更多“Cost of quality includes:A.Appraisal costB.detection costC.prevention costD.maintenance co ”相关问题
  • 第1题:

    12 What is the relative priority of project Cost, Schedule and Quality?

    A. 1)Cost - 2)Schedule - 3)Quality

    B. 1)Quality - 2)Schedule - 3)Cost

    C. 1)Quality - 2)Cost - 3)Schedule

    D. 1)Schedule - 2)Quality - 3)Cost

    E. All are of equal priority


    正确答案:E

  • 第2题:

    72 Project trade-offs vary between

    A. risk, cost and schedule.

    B. direct cost, indirect cost, and resource availability

    C. quality, schedule and time

    D. cost, quality and schedule

    E. contract terms, scope and budget


    正确答案:D

  • 第3题:

    154 Project trade-offs vary between

    A. risk, cost and schedule.

    B. direct cost, indirect cost, and resource availability

    C. quality, schedule and time

    D. cost, quality and schedule

    E. contract terms, scope and budget


    正确答案:D

  • 第4题:

    3 Project tradeoffs are usually made by comparing _____ and constraints.

    A. Time, cost, and quality

    B. Time, risk, and quality

    C. Risk, quality, and manpower availability

    D. Cost, quality, and technical performance

    E. Cost, quality, and risk


    正确答案:D

  • 第5题:

    85 Project tradeoffs are usually made by comparing _____ and constraints.

    A. Time, cost, and quality

    B. Time, risk, and quality

    C. Risk, quality, and manpower availability

    D. Cost, quality, and technical performance

    E. Cost, quality, and risk


    正确答案:D

  • 第6题:

    ● Project tradeoffs are usually made by comparing _____ and constraints.

    A Time, cost, and quality

    B Time, risk, and quality

    C Risk, quality, and manpower availability

    D Cost, quality, and technical performance

    E Cost, quality, and risk


    正确答案:D