67 In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
A. Increase, decrease.
B. Increase, increase
C. Increase, increase or decrease.
D. Decrease, decrease.
E. Decrease, increase
第2题:
______(increase),new technology is making it easier for us to find alternative methods of testing.
第3题:
A.shared
B.overlaid
C.dual-line
D.dual-label
E.single-line
F.dual-number
第4题:
88 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A. Increase, increase.
B. Increase, decrease.
C. Decrease, decrease.
D. Decrease, increase.
E. Remain the same, return to customer
第5题:
A. followed,followed
B. followed,following
C. following,followed
D. following,following
第6题:
根据慕课的学习,学术研究论文结构中的IMRD指的是什么?
A.introduction, message, research and discussion
B.introduction, message, results and discussion
C.introduction, methods, research and discussion
D.introduction, methods, results and discussion