47 A project can best be defined as:A. Series of non-related activities designed to accomplish single and multiple objectives.B. Coordinated effort of related activities designed to accomplish a goal without a well-established end point.C. Cradle-to-grave

题目

47 A project can best be defined as:

A. Series of non-related activities designed to accomplish single and multiple objectives.

B. Coordinated effort of related activities designed to accomplish a goal without a well-established end point.

C. Cradle-to-grave activities which must be accomplished in less than one year and consumes human and non-human resources.

D. Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints.

E. All of the above.


相似考题
更多“47 A project can best be defined as:A. Series of non-related activities designed to accomplish single and multiple objectives.B. Coordinated effort of related activities designed to accomplish a goal without a well-established end point.C. Cradle-to-grave”相关问题
  • 第1题:

    Standard deviation of project completion is _____ .

    A a relationship of the uncertainty of critical path activities.

    B an indicator of project end date target confidence

    C a function of critical path, leveling and project costs.

    D A and B

    E All of the above.


    正确答案:D

  • 第2题:

    111 Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:

    A. All activities.

    B. Only those activities with the longest time durations.

    C. Those activities on the critical path begining with the longest time duration activities.

    D. Those activities with the greatest degree of risk.

    E. None of the above


    正确答案:C

  • 第3题:

    130 Standard deviation of project completion is _____ .

    A. a relationship of the uncertainty of critical path activities.

    B. an indicator of project end date target confidence

    C. a function of critical path, leveling and project costs.

    D. A and B

    E. All of the above


    正确答案:D

  • 第4题:

    174 A project may be defined as _____

    A. an integrated approach to managing projects

    B. a coordinated undertaking of interrelated activities.

    C. a group of activities directed by a project manger over a life cycle

    D. an undertaking with a defined starting point and defined objectives

    E. All of the above


    正确答案:D

  • 第5题:

    ● A project is defined as:

    A a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.

    B a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end point.

    C an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than one year.

    D a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end product.

    E All of the above.


    正确答案:A

  • 第6题:

    The(69)Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

    A.Plannlng

    B.Executing

    C.Monitoring and Controlling

    D.Closing


    正确答案:B
    解析:执行过程组由用于完成为达成项目要求而在项目管理计划中定义的工作的过程组成。

  • 第7题:

    The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out


    正确答案:B
    执行(Executing)过程组由为达成项目要求而在项目管理计划中定义的工作的过程组成。

  • 第8题:

    ● A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called (72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73) , whose purpose is to contain the various pieces of relevant information – feasibility assessments, schedules, needs analysis, and so forth – in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.


    正确答案:B,D,A,C,D

  • 第9题:

    The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.

    A.project work breakdown

    B.project security authentication

    C.project management

    D.project flowchart


    正确答案:C

  • 第10题:

    The intention of the ( ) is to schedule,organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.

    A.project work breakdown
    B.project security authentication
    C.project management
    D.project flowchart

    答案:C
    解析:
    项目管理的目的就是计划,组织和控制项目的活动来达到最终的目的。A.项目工作分解 B.项目安全认证C.项目管理 D.项目流程图

  • 第11题:

    The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

    • A、Planning
    • B、Executing
    • C、Monitoring and Controlling
    • D、Closing

    正确答案:D

  • 第12题:

    单选题
    Which of the following activities actually does not involve writing? _____.
    A

    Completion according to outlines

    B

    Completion with multiple choices

    C

    Completion according to topic sentences

    D

    Completion with detailed examples related to the topic


    正确答案: B
    解析:
    多项选择题并不涉及写作能力的锻炼。

  • 第13题:

    165 A project can best be defined as:

    A. Series of non-related activities designed to accomplish single and multiple objectives.

    B. Coordinated effort of related activities designed to accomplish a goal without a well-established end point.

    C. Cradle-to-grave activities which must be accomplished in less than one year and consumes human and non-human resources.

    D. Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints.

    E. All of the above.


    正确答案:D

  • 第14题:

    185 A project is defined as:

    A. a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.

    B. a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end point.

    C. an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than one year.

    D. a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end product.

    E. All of the above


    正确答案:A

  • 第15题:

    149 A program can best be described as:

    A. A grouping of related activities which last two years or more

    B. The first major subdivision of a project

    C. A grouping of projects, similar in nature, which support a product or product line and have no definable end point

    D. A product line

    E. Another name for a project


    正确答案:C

  • 第16题:

    If we all work together, I believe we can ____________ our goal.

    (A) apply

    (B) seek

    (C) make

    (D) accomplish


    正确答案:D
    解答参考:D.apply:实施,应用;seek:寻找,探索;make:做;使得;accomplish:完成,实现,达到。【译文】如果我们一起努力,我相信我们能实现目标。

  • 第17题:

    ● A project can best be defined as:

    A Series of non-related activities designed to accomplish single and multiple objectives.

    B Coordinated effort of related activities designed to accomplish a goal without a well-established end point.

    C Cradle-to-grave activities which must be accomplished in less than one year and consumes human and non-human resources.

    D Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints.

    E All of the above.


    正确答案:D

  • 第18题:

    A project management technique that is currently in widespread use is the(71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called(72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide(73), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management.(74) was developed to make clear the interdependence between project tasks before those tasks are scheduled.(75) offers the advantage of clearly showing overlapping tasks.

    A.Structure Chart

    B.Organizational Structure

    C.Work Breakdown Structure

    D.Functional decomposition diagram


    正确答案:C

  • 第19题:

    This project () (accomplish) by the end of 2006 will greatly improve the basic facility of the city.


    参考答案:to be accomplished

  • 第20题:

    You are configuring an active/passive cluster of SRX Series devices as the firewall enforcer on a MAG Series device.Which statement is true?()

    A. Multiple Infranet Enforcer instances are created with a single serial number of an SRX Series device defined in each configuration.

    B. A single Infranet Enforcer instance is created with both serial numbers of the clustered SRX Series devices defined in the configuration.

    C. Multiple Infranet Enforcer instances are created with a single IP address of an SRX Series device defined in each configuration.

    D. A single Infranet enforcer instance is created with the VIP of the clustered SRX Series device defined in the configuration.


    参考答案:B

  • 第21题:

    A critical path for a project is the series of activities that determine( )by which the project can be completed.

    A.the earliest time
    B.the latest time
    C.the total time
    D.the free time

    答案:A
    解析:
    翻译:关键路径通常由一系列决定项目工期的活动组成,它们决定了整个项目的( )。A.最早完成时间 B.最迟完成时间 C.总时间 D.自由时间

  • 第22题:

    The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.

    • A、project work breakdown
    • B、project security authentication
    • C、project management
    • D、project flowchart

    正确答案:C

  • 第23题:

    You are configuring an active/passive cluster of SRX Series devices as the firewall enforcer on a MAG Series device.Which statement is true?()

    • A、Multiple Infranet Enforcer instances are created with a single serial number of an SRX Series device defined in each configuration.
    • B、A single Infranet Enforcer instance is created with both serial numbers of the clustered SRX Series devices defined in the configuration.
    • C、Multiple Infranet Enforcer instances are created with a single IP address of an SRX Series device defined in each configuration.
    • D、A single Infranet enforcer instance is created with the VIP of the clustered SRX Series device defined in the configuration.

    正确答案:B