第1题:
The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A.Time, schedule and cost.
B.Management coordination and organization structuring.
C.Work methods and accountability.
D.Quality of work.
E.Risk and impact decision-making.
第2题:
The most effective means of determining the cost of a project is to price out the _____.
A . Work breakdown structure.
B . Linear responsibility chart.
C . Project charter.
D . Scope statement.
E . Management plan.
第3题:
198 The most effective means of determining the cost of a project is to price out the _____.
A. Work breakdown structure.
B. Linear responsibility chart.
C. Project charter.
D. Scope statement.
E. Management plan
第4题:
63 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A. task
B. level of effort
C. sub-task
D. project
E. work package
第5题:
● A work breakdown structure is most useful for:
A identifying individual tasks for a project
B scheduling the start of tasks
C developing a cost estimate
D determining potential delays
E A and C
第6题:
● A clear definition of the user's needs serves as the direct basis for the:
A Work breakdown structure.
B Functional requirements.
C Project cost estimate.
D Selection of personnel.
E Termination decision.
第7题:
● A task-oriented family tree of activities is a:
A Detailed plan.
B Linear responsibility chart.
C Work breakdown structure.
D Cost account coding system.
E Work package description.
第8题:
A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements list
A.Essences
B.Elements
C.Purposes
D. Issues
第9题:
The creation of a work breakdown structure (WBS) is the process of______the major project deliverables.
A.subdividing
B.assessing
C.planning
D.integrating
第10题:
第11题:
The SOW (Statement of Work) is another name for the:()
第12题:
subdividing
assessing
planning
integrating
第13题:
A task-oriented family tree of activities is a:
A.Detailed plan.
B.Linear responsibility chart.
C.Work breakdown structure.
D.Cost account coding system.
E.Work package description.
第14题:
96 A task-oriented family tree of activities is a:
A. Detailed plan.
B. Linear responsibility chart.
C. Work breakdown structure.
D. Cost account coding system.
E. Work package description.
第15题:
45 A clear definition of the user's needs serves as the direct basis for the:
A. Work breakdown structure.
B. Functional requirements.
C. Project cost estimate.
D. Selection of personnel.
E. Termination decision.
第16题:
● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A task
B level of effort
C sub-task
D project
E work package
第17题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第18题:
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?
A Time, schedule and cost.
B Management coordination and organization structuring.
C Work methods and accountability.
D Quality of work.
E Risk and impact decision-making.
第19题:
● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .
(72)
A.identifying individual tasks for a project
B.scheduling the start of tasks
C.scheduling the end of tasks
D.determining potential delays
第20题:
The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.
A.Schedule and cost
B.Organization structuring
C.Management coordination
D.Quality of work
第21题:
第22题:
第23题:
Team member listing, scheduled tasks, and risk identification are part of the:()
第24题:
WBS (Work Breakdown Structure).
cost benefit analysis.
requirements specifications.
narrative description of the work to be accomplished.