A customer wants to run eight production partitions each with the following:   ? 0.7 CPU 1.65-GHz   ? 4GB of RAM   ? 2 Ethernet adapters   They do not have room for many RIO drawers since rack space is currently scarce in their data center.  They have si

题目

A customer wants to run eight production partitions each with the following:   ? 0.7 CPU 1.65-GHz   ? 4GB of RAM   ? 2 Ethernet adapters   They do not have room for many RIO drawers since rack space is currently scarce in their data center.  They have significant unused SAN attached disk.  In addition to the Advanced POWER Virtualization feature, which of the following is the minimum recommended configuration needed to meet the customer’s requirements?()

  • A、p5-570 6-way 1.65-GHz, 32GB
  • B、p5-570 8-way 1.65-GHz, 32GB
  • C、p5-570 6-way 1.65-GHz, 48GB
  • D、p5-570 8-way 1.65-GHz, 48GB

相似考题
更多“A customer wants to run eight production partitions each with the following:   ? 0.7 CPU 1.65-GHz   ? 4GB of RAM   ? 2 Ethernet adapters   They do not have room for many RIO drawers since rack space is currently scarce in their data center.  They have sig”相关问题
  • 第1题:

    Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()

    • A、Use shared memory and semaphores to transfer the data to the TSM LPAR
    • B、Provide gigabit Ethernet adapters in each LPAR and run a crossover cable
    • C、Create a Virtual Ethernet between the production server and the TSM LPARs
    • D、Create a Virtual Ethernet between the TSM server LPAR and the non-production LPARs

    正确答案:C

  • 第2题:

    A customer is planning to buy a two enclosure Power 770, and will implement 4 LPARs with the following requirements:Each LPAR must have a private, dedicated connection to the network.The adapter for this network connection must be hot-swappable.The customer wants to minimize the number of I/O slots used. Which of the following fulfills the customer requirements?()

    • A、Two dual-port PCIe adapters
    • B、A four-port PCIe Ethernet adapter
    • C、Four separate PCIe Ethernet adapters
    • D、Two embedded Integrated Virtual Ethernet adapters (IVE)

    正确答案:C

  • 第3题:

    A customer wants to run VMWare ESX on an x445 with a large number of virtual machines running Windows 2003 Server as a Disaster Recovery (DR) Site for the production environment.  Which of the following questions would most impact the memory configuration?()

    • A、What version of VMWare ESX Server is being considered?
    • B、Do the systems currently use Double Data Rate (DDR) memory?
    • C、What is the total number of processors installed in the production systems?
    • D、What is the total amount of memory currently being used across all the production systems?

    正确答案:D

  • 第4题:

    A customer wants to run DB2 on a Power 780 with uncapped partitions. They have licensed DB2 for 32 of the 64 active cores, and will use it in multiple partitions.   How can the customer ensure that the number of licenses purchased for DB2 is not exceeded?()

    • A、Create a 32-core shared processor pool for the DB2 partitions.
    • B、Limit the number of virtual processors on each DB2 partition to 32.
    • C、Use the IBM License Metric Tool to dynamically manage DB2 usage in the partitions.
    • D、Set the ‘Desired Processing Units’ in each DB2 partition profile so that the sum of all partitions equals 32.

    正确答案:A

  • 第5题:

    A finance company needs to increase its storage but has run out of floor space in the data center.Currently they have two ESS 800 systems with a total of 125 TB of System z data. Which of thefollowing IBM System Storage products would allow them to replace the ESS 800 systems,increase their performance, reduce their floor space, and still allow them room to grow?()

    • A、N5200 
    • B、DS5020 
    • C、DS5300 
    • D、DS8700

    正确答案:D

  • 第6题:

    Companycom tells the technical sales specialist that recent announcements state that virtual lan in the datacenter is the best option. The customer wants to use interpartition communication to save on adapters and increase performance. The systems are going to have shared and dedicated processor partitions. Some of the partitions will be running AIX 5.2 and some will be running AIX 5.3. The second p5 590 will be running a mixture of AIX 5.3 and Linux partitions with 2.6 kernel. What limitations of vlan/interpartition  communication should be discussed with this customer?()

    • A、Virtual Ethernet uses the system processors for all communication functions instead of offloading that load to processors on network adapter cards. Virtual Ethernet is supported on AIX 5L and Linux 2.5 and above. 
    • B、Virtual Ethernet can be used within groups of shared OR groups of dedicated processor partitions, but not both simultaneously. Virtual Ethernet comes with AIX 5L, and is supported in AIX 5.2 or AIX 5.3 partitions, but not Linux. 
    • C、Virtual Ethernet can be used in both shared and dedicated processor partitions. Virtual Ethernet can run in an AIX 5.3 or Linux 2.6 Kernel, but not AIX 5.2 partitions. Virtual Ethernet can only connect partitions within a single system. 
    • D、Virtual Ethernet uses the system processors for all communication functions instead of offloading that load to processors on network adapter cards. Virtual Ethernet can connect partitions between systems if the HMC is shared between systems.

    正确答案:C

  • 第7题:

    Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()

    • A、Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adapters
    • B、Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cards
    • C、Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after reboot
    • D、Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure

    正确答案:D

  • 第8题:

    A customer is purchasing a 12-way p5-570 to run light development workloads on eight AIX 5.3 partitions with two network adapters each.  When the current network configuration was reviewed, it was discovered that they only have four Ethernet ports available on their network switch.  Which of the following solutions would prevent them from having to buy another network switch or hub?()

    • A、Add two HMCs with two Ethernet adapters each and run EtherChannel for the original eight partitions.
    • B、Add two HMCs with two Ethernet adapters each and run Virtual Ethernet for the original eight partitions.
    • C、Add two hosting partitions with two Ethernet adapters each and run EtherChannel for the original eight partitions.
    • D、Add two hosting partitions with two Ethernet adapters each and run Virtual Ethernet for the original eight partitions.

    正确答案:D

  • 第9题:

    A customer wants to run a Domino e-mail application,a Business Intelligence database,and a batch processing application on Linux.The workloads have different behaviors and do not have peaks at the same time. What is a benefit of running these applications on a Power Systems server instead of running on separate x86 servers?()

    • A、Each Linux application can run in a Workload Partition, reducing the management efforts.
    • B、Total cost of Linux applications on Power Systems is more cost effective than on x86 because of platform licensing.
    • C、Memory cloning can be used on the Power Systems to have a single image of the Linux kernel shared by all partitions.
    • D、Using micro-partitions on Power Systems allow the workloads to share the processing resources, increasing the overall system utilization.

    正确答案:D

  • 第10题:

    单选题
    A customer wants to run a Domino e-mail application,a Business Intelligence database,and a batch processing application on Linux.The workloads have different behaviors and do not have peaks at the same time. What is a benefit of running these applications on a Power Systems server instead of running on separate x86 servers?()
    A

    Each Linux application can run in a Workload Partition, reducing the management efforts.

    B

    Total cost of Linux applications on Power Systems is more cost effective than on x86 because of platform licensing.

    C

    Memory cloning can be used on the Power Systems to have a single image of the Linux kernel shared by all partitions.

    D

    Using micro-partitions on Power Systems allow the workloads to share the processing resources, increasing the overall system utilization.


    正确答案: B
    解析: 暂无解析

  • 第11题:

    单选题
    A system has a mirrored data volume group that has a filesystem /data of 10 logical partitions. How many physical partitions will the filesystem have?()
    A

    1

    B

    2

    C

    10

    D

    20


    正确答案: D
    解析: 暂无解析

  • 第12题:

    A small organization is purchasing a POWER5 to consolidate four applications. Currently, each application has two Host Bus Adapters (HBA) connected to an Enterprise Storage Server (ESS). The customer is concerned about the cost of purchasing eight new HBAs. Which feature of virtualization will be most beneficial to this organization?()

    • A、Virtual Ethernet
    • B、Micro-Partitioning
    • C、Virtual I/O Server
    • D、Capped and uncapped partitions

    正确答案:C

  • 第13题:

    A customer wants to install data deduplication and is currently backing up 100 MB of data per night and 300 MB of data per week. They require 100mb/sec of throughput to achieve this backup in their backup window. They have very limited rack space and can only offer 4U space in one of their existing racks. Which ProtecTIER product set best suits this customer?()

    • A、TS3500
    • B、TS7610
    • C、TS7650G
    • D、TS7650A

    正确答案:C

  • 第14题:

    A system has a mirrored data volume group that has a filesystem /data of 10 logical partitions.  How many physical partitions will the filesystem have?()

    • A、1
    • B、2
    • C、10
    • D、20

    正确答案:D

  • 第15题:

    A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention. Which of the following meets the customer requirement?()

    • A、Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partition maximums to one core. Configure each partition to be capped.
    • B、Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partition maximums to one core. Configure each partition to be uncapped.
    • C、Define the production partitions' maximum CPU to the licensing limitations.  Define the development/test partitions to use no more than one core. Configure the HMC scheduler to  dynamically assign processors among the pools over a day.
    • D、Create a shared processor pool for each production partition, with the maximum processor limit set to the  licensing limit for the application in the pool. Assign the development and testing partitions to a processor  pool with a maximum of 1 core. Configure each partition to use uncapped processing.

    正确答案:D

  • 第16题:

    A large customer is consolidating their pSeries systems onto a p5 590. They will have a requirement for a single device (disk, lun) to have multiple paths through different  adapters in a single LPAR. The primary applications were written for AIX 5.2. Which of the following would be the recommended solution to satisfy this requirement?()

    • A、Assign the adapters to a Virtual IO partition
    • B、Use the MPIO function included in AIX 5.2
    • C、Migrate the application to AIX 5.3 and use the MPIO function
    • D、Set up two Virtual IO partitions and attach both partitions to the device

    正确答案:B

  • 第17题:

    A Power 770 customer needs to add additional I/O adapters.  There is no room for the cards, so an I/O drawer must be added. What resource will help identify supported I/O drawers and the maximum number of drawers permitted per loop?()

    • A、I/O Planning Guide
    • B、Power Systems data sheet
    • C、Power Systems Facts and Features
    • D、Run FLRT to recommend I/O features

    正确答案:C

  • 第18题:

    A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following questions is most important to ensure that the power in the datacenter environment is ready for the initial install?()

    • A、Have optional Fibre Channel and Ethernet switches been installed in the server?
    • B、What is the available kVA value of the UPS?
    • C、Are there sufficient empty socket outlets in the UPS?
    • D、What is the impact on the power consumption of the data center cooling system?

    正确答案:B

  • 第19题:

    A customer is upgrading from a 16-core POWER6 570 with two enclosures to a 16-core Power 770 with only one enclosure. There are 22 PCI-X adapters and 19 PCIe adapters spread across the current CECs and I/O drawers. How many and what kind of drawers are needed to connect these adapters?()

    • A、2 PCI-X drawers and 2 PCIe drawers
    • B、3 PCI-X drawers and 4 PCIe drawers
    • C、4 PCI-X drawers and 3 PCIe drawers
    • D、4 PCI-X drawers and 2 PCIe drawers

    正确答案:D

  • 第20题:

    单选题
    A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following questions is most important to ensure that the power in the datacenter environment is ready for the initial install?()
    A

    Have optional Fibre Channel and Ethernet switches been installed in the server?

    B

    What is the available kVA value of the UPS?

    C

    Are there sufficient empty socket outlets in the UPS?

    D

    What is the impact on the power consumption of the data center cooling system?


    正确答案: A
    解析: 暂无解析

  • 第21题:

    单选题
    A customer wants to run VMWare ESX on an x445 with a large number of virtual machines running Windows 2003 Server as a Disaster Recovery (DR) Site for the production environment.  Which of the following questions would most impact the memory configuration?()
    A

    What version of VMWare ESX Server is being considered?

    B

    Do the systems currently use Double Data Rate (DDR) memory?

    C

    What is the total number of processors installed in the production systems?

    D

    What is the total amount of memory currently being used across all the production systems?


    正确答案: C
    解析: 暂无解析