● A non-critical path activity is completed in half the time. Then,A The critical path is also reduced.B The slack in the path containing this activity will increase.C The total cost for this activity has decreased.D Manpower from this activity can be ass

题目

● A non-critical path activity is completed in half the time. Then,

A The critical path is also reduced.

B The slack in the path containing this activity will increase.

C The total cost for this activity has decreased.

D Manpower from this activity can be assigned to other activities.

E All of the above.


相似考题
更多“●A non-critical path activity is completed in half the time. Then,AThe critical path is al ”相关问题
  • 第1题:

    关于os.path子库,以下选项中用来计算相对路径的函数是:

    A.os.path.basename(path)

    B.os.path.relpath(path)

    C.os.path.abspath(path)

    D.os.path.normpath(path)


    os.path.relpath(path)

  • 第2题:

    关于os.path子库,以下选项中用来计算相对路径的函数是:‪‬‪‬‪‬‪‬‪‬‮‬‪‬‮‬‪‬‪‬‪‬‪‬‪‬‮‬‫‬‮‬‪‬‪‬‪‬‪‬‪‬‮‬‭‬‫‬‪‬‪‬‪‬‪‬‪‬‮‬‪‬‮‬‪‬‪‬‪‬‪‬‪‬‮‬‫‬‮‬‪‬‪‬‪‬‪‬‪‬‮‬‪‬‭

    A.os.path.normpath(path)

    B.os.path.basename(path)

    C.os.path.abspath(path)

    D.os.path.relpath(path)


    os.path.relpath(path)

  • 第3题:

    关于os.path子库,以下选项中获得文件或目录最近一次修改时间的是:‪‪‪‪‪‪‪‪‪‪‪‫‪‪‪‪‪‫‪‪‪‪‪‪‪‪‪‪‪‪

    A.os.path.getatime(path)

    B.os.path.getctime(path)

    C.os.path.getdtime(path)

    D.os.path.getmtime(path)


    os.path.getmtime(path)

  • 第4题:

    关于os.path子库,以下选项中用来计算相对路径的函数是:

    A.os.path.abspath(path)

    B.os.path.relpath(path)

    C.os.path.normpath(path)

    D.os.path.basename(path)


    os.path.relpath(path)

  • 第5题:

    8、‬关于os.path子库,以下选项中用来计算相对路径的函数是:

    A.os.path.relpath(path)

    B.os.path.normpath(path)

    C.os.path.basename(path)

    D.os.path.abspath(path)


    C

  • 第6题:

    关于os.path子库,以下选项中用来计算相对路径的函数是:‪‪‪‪‪‪‪‪‪‪‪‫‪‪‪‪‪‫‪‪‪‪‪‪‪‪‪‪‪‪

    A.os.path.abspath(path)

    B.os.path.basename(path)

    C.os.path.normpath(path)

    D.os.path.relpath(path)


    os.path.relpath(path)