更多“The work breakdown structure (WBS) is first developed in which scope management process?A . InitiationB . Scope planningC . Scope change controlD . Scope DefinitionE . Scope verification”相关问题
  • 第1题:

    The "rolling wave" or "moving window" concept is used most frequently on projects where:

    AThe baseline is frozen for the duration of the project and no scope changes are permitted

    BMarketing is unsure of what the customer actually wants and reserves the right to make major scope changes

    CThe low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work

    DNetworking techniques are not appropriate

    EAll of the above


    正确答案:C

  • 第2题:

    The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A.The scope baseline.

    B.Scope authorization

    C.Scope definition

    D.Scope planning.

    E.All of the above.


    正确答案:D
    D

  • 第3题:

    198 The most effective means of determining the cost of a project is to price out the _____.

    A. Work breakdown structure.

    B. Linear responsibility chart.

    C. Project charter.

    D. Scope statement.

    E. Management plan


    正确答案:A

  • 第4题:

    141 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation

    B. Scope planning

    C. Scope change control

    D. Scope Definition

    E. Scope verification


    正确答案:D

  • 第5题:

    143 In which of the following scope management processes is the scope management plan prepared?

    A. Initiation

    B. Scope planning

    C. Scope Definition

    D. Scope change control

    E. Scope verification


    正确答案:B

  • 第6题:

    23 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation

    B. Scope planning

    C. Scope change control

    D. Scope

    Definition

    E. Scope verification


    正确答案:D

  • 第7题:

    ● The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A The scope baseline.

    B Scope authorization

    C Scope definition

    D Scope planning.

    E All of the above.


    正确答案:D

  • 第8题:

    is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    A.Project acceptance

    B.Scope verification

    C.Scope definition

    D.WBS Creation


    正确答案:B
    解析:范围验证是指获取项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。

  • 第9题:

    The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

    A.project charter

    B.project scope goal

    C.project budget

    D.project scope statement


    正确答案:C

  • 第10题:

    Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()

    A.Scope Planning
    B.Scope Verification
    C.Scope Change Control
    D.Scope Definition

    答案:D
    解析:
    在以下项目范围管理几个过程中,(74)涉及将主要项目可交付成果细分成更小、更容易管理的组件单元。A.范围规划B.范围确认C.范围变更控制D.范围定义

  • 第11题:

    The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.

    A.project charter
    B.project scope goal
    C.project budget
    D.project scope statement

    答案:D
    解析:
    翻译:范围管理计划是团队如何准备项目范围说明文件,包括描述创建WBS,核实项目的可交付成果的完成,并为项目范围变更控制的要求。A.项目章程 B.项目范围目标C.项目预算 D.范围说明书

  • 第12题:

    ()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    • A、Project acceptance
    • B、Scope verification
    • C、Scope definition
    • D、WBS Creation

    正确答案:B

  • 第13题:

    The Work Breakdown Structure (WBS) is the basis for communicating:

    A.Project scope, cost control, schedule, quality

    B.Project objectives, dependencies, plan, cost control

    C.Project scope, schedule, staffing, cost control

    D.Project scope, quality, schedule, dependencies

    E.Project budget, schedule, risk factors, work assignments.


    正确答案:A
    A

  • 第14题:

    The most effective means of determining the cost of a project is to price out the _____.

    A . Work breakdown structure.

    B . Linear responsibility chart.

    C . Project charter.

    D . Scope statement.

    E . Management plan.


    正确答案:A

  • 第15题:

    140 In which of the following scope management processes are subject matter experts used? A. Initiation

    B. Scope planning

    C. Scope Definition

    D. Scope change control

    E. Scope verification


    正确答案:A

  • 第16题:

    142 The project charter is prepared in which scope management process?

    A. Initiation

    B. Scope planning

    C. Scope Definition

    D. Scope change control

    E. Scope verification


    正确答案:A

  • 第17题:

    144 Which of the following is not a scope management process?

    A. Initiation

    B. Scope planning

    C. Scope Definition

    D. Scope change control

    E. Scope verification


    正确答案:D

  • 第18题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第19题:

    is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    A.WBS Creation

    B.Scope definition

    C.Project acceptance

    D.Scope verification


    正确答案:D

  • 第20题:

    ● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)

    (74)

    A. Scope Planning

    B. Scope Verification

    C. Scope Change Control

    D. Scope Definition


    正确答案:D

  • 第21题:

    Which of following is an important input to scope verification? ()

    A.Work results
    B.Historical information
    C.Formal acceptance
    D.Change request

    答案:A
    解析:
    译文:下面哪一项是范围确认的重要输入?
    A、工作结果 B、历史信息 C、正式验收 D、变更请求

  • 第22题:

    () is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily.

    A.Project acceptance
    B.Scope verification
    C.Scope definition
    D.WBS Creation

    答案:B
    解析:
    范围验证是指获得项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。

  • 第23题:

    () is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    • A、projectacceptance
    • B、scopeverification
    • C、scopedefinition
    • D、WBS Creation

    正确答案:B