● Which may be employed to shorten a schedule without changing the scope of the task?A Fast tracking.B CrashingC Releasing resources earlier from tasks which were scheduled with a late start.D Alter to task priorities.E A or B

题目

● Which may be employed to shorten a schedule without changing the scope of the task?

A Fast tracking.

B Crashing

C Releasing resources earlier from tasks which were scheduled with a late start.

D Alter to task priorities.

E A or B


相似考题
更多“● Which may be employed to shorten a schedule without changing the scope of the task?A Fast tracking.B CrashingC Releasing resources earlier from tasks which were scheduled with a late start.D Alter to task priorities.E A or B”相关问题
  • 第1题:

    177 Which may be employed to shorten a schedule without changing the scope of the task?

    A. Fast tracking.

    B. Crashing

    C. Releasing resources earlier from tasks which were scheduled with a late start.

    D. Alter to task priorities.

    E. A or B


    正确答案:A

  • 第2题:

    ● The critical path is calculated by

    A subtracting the end date of task one from the start date of task two.

    B determining which tasks have the least amount of total slack.

    C totaling the time for all activities.

    D determining the shortest path through the network.

    E Determining which tasks have the most slack


    正确答案:B

  • 第3题:

    To view the results of a manual SQL Tuning Advisor task, which steps should the DBA take?()

    A. From the Advisor Central home page, select the tuning task from the Advisor Tasks section.

    B. From Advisor Central, choose SQL Advisors, SQL Tuning Advisors, Manual Tuning Task Results.

    C. From Advisor Central, choose SQL Advisors, Manual SQL Tuning Advisors, Tuning Task Results.

    D. Either B or C


    参考答案:A

  • 第4题:

    Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ).

    A.fast tracking
    B.what-if scenario analysis
    C.resource leveling
    D.critical chain methoD.

    答案:A
    解析:
    进度压缩技术包括赶工和快速跟进。(74) A.快速跟进 B.假设情景分析 C.资源平衡 D.关键链法

  • 第5题:

    You are the network administrator for All network servers run Windows Server 2003. Recently, another network administrator create a scheduled task to perform a normal backup of Microsoft Exchange Server 2003 compuer every Saturday night. You need to perform maintenance tasks on the Exchange server on this Saturday night only. If the backup starts while you are performing the maintenance tasks,data might be corrupted. You need to ensure that the backup task does not start while you perform the maintenance tasks. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.()Choose two.)

    • A、In the Backup utility, clear the Enabled (scheduled tasks runs at specified time) check box.
    • B、In Control Panel, use Scheduled Tasks to pause Task Scheduler.
    • C、Run the Schtasks command with the /end /p parameters.
    • D、Use the Services snap-in to change the startup type of the Task Scheduler service from Automatic to Manual.

    正确答案:A,B

  • 第6题:

    To view the results of a manual SQL Tuning Advisor task, which steps should the DBA take?()

    • A、From the Advisor Central home page, select the tuning task from the Advisor Tasks section.
    • B、From Advisor Central, choose SQL Advisors, SQL Tuning Advisors, Manual Tuning Task Results.
    • C、From Advisor Central, choose SQL Advisors, Manual SQL Tuning Advisors, Tuning Task Results.
    • D、Either B or C

    正确答案:A

  • 第7题:

    To view the results of a manual SQL Tuning Advisor task, which steps should the DBA take?()  

    • A、 From the Advisor Central home page,select the tuning task from the Advisor Tasks section 
    • B、 From Advisor Central,choose SQL Advisors,SQL Tuning Advisors,Manual Tuning Task Results
    • C、 From Advisor Central,choose SQL Advisors,Manual SQL Tuning Advisors,Tuning Task Results
    • D、 Either B or C

    正确答案:A

  • 第8题:

    You are a network administrator for ExamSheet.net's Windows 2000 network.  Your computer is installed with Windows 2000 Professional. You schedule a task that will copy files from your computer to another computer on the network. You notice that the task is not completing correctly. You manually copy the files from your computer to other computers on the network without any errors. You verify that all of your other tasks are working correctly. You want the task to complete successfully.  What should you do? ()

    • A、Start the Remote Procedure Call (RPC) Locater service and configure the service to start automatically.
    • B、Start the RunAs service and configure the service to start automatically.
    • C、Configure the Task Scheduler service account to use the local Administrator account and password. Restart the service.
    • D、Use Scheduled Tasks to configure the task to run under the security context of your account.

    正确答案:D

  • 第9题:

    You have a WINS server that runs Windows Server 2003 Service Pack 2 (SP2). You need to schedule a backup of the WINS database whenever the WINS service stops. What should you do? ()

    • A、Create a scheduled task that runs Wins.exe.
    • B、Create a scheduled task that runs Netsh.exe.
    • C、Modify the General options from the WINS snap-in.
    • D、Schedule a system state backup by using Windows Backup

    正确答案:C

  • 第10题:

    单选题
    You use Windows 2000 Professional on your desktop computer Company1. You use Company1 to runautomated reports and retrieve performance data from Windows 2000 Server computers.You configure Scheduled Tasks to notify you of failed tasks. Three days later, you notice that none ofyour tasks was started and you never received notification. You view the list of scheduled tasks as shownin the exhibit. You want to enable your tasks to start and then to receive notification of failed tasks. What should you do? ()
    A

    Use Scheduled Tasks to configure the tasks to run under the security context of a local      Administrator account. 

    B

    Configure the Task Scheduler service account to use a local Administrator account and password.  

    C

    Use Computer Management to start the Messenger service and to configure the Messenger service to start automatically. 

    D

    Use Computer Management to start the Task Scheduler service and to configure the Task Scheduler service to start automatically.


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    You work as a database administrator at Certkiller .com. In your production database there is a job, CALC_STAT, which has been scheduled to run every Friday at 5.00 p.m. CALC_STATupdates the optimizer statistics for the objects owned by the APPSschema. You want the task to be generic, thereby allowing users to modify the attributes of the task at run time without affecting the original task.Which component of Oracle Scheduler must you define to achieve this?()
    A

     Window

    B

     Program

    C

     Job class

    D

     Window group


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    To view the results of a manual SQL Tuning Advisor task, which steps should the DBA take?()
    A

    From the Advisor Central home page, select the tuning task from the Advisor Tasks section.

    B

    From Advisor Central, choose SQL Advisors, SQL Tuning Advisors, Manual Tuning Task Results.

    C

    From Advisor Central, choose SQL Advisors, Manual SQL Tuning Advisors, Tuning Task Results.

    D

    Either B or C


    正确答案: D
    解析: 暂无解析

  • 第13题:

    ● Which of the following is indicative of negative float?

    A The late start date is earlier than the early start date.

    B The critical path supports the imposed end date.

    C The early finish date is equal to the late finish date.

    D When leads are employed in the schedule.

    E The project is sinking.


    正确答案:A

  • 第14题:

    The Database Resource Manager is automatically enabled in the maintenance window that runs the Automated Maintenance Task. What is the reason for this?()

    A. to prevent the creation of an excessive number of scheduler job classes

    B. to allow the Automated Maintenance Tasks to use system resources without any restriction

    C. to allow resource sharing only among the Automated Maintenance Tasks in the maintenance window

    D. to prevent the Automated Maintenance Tasks from consuming excessive amounts of system resources


    参考答案:D

  • 第15题:

    Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )

    A.fast tracking

    B.what-if scenario analysis

    C.resource leveling

    D.critical chain method


    正确答案:A

  • 第16题:

    In your production database there is a job, CALC_STAT, which has been scheduled to run every Friday at 5:00 p.m. CALC_STAT updates the optimizer statistics for the objects owned by the APPS schema. You want the task to be generic, thereby allowing users to modify the attributes of the task at run time without affecting the original task. Which component of Oracle Scheduler must you define to achieve this?()

    • A、Window
    • B、Program
    • C、Job class
    • D、Window group

    正确答案:B

  • 第17题:

    The Database Resource Manager is automatically enabled in the maintenance window that runs the Automated Maintenance Task. What is the reason for this?()

    • A、to prevent the creation of an excessive number of scheduler job classes
    • B、to allow the Automated Maintenance Tasks to use system resources without any restriction
    • C、to allow resource sharing only among the Automated Maintenance Tasks in the maintenance window
    • D、to prevent the Automated Maintenance Tasks from consuming excessive amounts of system resources

    正确答案:D

  • 第18题:

    You work as a database administrator at Certkiller .com. In your production database there is a job, CALC_STAT, which has been scheduled to run every Friday at 5.00 p.m. CALC_STATupdates the optimizer statistics for the objects owned by the APPSschema. You want the task to be generic, thereby allowing users to modify the attributes of the task at run time without affecting the original task.Which component of Oracle Scheduler must you define to achieve this?()

    • A、 Window
    • B、 Program
    • C、 Job class
    • D、 Window group

    正确答案:B

  • 第19题:

    You use Windows 2000 Professional on your desktop computer Company1. You use Company1 to runautomated reports and retrieve performance data from Windows 2000 Server computers.You configure Scheduled Tasks to notify you of failed tasks. Three days later, you notice that none ofyour tasks was started and you never received notification. You view the list of scheduled tasks as shownin the exhibit. You want to enable your tasks to start and then to receive notification of failed tasks. What should you do? ()

    • A、Use Scheduled Tasks to configure the tasks to run under the security context of a local      Administrator account. 
    • B、Configure the Task Scheduler service account to use a local Administrator account and password.  
    • C、Use Computer Management to start the Messenger service and to configure the Messenger service to start automatically. 
    • D、Use Computer Management to start the Task Scheduler service and to configure the Task Scheduler service to start automatically.

    正确答案:A

  • 第20题:

    You use Windows 2000 Professional on your desktop Computer. You schedule a task to run an MMC snap-in to perform configuration tasks on other computers. You notice that the task is not completing correctly. You manually start MMC. You add the snap-in. You are then able to successfully run the task. You verify that all of your other tasks are working correctly. You want to enable your tasks to complete successfully. What should you do?()

    • A、Use Scheduled Tasks to configure the task to run under the security context of your account.
    • B、Configure the Task Scheduler service account to use a local Administrator account and password.
    • C、Use Computer Management to start the Messenger service and to configure the Messenger service to start automatically. 
    • D、Use Computer Management to start the Task Scheduler service and to configure the Task Scheduler service to start automatically. 

    正确答案:A

  • 第21题:

    Your network consists of a single Active Directory domain named contoso.com. The functional level of the domain is Windows Server 2003. You need to schedule a task to find all user accounts whose passwords have remained unchanged during the past 60 days. Which tool should the scheduled task run? ()

    • A、Dsget.exe
    • B、Dsquery.exe
    • C、Active Directory Usersand Computers
    • D、Find.exe

    正确答案:B

  • 第22题:

    单选题
    You use Windows 2000 Professional on your desktop Computer. You schedule a task to run an MMC snap-in to perform configuration tasks on other computers. You notice that the task is not completing correctly. You manually start MMC. You add the snap-in. You are then able to successfully run the task. You verify that all of your other tasks are working correctly. You want to enable your tasks to complete successfully. What should you do?()
    A

    Use Scheduled Tasks to configure the task to run under the security context of your account.

    B

    Configure the Task Scheduler service account to use a local Administrator account and password.

    C

    Use Computer Management to start the Messenger service and to configure the Messenger service to start automatically. 

    D

    Use Computer Management to start the Task Scheduler service and to configure the Task Scheduler service to start automatically. 


    正确答案: C
    解析: 暂无解析

  • 第23题:

    单选题
    You are a network administrator for ExamSheet.net's Windows 2000 network.  Your computer is installed with Windows 2000 Professional. You schedule a task that will copy files from your computer to another computer on the network. You notice that the task is not completing correctly. You manually copy the files from your computer to other computers on the network without any errors. You verify that all of your other tasks are working correctly. You want the task to complete successfully.  What should you do? ()
    A

    Start the Remote Procedure Call (RPC) Locater service and configure the service to start automatically.

    B

    Start the RunAs service and configure the service to start automatically.

    C

    Configure the Task Scheduler service account to use the local Administrator account and password. Restart the service.

    D

    Use Scheduled Tasks to configure the task to run under the security context of your account.


    正确答案: A
    解析: 暂无解析