should the pSeries technical specialist recommend that the customer call?()
第17题:
A customer recently acquired two Power servers and plans to implement AIX 6.1 and Live Application Mobility. What other product is required to accomplish this objective? ()
第18题:
A customer has a very large number of physical Windows-based servers and no centralizedstorage. Which technology solution will help the customer reduce the footprint of their existingserver estate?()
第19题:
You are configuring a new Microsoft System Center Virtual Machine Manager (VMM) 2008 R2 environment to manage your existing virtual infrastructure. The existing infrastructure includes Windows Server 2008 R2 host servers and VMware ESX host servers. You need to add a VMware ESX host server named Host1 to your VMM environment. What should you do?()
第20题:
There is less risk through the implementation of proven solutions
Proactive planning enhances customer satisfaction
Thereare faster implementation of new business applications
Solution differentiation from the competition allows for premium margins
第21题:
Use the default root credentials as the virtual machine delegate, and enable SSH root login
Create a new virtual machine delegate account, add the account as a member of the VMware Administrators role, and enable SSH root login
Create a new virtual machine delegate account, add the account as a member of the VMware Administrators role, and disable SSH root login
Use the default root credentials as the virtual machine delegate, and disable SSH root login
第22题:
avoid mentioning the upgrade to the customer
schedule a convenient time to upgrade again, backing up the configuration before and after theupgrade
contact customer support and ask them to run the upgrade for you
immediately show the customer how to run the CLI command upgrade
第23题:
In the Computer name field of the Add VMware VirtualCenter server dialog box, type the fully qualified domain name (FQDN) of Host1.
In the Computer name field of the Add VMware VirtualCenter server dialog box, type the fully qualified domain name (FQDN) of the VMware VirtualCenter server that manages Host1.
In the Add Hosts wizard, select the VMware ESX Server host (any location) option. In the Computer name field, type the fully qualified domain name (FQDN) of Host1.
In the Add Hosts wizard, select the VMware ESX Server host (any location) option. In the Computer name field, type the fully qualified domain name (FQDN) of the VMware VirtualCenter server that manages Host1.