更多“_____ is a narrative description of the work to be accomplished or resource to be supplied.A Purchase orderB Level of effort workC Scope of workD Contract stipulationE None of the above.”相关问题
  • 第1题:

    Quality and _____ are directly related.

    A . productivity

    B . cost overruns

    C . scope control

    D . Pareto diagram

    E . None of the above.


    正确答案:A

  • 第2题:

    A legally binding document offered unilaterally is a _____ .

    A purchase order

    B scope of work description

    C contract stipulation

    D level of effort proposal

    E request for proposal


    正确答案:A

  • 第3题:

    _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.

    A Acquisition

    B Contract negotiation

    C Procurement

    D Purchase negotiation

    E None of the above.


    正确答案:B

  • 第4题:

    In which of the following contract types is it easier to change the scope of the contract:

    A firm fixed price

    B fixed price plus incentive fee

    C cost plus percentage of cost

    D letter contract

    E None of the above.


    正确答案:C

  • 第5题:

    131 _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.

    A. Acquisition

    B. Contract negotiation

    C. Procurement

    D. Purchase negotiation

    E. None of the above


    正确答案:B

  • 第6题:

    13 A legally binding document offered unilaterally is a _____ .

    A. purchase order

    B scope of work description

    C. contract stipulation

    D. level of effort proposal

    E. request for proposal


    正确答案:A

  • 第7题:

    95 A legally binding document offered unilaterally is a _____ .

    A. purchase order

    B. scope of work description

    C. contract stipulation

    D. level of effort proposal

    E. request for proposal


    正确答案:A

  • 第8题:

    ● Scope Management:

    A entails managing the project's work content.

    B is a subset of configuration management and as such is performed by CM specialists.

    C is concerned with naming all activities performed, the end products which results and the resources consumed.

    D is not a concern of the project manager.

    E None of the above.


    正确答案:C

  • 第9题:

    I’m on night duty.When you go to( ), I go to( ).

    A.the bed...the work

    B.bed...the work

    C.bed...work

    D.the bed...work


    参考答案:A

  • 第10题:

    She must arrange to lose time _______, but not to lose her joy.

    A.for work

    B.at work

    C.in work

    D.on work


    正确答案:B

  • 第11题:

    在HTML文件中,()标记在页面中显示work为斜体字。

    A.
    work

    B. work
    C. work
    D. work

    答案:C
    解析:

  • 第12题:

    The SOW (Statement of Work) is another name for the:()

    • A、WBS (Work Breakdown Structure).
    • B、cost benefit analysis.
    • C、requirements specifications.
    • D、narrative description of the work to be accomplished.

    正确答案:D

  • 第13题:

    Inspection of a complex project according to specifications is accomplished by _____.

    A . inspection by attributes.

    B . cyclical inspection

    C . quality conformance inspection

    D . original inspection

    E . None of the above.


    正确答案:C

  • 第14题:

    _____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form. the basis of a contract.

    A Request for proposal

    B Invitation to bid

    C Request for quotation

    D Intention for bid

    E None of the above.


    正确答案:A

  • 第15题:

    By which process may an unsuccessful supplier seek remedy for unjust awards?

    A Contract dispute

    B Stop work order

    C Bid protest

    D Coffective action

    E None of the above.


    正确答案:C

  • 第16题:

    123 _____ is a narrative description of the work to be accomplished or resource to be supplied.

    A. Purchase order

    B. Level of effort work

    C. Scope of work

    D. Contract stipulation

    E. None of the above


    正确答案:C

  • 第17题:

    138 _____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form. the basis of a contract.

    A. Request for proposal

    B. Invitation to bid

    C. Request for quotation

    D. Intention for bid

    E. None of the above


    正确答案:A

  • 第18题:

    5 _____ is a narrative description of the work to be accomplished or resource to be supplied. A. Purchase order

    B. Level of effort work

    C. Scope of work

    D. Contract stipulation

    E. None of the above


    正确答案:C

  • 第19题:

    115 In which of the following contract types is it easier to change the scope of the contract:

    A. firm fixed price

    B. fixed price plus incentive fee

    C. cost plus percentage of cost

    D. letter contract

    E. None of the above.


    正确答案:C

  • 第20题:

    It's high time you _____.

    A. start to work

    B. would start to work

    C. started to work

    D. had started to work


    参考答案: C

  • 第21题:

    She must arrange to lose time _______, but not to lose her job

    A、for work

    B、at work

    C、in work

    D、on work


    参考答案:B

  • 第22题:

    哪个命令用来创建/work目录()

    A.mkpoint/work

    B.mkmountpoint/work

    C.touch/work

    D.mkdir/work


    参考答案:D

  • 第23题:

    哪个命令用来创建/work目录()

    • A、mkpoint/work
    • B、mkmountpoint/work
    • C、touch/work
    • D、mkdir/work

    正确答案:D