● The project scope/charter baseline includes:A Summary of background conditions defining the project.B Organization, authority and responsibility relationships.C Functions to be performed.D Resource requirement schedule including time estimates.E All of

题目

● The project scope/charter baseline includes:

A Summary of background conditions defining the project.

B Organization, authority and responsibility relationships.

C Functions to be performed.

D Resource requirement schedule including time estimates.

E All of the above.


相似考题
参考答案和解析
正确答案:E
更多“●The project scope/charter baseline includes:ASummary of background conditions defining th ”相关问题
  • 第1题:

    ● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.

    (71)

    A.risk

    B.problem

    C.result

    D.data


    正确答案:A

  • 第2题:

    Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk

    B.problem

    C.result

    D.data


    正确答案:A
    风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第3题:

    Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk
    B.problem
    C.result
    D.data

    答案:A
    解析:
    风险不是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第4题:

    Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

    A.risk

    B.problem

    C.result

    D.data


    正确答案:A
    解析:风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

  • 第5题:

    Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.

    A.risk
    B.problem
    C.result
    D.data

    答案:A
    解析:
    风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A 是风险,选项B 是问题,选项 C 是结果,选项 D 是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择 A

  • 第6题:

    2、在HTML语言中,下列()是专属于td、th元素的属性。

    A.bgcolor

    B.align

    C.colspan

    D.background


    C