更多“单选题The SOW (Statement of Work) is another name for the:()A WBS (Work Breakdown Structure).B cost benefit analysis.C requirements specifications.D narrative description of the work to be accomplished.”相关问题
  • 第1题:

    The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

    A.Time, schedule and cost.

    B.Management coordination and organization structuring.

    C.Work methods and accountability.

    D.Quality of work.

    E.Risk and impact decision-making.


    正确答案:D
    D

  • 第2题:

    The most effective means of determining the cost of a project is to price out the _____.

    A . Work breakdown structure.

    B . Linear responsibility chart.

    C . Project charter.

    D . Scope statement.

    E . Management plan.


    正确答案:A

  • 第3题:

    198 The most effective means of determining the cost of a project is to price out the _____.

    A. Work breakdown structure.

    B. Linear responsibility chart.

    C. Project charter.

    D. Scope statement.

    E. Management plan


    正确答案:A

  • 第4题:

    63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

    A. task

    B. level of effort

    C. sub-task

    D. project

    E. work package


    正确答案:E

  • 第5题:

    ● A work breakdown structure is most useful for:

    A identifying individual tasks for a project

    B scheduling the start of tasks

    C developing a cost estimate

    D determining potential delays

    E A and C


    正确答案:E

  • 第6题:

    ● A clear definition of the user's needs serves as the direct basis for the:

    A Work breakdown structure.

    B Functional requirements.

    C Project cost estimate.

    D Selection of personnel.

    E Termination decision.


    正确答案:B

  • 第7题:

    ● A task-oriented family tree of activities is a:

    A Detailed plan.

    B Linear responsibility chart.

    C Work breakdown structure.

    D Cost account coding system.

    E Work package description.


    正确答案:C

  • 第8题:

    A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements list

    A.Essences

    B.Elements

    C.Purposes

    D. Issues


    正确答案:B
    本题目翻译:进度表是常用的项目规划和项目组合管理。按计划元素可能是密切相关的工作分解结构(WBS)的终端元素,工作的陈述,或合同数据要求清单。考察的是进度计划。

  • 第9题:

    The creation of a work breakdown structure (WBS) is the process of______the major project deliverables.

    A.subdividing

    B.assessing

    C.planning

    D.integrating


    正确答案:A
    解析:创建工作分解结构是分解项目可交付物的过程。选项A是分解,选项B是估算,选项C是计划,选项D是整合。

  • 第10题:

    A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.

    A.Essences
    B.Elements
    C.Purposes
    D.Issues

    答案:B
    解析:
    时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素,工作说明书,或合同数据需求清单密切相关。

  • 第11题:

    The SOW (Statement of Work) is another name for the:()

    • A、WBS (Work Breakdown Structure).
    • B、cost benefit analysis.
    • C、requirements specifications.
    • D、narrative description of the work to be accomplished.

    正确答案:D

  • 第12题:

    单选题
    The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.
    A

    subdividing

    B

    assessing

    C

    planning

    D

    integrating


    正确答案: B
    解析: 该题的关键词为"work breakdown structure、 major project deliverables",其语句结构为"The creation ofa work breakdown structure (WBS)(主语)is(谓语)the processof()the major project deliverables",含义为"创建WBS是怎样主要的项目交付物的过程"。根据WBS定义以及选项,容易识别出应选择分解(subdividing)

  • 第13题:

    A task-oriented family tree of activities is a:

    A.Detailed plan.

    B.Linear responsibility chart.

    C.Work breakdown structure.

    D.Cost account coding system.

    E.Work package description.


    正确答案:C
    C

  • 第14题:

    96 A task-oriented family tree of activities is a:

    A. Detailed plan.

    B. Linear responsibility chart.

    C. Work breakdown structure.

    D. Cost account coding system.

    E. Work package description.


    正确答案:C

  • 第15题:

    45 A clear definition of the user's needs serves as the direct basis for the:

    A. Work breakdown structure.

    B. Functional requirements.

    C. Project cost estimate.

    D. Selection of personnel.

    E. Termination decision.


    正确答案:B

  • 第16题:

    ● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

    A task

    B level of effort

    C sub-task

    D project

    E work package


    正确答案:E

  • 第17题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第18题:

    ● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

    A Time, schedule and cost.

    B Management coordination and organization structuring.

    C Work methods and accountability.

    D Quality of work.

    E Risk and impact decision-making.


    正确答案:D

  • 第19题:

    ● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .

    (72)

    A.identifying individual tasks for a project

    B.scheduling the start of tasks

    C.scheduling the end of tasks

    D.determining potential delays


    正确答案:A

  • 第20题:

    The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.

    A.Schedule and cost

    B.Organization structuring

    C.Management coordination

    D.Quality of work


    正确答案:D

  • 第21题:

    A schedule is commonly used in project planning and project portfolio management. ( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素( ),工作说明书,或合同数据需求清单密切相关。

    A.Essences精髓
    B.Elements元素
    C.Purposes目的
    D.Issues问题

    答案:B
    解析:

  • 第22题:

    The creation of a work breakdown structure(WBS)is the process of ( ) the major project deliverables.

    A.subdividing
    B.assessing
    C.planning
    D.integrating

    答案:A
    解析:
    创建工作分解结构是分解项目可交付物的过程。A.分解 B.估算 C.计划 D.整合

  • 第23题:

    Team member listing, scheduled tasks, and risk identification are part of the:()

    • A、project plan.
    • B、project charter.
    • C、communication plan.
    • D、WBS (Work Breakdown Structure).

    正确答案:A

  • 第24题:

    单选题
    The SOW (Statement of Work) is another name for the:()
    A

    WBS (Work Breakdown Structure).

    B

    cost benefit analysis.

    C

    requirements specifications.

    D

    narrative description of the work to be accomplished.


    正确答案: C
    解析: 暂无解析