更多“123 _____ is a narrative description of the work to be accomplished or resource to be supplied.A. Purchase orderB. Level of effort workC. Scope of workD. Contract stipulationE. None of the above”相关问题
  • 第1题:

    _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.

    A Acquisition

    B Contract negotiation

    C Procurement

    D Purchase negotiation

    E None of the above.


    正确答案:B

  • 第2题:

    By which process may an unsuccessful supplier seek remedy for unjust awards?

    A Contract dispute

    B Stop work order

    C Bid protest

    D Coffective action

    E None of the above.


    正确答案:C

  • 第3题:

    33 In which of the following contract types is it easier to change the scope of the contract:

    A. firm fixed price

    B. fixed price plus incentive fee

    C. cost plus percentage of cost

    D. letter contract

    E. None of the above


    正确答案:C

  • 第4题:

    131 _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.

    A. Acquisition

    B. Contract negotiation

    C. Procurement

    D. Purchase negotiation

    E. None of the above


    正确答案:B

  • 第5题:

    13 A legally binding document offered unilaterally is a _____ .

    A. purchase order

    B scope of work description

    C. contract stipulation

    D. level of effort proposal

    E. request for proposal


    正确答案:A

  • 第6题:

    86 The contractual statement of work (CSOW)

    A. Must be the same as the proposal statement of work

    B. Does not identify reporting requirements

    C. Can be at a different level of detail (i.e. WBS level) than the proposal statement of work

    D. Identifies the contractor's organizational structure for the project

    E. All of the above


    正确答案:C

  • 第7题:

    95 A legally binding document offered unilaterally is a _____ .

    A. purchase order

    B. scope of work description

    C. contract stipulation

    D. level of effort proposal

    E. request for proposal


    正确答案:A

  • 第8题:

    ● Configuration (baseline) control monitors performance against the

    A scope baseline

    B original schedule

    C original budget

    D All of the above.

    E None of the above.


    正确答案:A

  • 第9题:

    Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.

    A.milestone

    B.baseline

    C.quality

    D.work


    正确答案:D
    解析:估算活动历时使用的信息包括活动的工作范围、所需资源类型、估算的资源数量,以及资源日历。

  • 第10题:

    The writer of the passage thinks that ______.

    A. it is true to say artists fail in their work

    B. it is untrue to say artists fail in their work

    C. it is true to say some artists fail in their work

    D. it is true to say only painters fail in their work


    正确答案:C

    52.答案为C。根据第一段第五句,It isof coursetrue that many artists do not succeed in their work and instead produce works that can only be considered as failures作出该项选择。

  • 第11题:

    Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.

    • A、milestone
    • B、baseline
    • C、quality
    • D、work

    正确答案:D

  • 第12题:

    单选题
    The SOW (Statement of Work) is another name for the:()
    A

    WBS (Work Breakdown Structure).

    B

    cost benefit analysis.

    C

    requirements specifications.

    D

    narrative description of the work to be accomplished.


    正确答案: C
    解析: 暂无解析

  • 第13题:

    _____ is a narrative description of the work to be accomplished or resource to be supplied.

    A Purchase order

    B Level of effort work

    C Scope of work

    D Contract stipulation

    E None of the above.


    正确答案:C

  • 第14题:

    In which of the following contract types is it easier to change the scope of the contract:

    A firm fixed price

    B fixed price plus incentive fee

    C cost plus percentage of cost

    D letter contract

    E None of the above.


    正确答案:C

  • 第15题:

    75 By which process may an unsuccessful supplier seek remedy for unjust awards?

    A. Contract dispute

    B. Stop work order

    C. Bid protest

    D. Coffective action

    E. None of the above


    正确答案:C

  • 第16题:

    138 _____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form. the basis of a contract.

    A. Request for proposal

    B. Invitation to bid

    C. Request for quotation

    D. Intention for bid

    E. None of the above


    正确答案:A

  • 第17题:

    51 Going from Level 2 to Level 4 in the work breakdown structure will result in

    A. Less estimating accuracy

    B. Better control of the project

    C. Lower status reporting costs

    D. A greater likelihood that something will fall through the cracks

    E. None of the above


    正确答案:E

  • 第18题:

    5 _____ is a narrative description of the work to be accomplished or resource to be supplied. A. Purchase order

    B. Level of effort work

    C. Scope of work

    D. Contract stipulation

    E. None of the above


    正确答案:C

  • 第19题:

    115 In which of the following contract types is it easier to change the scope of the contract:

    A. firm fixed price

    B. fixed price plus incentive fee

    C. cost plus percentage of cost

    D. letter contract

    E. None of the above.


    正确答案:C

  • 第20题:

    ● Going from Level 2 to Level 4 in the work breakdown structure will result in

    A Less estimating accuracy

    B Better control of the project

    C Lower status reporting costs

    D A greater likelihood that something will fall through the cracks

    E None of the above


    正确答案:E

  • 第21题:

    It's high time you _____.

    A. start to work

    B. would start to work

    C. started to work

    D. had started to work


    参考答案: C

  • 第22题:

    在HTML文件中,()标记在页面中显示work为斜体字。

    A.
    work

    B. work
    C. work
    D. work

    答案:C
    解析:

  • 第23题:

    The SOW (Statement of Work) is another name for the:()

    • A、WBS (Work Breakdown Structure).
    • B、cost benefit analysis.
    • C、requirements specifications.
    • D、narrative description of the work to be accomplished.

    正确答案:D