()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.
A.The project charter
B.The project scope statement
C.The WBS dictionary
D.The activity list
第1题:
23 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation
B. Scope planning
C. Scope change control
D. Scope
Definition
E. Scope verification
第2题:
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A Time, schedule and cost.
B Management coordination and organization structuring.
C Work methods and accountability.
D Quality of work.
E Risk and impact decision-making.
第3题:
第4题:
A、wbs必须符合项目范围
B、wbs元素必须由多个人负责
C、wbs必需控制在5-8层
D、wbs的编制只需要项目团队成员参与
第5题:
第6题:
第7题:
第8题:
以下哪个最好地描述了工作分解结构(WBS)?()
第9题:
关于工作分解结构(WBS)的说明,哪个是错误的:()
第10题:
Which of the following is NOT a phase of the troubleshooting process?()
第11题:
subdividing
assessing
planning
integrating
第12题:
It provides reliable input for verifying network consistency.
It requires a network audit to support some upgrade decisions.
It requires a network audit to support any network restructuring.
It begins with gathering organizational input that may be inaccurate.
第13题:
● Which of the following can be tracked using the WBS?
A time
B cost
C performance
D scope
E None of the above.
第14题:
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
(75)
A.independent resource
B.individual work load
C.work milestone
D.work package
第15题:
项目范围基线包括()
A、批准的项目范围说明书、WBS及WBS字典
B、项目初步范围说明书、WBS及WBS字典
C、批准的项目范围说明书,WBS字典
D、项目详细范围说明书、WBS
第16题:
第17题:
第18题:
第19题:
() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
第20题:
我们常说的项目责任矩阵是()
第21题:
As an experienced technician, you are responsible for Technical Support in your company. You ask one of the trainees to document the layers of an existing CIS network. Which three statements best characterize this process? ()(Choose three.)
第22题:
Which document provides guidelines to support planning and provides pre-installation steps forthe IBM System Storage DS8000?()
第23题:
independentresource
individualworkload
workmilestone
workpackage