Have the PDU requirements been met?
Are there sufficient KVM connections?
Is there sufficient service clearance?
Is there sufficient space in the existing rack?
第1题:
A customer is ordering a new p650 server to be placed into an existing OEM 42U 19-inch rack containing only two p630 servers. This is the first p650 in the enterprise. What is the most important question that the pSeries technical specialist should ask the customer before the order is placed?()
第2题:
A customer wants to upgrade their existing 6-way p650 to an 8-way. The installed inventory shows the p650 as only a 4-way. What should the pSeries technical specialist do in order to best correct IBMinventory records? ()
第3题:
A customer with p615, p630 and p650 pSeries servers installed and running AIX is considering Linux as an additional environment. Which Linux capabilities can the pSeries Sales Specialist present as choices that are available to enhance the existing systems?()
第4题:
A space-constrained customer is currently running AIX 5.2 on a number of p650 servers and a pair of new p5-550 servers. They have four identical new applications each requiring a minimum of seven processors and 96GB of memory. Which solution would best meet the customer’s requirements?()
第5题:
Sales Manual
Announcement Letter
Site and Hardware Planning Information
Adapter, Devices, and Cable Information for Multiple Bus Systems
第6题:
Voltage
Frequency
Power Source Loading (max)
Power Source Loading (typical)
第7题:
Explain to the customer that they need an additional HMC for the POWER5 system.
Obtain a PO from the customer to purchase additional serial connections to the HMC.
Obtain a PO from the customer to purchase additional Ethernet connections to the HMC.
Explain to the customer that they need a firmware update on the HMC to support both POWER4 and POWER5.
第8题:
A DCE domain
A Kerberos domain
A PPP tunnel between the servers
An IPSEC tunnel between the servers
第9题:
Request that the pSeries technical specialist provide the discount percentage to the customer.
Run both eConfig and PCRS6000 to ensure that both configurators provide the same upgrade quote.
Confirm with the customer that the installed inventory accurately reflects what is actually installed.
Provide options to the customer so they can choose the most appropriate upgrade for their environment.
第10题:
Offer to rebuild the logical volume for a fee.
Offer to talk the customer through the procedure to rebuild the logical volume for a fee.
Suggest the customer open a call with IBM TechLine; offer to explain how the process works.
Suggest the customer open a call with IBM SupportLine; offer to explain how the process works.
第11题:
Have the PDU requirements been met?
Are there sufficient KVM connections?
Is there sufficient service clearance?
Is there sufficient space in the existing rack?
第12题:
Because additional systems would require more power receptacles
Because the customer may need to do additional facilities planning
Because the customer needs additional funding to cover the services
Because postponing the eventual discussion will likely lead to customer dissatisfaction
第13题:
A customer wants to upgrade an existing pSeries system. In addition to retrieving the IBM configuration records, what else should be done to ensure an accurate upgrade quote is provided?()
第14题:
A customer has two locations that host their pSeries servers. Traffic is being routed through the public Internet. The customer needs to exchange confidential financial data between the servers. Which of the following solutions should the pSeries technical specialist propose to the customer to secure the data?()
第15题:
A customer requires a deskside solution that they will rack-mount in the future. Space is at a premium. The solution must support two AIX 5.2 applications that require two processors each. Which of the following deskside configurations should the pSeries Technical Specialist recommend?()
第16题:
A company has recently placed an order for a POWER4+ p650 server. Their facilities manager has approached the pSeries technical specialist to gather information on the correct power receptacle for thenew server. They have requested a picture of the power cord plug to show to their electrician. Where would the pSeries technical specialist find the required information?()
第17题:
Sales Manual
Announcement Letter
POWER4+ p650 Specification Sheet
Site and Hardware Planning Information Manual
第18题:
Enable logon auditing in both the new and the existing domains
Enable logon auditing only in the existing domain
Enable logon auditing only in the new domain
Enable logon auditing on only the Web server
第19题:
Some Express Configurations limit the amount of maximum memory at order time.
The customer must meet minimum system requirements to obtain Express Configuration pricing.
The Express Configurations offer less than the maximum number of processors.
The Express Configurations are only offered through the QuickShip Program.
第20题:
Linux will be restricted to the p650 system, as it is not supported on the p630.
The customer can run Linux on all the existing systems with or without the presence of AIX.
Linux can run in LPARs on the existing systems but Linux will require the presence of AIX in at least one LPAR.
Linux can be installed on all existing systems but will require the AIX Linux Affinity libraries to boot the systems and run Linux.
第21题:
Higher rack density that reduces data center footprints
Internal upgrades that only IBM can offer
Total Cost of Ownership (TCO) related to innovative components such as Integrated Switches
The Rear Door Heat eXchanger that only IBM can offer
第22题:
Submit an RPO-MES to add the missing 2-way processor card.
Submit an MES order to add the missing 2-way processor card.
Request VPD from the customer and then submit an RPO-MES request.
Request VPD from the customer and then submit an MES order to add the missing 2-way processor card.
第23题:
One p5-550 4-way
Two 2-way p5-520s
One p630 4-way
Two 2-way p615s
第24题:
Obtain buy-in and feedback from the customer.
First ask the client executive if financing has been arranged.
Plan the installation and rollout schedule before ordering.
Confirm that any additional requirements are handled by others.