● Network schedules are prepared during the _____ phase and updated during the _____ phase.A Conceptual, execution.B Development, implementation.C Development, close-out.D Implementation, close-out.E Planning, finishing.

题目

● Network schedules are prepared during the _____ phase and updated during the _____ phase.

A Conceptual, execution.

B Development, implementation.

C Development, close-out.

D Implementation, close-out.

E Planning, finishing.


相似考题
参考答案和解析
正确答案:B
更多“● Network schedules are prepared during the _____ phase and updated during the _____ phase.A Conceptual, execution.B Development, implementation.C Development, close-out.D Implementation, close-out.E Planning, finishing.”相关问题
  • 第1题:

    Network schedules are prepared during the _____ phase and updated during the _____ phase.

    A.Conceptual, execution.

    B.Development, implementation.

    C.Development, close-out.

    D.Implementation, close-out.

    E.Planning, finishing.


    正确答案:B
    B

  • 第2题:

    62 Make or buy decisions are usually made during the _____ phase of a project.

    A. Conceptual

    B. Development.

    C. Implementation

    D. Execution

    E. Close-out


    正确答案:B

  • 第3题:

    6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第4题:

    88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

    B. Development of design phase

    C. Execution phase.

    D. Termination phase.

    E. None of the above


    正确答案:C

  • 第5题:

    ● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.

    A Preliminary planning, detail planning, closeout

    B Implementation, reporting, termination

    C Development, implementation, termination

    D Execution, reporting, finishing

    E Implementation, termination, post-audit review


    正确答案:C

  • 第6题:

    Which phase of the software development requires the most development time?

    A.the design phase

    B.the testing phase

    C.the maintenance phase

    D.the development phase


    正确答案:C

  • 第7题:

    During the systems analysis phase, greater user involvement usually results in better communication, faster development times, and more satisfied users.There are three common team-based approaches that encourage system users to participate actively in various development tasks.1) () is a popular fact-finding technique that brings users into the development process as active participants. The end product of the approach is a requirements model.2) (请作答此空 ) is a team-based technique that speeds up information systems development and produces a functioning information system. The approach consists of several phases. The () combines elements of the systems planning and systems analysis phases of tbe SDLC.Users, managers, and IT staff members discuss and agree on business needs, project scope, constraints, and system requirements. During (), users interact with systems analysts and develop models and prototypes that represent all system processes, outputs, and inputs.3) () attempt to develop a system incrementally by building a series of prototypes and constantly adjusting them to user requirements.

    A.Object-oriente development
    面向对象开发
    B.Model-driven development
    模型驱动开发
    C.RapiD.application development
    快速应用开发
    D.Commercial Application package
    商业套件

    答案:C
    解析:
    在系统分析阶段,重要用户参与通常会导致更好的沟通,更快的开发时间和更满意的用户。有三种常见的基于团队的方法可以鼓励系统用户积极参与各种开发任务.1)(71 Joint application development JAD联合应用开发)作为积极的参与者将用户带入开发过程的流行实况调查技术。该方法的最终产品是一个需求模型.2)(72 Rapid application development RAD)是一种基于团队的技术,可加速信息系统开发并生成功能正常的信息系统。该方法由几个阶段组成。(73 项目范围定义阶段)由生命周期管理(SDLC)中的系统规划和系统分析两个活动组成。用户、管理人员和IT人员讨论并商定业务需求、项目范围、约束和系统要求。在(74 原型设计)期间,用户与系统分析员进行交互,并开发代表所有系统过程,输出和输入的模型和原型.3)(敏捷方法)通过构建一系列原型并不断调整以满足用户需求,试图逐步开发系统。

  • 第8题:

    During the systems analysis phase, greater user involvement usually results in better communication, faster development times, and more satisfied users.There are three common team-based approaches that encourage system users to participate actively in various development tasks.1) () is a popular fact-finding technique that brings users into the development process as active participants. The end product of the approach is a requirements model.2) () is a team-based technique that speeds up information systems development and produces a functioning information system. The approach consists of several phases. The (请作答此空) combines elements of the systems planning and systems analysis phases of tbe SDLC.Users, managers, and IT staff members discuss and agree on business needs, project scope, constraints, and system requirements. During (), users interact with systems analysts and develop models and prototypes that represent all system processes, outputs, and inputs.3) () attempt to develop a system incrementally by building a series of prototypes and constantly adjusting them to user requirements.

    A.requirements planning phase
    需求计划阶段
    B.business process modeling
    业务流程建模
    C.business process improvement
    业务流程优化
    D.scope definition phase
    范围定义阶段

    答案:D
    解析:
    在系统分析阶段,重要用户参与通常会导致更好的沟通,更快的开发时间和更满意的用户。有三种常见的基于团队的方法可以鼓励系统用户积极参与各种开发任务.1)(71 Joint application development JAD联合应用开发)作为积极的参与者将用户带入开发过程的流行实况调查技术。该方法的最终产品是一个需求模型.2)(72 Rapid application development RAD)是一种基于团队的技术,可加速信息系统开发并生成功能正常的信息系统。该方法由几个阶段组成。(73 项目范围定义阶段)由生命周期管理(SDLC)中的系统规划和系统分析两个活动组成。用户、管理人员和IT人员讨论并商定业务需求、项目范围、约束和系统要求。在(74 原型设计)期间,用户与系统分析员进行交互,并开发代表所有系统过程,输出和输入的模型和原型.3)(敏捷方法)通过构建一系列原型并不断调整以满足用户需求,试图逐步开发系统。

  • 第9题:

    Which implement phase service component consists of preparing for migration,excuting a network migration plan,and completing migration test cases?()

    • A、staging and system migration
    • B、post implementation support handoff meeting
    • C、detailed design development
    • D、staff training
    • E、migration plan development

    正确答案:A

  • 第10题:

    Which of these is an accurate list of Cisco Lifecycle Services phases? Select exactly 1 answer(s) from the following:()。

    • A、initiation planning analysis design development implementation operations and maintenance
    • B、project planning, site assessment risk assessment solution selection and acquisition, testing, and operations
    • C、prepare, plan, design, implement operate, and optimize
    • D、analysis, design, deployment testing, implementation, and production
    • E、presales, project planning, development implementation, operations testing, and operations sign- off

    正确答案:C

  • 第11题:

    单选题
    Which implement phase service component consists of preparing for migration,excuting a network migration plan,and completing migration test cases?()
    A

    staging and system migration

    B

    post implementation support handoff meeting

    C

    detailed design development

    D

    staff training

    E

    migration plan development


    正确答案: A
    解析: 暂无解析

  • 第12题:

    单选题
    During which phase of the steps to success methodology for Cisco SMB security solutions would the Network Readiness Assessment be used to assess the readiness of an existing network infrastructure and determine which, if any, modification should be made prior to implementation?()
    A

    Position

    B

    Prepare

    C

    Design

    D

    Perform

    E

    Plan


    正确答案: D
    解析: 暂无解析

  • 第13题:

    Typically, during which phase in a project life cycle are most of the project expenses incurred.

    A . Concept phase

    B . Development of design phase

    C . Execution phase.

    D . Termination phase.

    E . None of the above


    正确答案:C

  • 第14题:

    148 Network schedules are prepared during the _____ phase and updated during the _____ phase. A. Conceptual, execution.

    B. Development, implementation.

    C. Development, close-out.

    D. Implementation, close-out.

    E. Planning, finishing


    正确答案:B

  • 第15题:

    92 Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.

    A. Preliminary planning, detail planning, closeout

    B. Implementation, reporting, termination

    C. Development, implementation, termination

    D. Execution, reporting, finishing

    E. Implementation, termination, post-audit review


    正确答案:C

  • 第16题:

    82 Which of the following are included in the Acquisition phase(s) of the project life cycle.

    A. concept and development

    B. development and planning

    C. execution and phase-out

    D. planning and implementation

    E. concept and planning


    正确答案:C

  • 第17题:

    ● Make or buy decisions are usually made during the _____ phase of a project.

    A Conceptual

    B Development.

    C Implementation

    D Execution

    E Close-out


    正确答案:B

  • 第18题:

    The stages within the development phase of the software life cycle are ( 71 ).

    A.design, analysis, implementation, and testing

    B.analysis, design, implementation, and testing

    C.analysis, design, testing, and implementation

    D.design, analysis, testing, and implementation


    正确答案:C

  • 第19题:

    Many of the activities performed during the preliminary investigation are still being conducted in ____, but in much greater depth than before.

    A.analysis phase
    B.design phase
    C.implementation phase
    D.maintenance phase

    答案:A
    解析:

  • 第20题:

    The most crucial time for project risk assessment is ( ) .

    A.when a problem surfaces
    B.during the planning phase
    C.during the close-out phase
    D.after the project schedule has been published

    答案:B
    解析:
    进行项目风险评估最关键的时候是规划阶段。A.问题出现时 B.规划阶段 C.结束阶段 D.项目进度公布后

  • 第21题:

    During which phase of the steps to success methodology for Cisco SMB Security Solutions would the Network Readiness Assessment be used to assess the readiness of an existing network infrastructure and determine which,if any modification should be prior to implementation?()

    • A、Prepare
    • B、Design
    • C、Position
    • D、Develop
    • E、Plan
    • F、Perform

    正确答案:A

  • 第22题:

    单选题
    During which phase of the steps to success methodology for Cisco SMB Security Solutions would the Network Readiness Assessment be used to assess the readiness of an existing network infrastructure and determine which,if any modification should be prior to implementation?()
    A

    Prepare

    B

    Design

    C

    Position

    D

    Develop

    E

    Plan

    F

    Perform


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    Which of these is an accurate list of Cisco Lifecycle Services phases? Select exactly 1 answer(s) from the following:()。
    A

    initiation planning analysis design development implementation operations and maintenance

    B

    project planning, site assessment risk assessment solution selection and acquisition, testing, and operations

    C

    prepare, plan, design, implement operate, and optimize

    D

    analysis, design, deployment testing, implementation, and production

    E

    presales, project planning, development implementation, operations testing, and operations sign- off


    正确答案: D
    解析: 暂无解析