The work breakdown structure (WBS) is first developed in which scope management process?
A . Initiation
B . Scope planning
C . Scope change control
D . Scope Definition
E . Scope verification
第1题:
The "rolling wave" or "moving window" concept is used most frequently on projects where:
AThe baseline is frozen for the duration of the project and no scope changes are permitted
BMarketing is unsure of what the customer actually wants and reserves the right to make major scope changes
CThe low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work
DNetworking techniques are not appropriate
EAll of the above
第2题:
The process of choosing/documenting the best approach to achieve the project objectives is part of:
A.The scope baseline.
B.Scope authorization
C.Scope definition
D.Scope planning.
E.All of the above.
第3题:
198 The most effective means of determining the cost of a project is to price out the _____.
A. Work breakdown structure.
B. Linear responsibility chart.
C. Project charter.
D. Scope statement.
E. Management plan
第4题:
141 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation
B. Scope planning
C. Scope change control
D. Scope Definition
E. Scope verification
第5题:
143 In which of the following scope management processes is the scope management plan prepared?
A. Initiation
B. Scope planning
C. Scope Definition
D. Scope change control
E. Scope verification
第6题:
23 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation
B. Scope planning
C. Scope change control
D. Scope
Definition
E. Scope verification
第7题:
● The process of choosing/documenting the best approach to achieve the project objectives is part of:
A The scope baseline.
B Scope authorization
C Scope definition
D Scope planning.
E All of the above.
第8题:
is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A.Project acceptance
B.Scope verification
C.Scope definition
D.WBS Creation
第9题:
The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.
A.project charter
B.project scope goal
C.project budget
D.project scope statement
第10题:
第11题:
第12题:
()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
第13题:
The Work Breakdown Structure (WBS) is the basis for communicating:
A.Project scope, cost control, schedule, quality
B.Project objectives, dependencies, plan, cost control
C.Project scope, schedule, staffing, cost control
D.Project scope, quality, schedule, dependencies
E.Project budget, schedule, risk factors, work assignments.
第14题:
The most effective means of determining the cost of a project is to price out the _____.
A . Work breakdown structure.
B . Linear responsibility chart.
C . Project charter.
D . Scope statement.
E . Management plan.
第15题:
140 In which of the following scope management processes are subject matter experts used? A. Initiation
B. Scope planning
C. Scope Definition
D. Scope change control
E. Scope verification
第16题:
142 The project charter is prepared in which scope management process?
A. Initiation
B. Scope planning
C. Scope Definition
D. Scope change control
E. Scope verification
第17题:
144 Which of the following is not a scope management process?
A. Initiation
B. Scope planning
C. Scope Definition
D. Scope change control
E. Scope verification
第18题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第19题:
is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A.WBS Creation
B.Scope definition
C.Project acceptance
D.Scope verification
第20题:
● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)
(74)
A. Scope Planning
B. Scope Verification
C. Scope Change Control
D. Scope Definition
第21题:
第22题:
第23题:
() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.