()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.A.The project charterB.The project scope statementC.The WBS dictionaryD.The activity list

题目

()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.

A.The project charter

B.The project scope statement

C.The WBS dictionary

D.The activity list


相似考题
参考答案和解析
正确答案:C
更多“()is a document generated by the creating WBS process that support the WBS,which provides ”相关问题
  • 第1题:

    23 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation

    B. Scope planning

    C. Scope change control

    D. Scope

    Definition

    E. Scope verification


    正确答案:D

  • 第2题:

    ● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

    A Time, schedule and cost.

    B Management coordination and organization structuring.

    C Work methods and accountability.

    D Quality of work.

    E Risk and impact decision-making.


    正确答案:D

  • 第3题:

    什么是WBS?WBS分解的实质意义是什么?检验WBS是否完全的六个标准是什么?


    参考答案:WBS的含义:WBS(work breakdown structures)即工作分解结构,是按照一定的逻辑关系将项目划分为可管理的工作单元。工作分解结构是确定整个项目范围的一种最常用的方法,它先将一个项目分解为数个子项目,每个子项目再逐级分解为相对独立的小的工作单元,并确定每个工作单元的任务及其从属的工作(或活动),因而能够更为容易也更准确地确定这些工作单元的成本和进度,明确定义其质量要求,以便更有效地组织项目进行。WBS分解的实质意义体现在项目过程中的项目职责的落实和明确划分。“责任到人”是项目管理的核心,实际工作中项目管理最怕的就是“事情出了没人认账,没人负责”。要避免这个问题的出现,就要在每一层次WBS分解过程中都考虑到项目责任划分和归属,尽可能每一个最底层的节点都有唯一责任人(或部门)相对应,其分解的粒度是“可以分配,可以交付”。
      检验WBS是否完全的六个标准是:
      (1)状态/完成是可计量的;
      (2)明确定义了开始/结束事件;
      (3)活动有一个可交付成果;
      (4)时间/费用容易估计;
      (5)活动工期在可接受期限内;
      (6)工作安排是独立的。

  • 第4题:

    关于工作分解结构(wBs)的描述,正确的是()。

    A、wbs必须符合项目范围

    B、wbs元素必须由多个人负责

    C、wbs必需控制在5-8层

    D、wbs的编制只需要项目团队成员参与


    正确答案:A

  • 第5题:

    项目范围基线包括 ( ) 。

    A.批准的项目范围说明书、WBS及WBS字典
    B.项目初步范围说明书、WBS及WBS字典
    C.批准的项目范围说明书,WBS字典
    D.项目详细范围说明书、WBS

    答案:A
    解析:
    范围基线又叫作范围基准,包括:经批准的范围说明书、WBS、WBS字典。

  • 第6题:

    The creation of a work breakdown structure(WBS)is the process of ( ) the major project deliverables.

    A.subdividing
    B.assessing
    C.planning
    D.integrating

    答案:A
    解析:
    创建工作分解结构是分解项目可交付物的过程。A.分解 B.估算 C.计划 D.整合

  • 第7题:

    Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.

    A.independent resource
    B.individual work load
    C.work milestone
    D.work package

    答案:D
    解析:
    WBS(工作分解结构)是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包(work package)的层次。A. 独立资源 B. 个人工作负荷C. 工作里程碑 D. 工作包

  • 第8题:

    以下哪个最好地描述了工作分解结构(WBS)?()

    • A、.WBS是对工作成果的层级分解
    • B、.WBS是对工作本身的层级分解
    • C、WBS是对项目产品的层级分解
    • D、WBS是对项目活动的层级分解

    正确答案:A

  • 第9题:

    关于工作分解结构(WBS)的说明,哪个是错误的:()

    • A、WBS遵循100%的原则
    • B、WBS中的每个模块应该都是独特的
    • C、WBS分解只能自上而下
    • D、WBS遵循滚动式规划原则

    正确答案:C

  • 第10题:

    Which of the following is NOT a phase of the troubleshooting process?()

    • A、confirm the repair
    • B、define the problem
    • C、document the results
    • D、simplify the problem

    正确答案:D

  • 第11题:

    单选题
    The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.
    A

    subdividing

    B

    assessing

    C

    planning

    D

    integrating


    正确答案: B
    解析: 该题的关键词为"work breakdown structure、 major project deliverables",其语句结构为"The creation ofa work breakdown structure (WBS)(主语)is(谓语)the processof()the major project deliverables",含义为"创建WBS是怎样主要的项目交付物的过程"。根据WBS定义以及选项,容易识别出应选择分解(subdividing)

  • 第12题:

    多选题
    As an experienced technician, you are responsible for Technical Support in your company. You ask one of the trainees to document the layers of an existing CIS network. Which three statements best characterize this process? ()(Choose three.)
    A

    It provides reliable input for verifying network consistency.

    B

    It requires a network audit to support some upgrade decisions.

    C

    It requires a network audit to support any network restructuring.

    D

    It begins with gathering organizational input that may be inaccurate.


    正确答案: A,C,D
    解析: 暂无解析

  • 第13题:

    ● Which of the following can be tracked using the WBS?

    A time

    B cost

    C performance

    D scope

    E None of the above.


    正确答案:D

  • 第14题:

    ● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.

    (75)

    A.independent resource

    B.individual work load

    C.work milestone

    D.work package


    正确答案:D
    试题(75)分析
     WBS工作分解结构是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包work package的层次。
     独立资源independent resource、个人工作负荷individual work load以及工作里程碑work milestone都不是WBS分解的最小层级,因此选D。
    参考答案
    (75)D

  • 第15题:

    项目范围基线包括()

    A、批准的项目范围说明书、WBS及WBS字典

    B、项目初步范围说明书、WBS及WBS字典

    C、批准的项目范围说明书,WBS字典

    D、项目详细范围说明书、WBS


    正确答案:A

  • 第16题:

    ( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives.

    A.Collecting requirements
    B.Defining requirements
    C.Creating WBS
    D.Requirements analysis

    答案:A
    解析:
    翻译:收集需求是一个确定、记录、管理干系人需求以便满足项目需求的过程。A.收集需求 B.定义需求C.创建WBS D.需求分析

  • 第17题:

    关于工作分解结构(WBS)的描述,正确的是( )。

    A.WBS必须符合项目范围
    B.WBS元素必须由多个人负责
    C.WBS必需控制在5-8层
    D.WBS的编制只需要项目团队成员参与

    答案:A
    解析:
    本题考查分解WBS的原则,也可以是注意事项是个常考点,记住关键点进行答题,会简单一点。
    (1)WBS必须是面向可交付成果的。
    (2)WBS必须符合项目的范围。
    (3)WBS的底层应该支持计划和控制。
    (4)WBS中的元素必须有人负责,而且只由一个人负责,尽管实际上可能需要多个人参与。所以B选项错误
    (5)WBS的指导。WBS应控制在4~6层。所以C选项错误。
    (6)WBS应包括项目管理工作(因为管理是项目具体工作的一部分),也要包括分包出去的工作。
    (7)WBS的编制需要所有(主要)项目干系人的参与,需要项目团队成员的参与。所以D选项错误。
    (8)WBS并非是一成不变的。

  • 第18题:

    ( )is the process of determining,documenting ,and managing stakeholder needs and requirements to meet project objectives.

    A.Collecting requirements
    B.Defining requirements
    C.Creating WBS
    D.Requirements analysis

    答案:A
    解析:
    翻译:收集需求是一个确定、记录、管理干系人需求以便满足项目需求的过程。A.收集需求 B.定义需求C.创建WBS D.需求分析

  • 第19题:

    () is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    • A、projectacceptance
    • B、scopeverification
    • C、scopedefinition
    • D、WBS Creation

    正确答案:B

  • 第20题:

    我们常说的项目责任矩阵是()

    • A、WBS—RBS
    • B、WBS—OBS
    • C、WBS—CBS
    • D、OBS—ABS

    正确答案:B

  • 第21题:

    As an experienced technician, you are responsible for Technical Support in your company. You ask one of the trainees to document the layers of an existing CIS network. Which three statements best characterize this process? ()(Choose three.)

    • A、It provides reliable input for verifying network consistency.
    • B、It requires a network audit to support some upgrade decisions.
    • C、It requires a network audit to support any network restructuring.
    • D、It begins with gathering organizational input that may be inaccurate.

    正确答案:A,C,D

  • 第22题:

    Which document provides guidelines to support planning and provides pre-installation steps forthe IBM System Storage DS8000?()

    • A、Solution Assurance Product Review Guide
    • B、DS8000 Introduction and Planning Guide
    • C、DS8000 Installation Guide
    • D、System Assurance Product Review Guide

    正确答案:D

  • 第23题:

    单选题
    Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
    A

    independentresource

    B

    individualworkload

    C

    workmilestone

    D

    workpackage


    正确答案: D
    解析: 暂无解析