单选题A customer has 4 POWER6 servers managed by a Hardware Management Console (HMC). They plan to install a second HMC for redundancy.  Which of the following statements correctlydescribes the dual HMC environment? ()ATo provide the Service Agent function, 

题目
单选题
A customer has 4 POWER6 servers managed by a Hardware Management Console (HMC). They plan to install a second HMC for redundancy.  Which of the following statements correctlydescribes the dual HMC environment? ()
A

 To provide the Service Agent function, both HMCs must have Service Agent enabled and a dedicated modem and phone line.

B

 Authorized users must have the same username and password on both HMCs, so that every user of one HMC is automatically authorized on the other.

C

 Both HMCs are automatically notified of any changes that occur in the managed systems, so results of changes made to the managed system by one HMC are visible on the

D

 Both HMCs must be running the same software revision. Software maintenance must be performed on both HMCs at the same time, but one HMC should be disconnected from


相似考题
参考答案和解析
正确答案: B
解析: 暂无解析
更多“单选题A customer has 4 POWER6 servers managed by a Hardware Management Console (HMC). They plan to install a second HMC for redundancy.  Which of the following statements correctlydescribes the dual HMC environment? ()A  To provide the Service Agent function”相关问题
  • 第1题:

    A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()

    • A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.
    • B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.
    • C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.
    • D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

    正确答案:D

  • 第2题:

    Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()

    • A、Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. 
    • B、The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. 
    • C、If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. 
    • D、The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 

    正确答案:B

  • 第3题:

    Which of the following interfaces is required to implement Workload Partition Mobility? ()

    • A、 Workload Partitions Manager for AIX
    • B、 Hardware Management Console (HMC) GUI
    • C、 Integrated Virtualization Manager (IVM)
    • D、 Advanced System Management Interface (ASMI)

    正确答案:A

  • 第4题:

    On which HMC GUI panel can the ’Enable Electronic Service Agent’ option be found?() 

    • A、HMC Management
    • B、Systems Management
    • C、Service Management
    • D、Electronic Management

    正确答案:C

  • 第5题:

    An administrator is applying a corrective service to their HMC. The corrective service has been shipped on 3 DVDs. Which action will ensure the corrective service is correctly installed?()

    • A、Select the option to automatically reboot the HMC
    • B、Select the option to automatically reboot the HMC after each disk
    • C、Shutdown all managed LPARs prior to beginning the install process
    • D、Copy all disks into the "SERVICE" directory and select concurrent install

    正确答案:A

  • 第6题:

    单选题
    Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()
    A

     The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).

    B

     The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).

    C

     Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).

    D

     Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).


    正确答案: D
    解析: 暂无解析

  • 第7题:

    单选题
    An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
    A

    An additional switch for the new HMC

    B

    Asynchronous adapters on the new HMC

    C

    The two 570 servers are directly connected to the new HMC

    D

    One 570 is directly connected to the new HMC and the other is directly connected to the existing HMC


    正确答案: B
    解析: 暂无解析

  • 第8题:

    单选题
    A new customer wants to install a Power 750 in a warehouse location that has no local staff to support it. They are concerned about hardware support and would like to have the system notify IBM service if there is an issue.Which actions will address the customer concern?()
    A

    Enable automatic problem reporting from smit

    B

    Use IVM to enable console mirroring to IBM Remote Support.

    C

    Use the HMC to enable reporting through Electronic Service Agent.

    D

    Enable Automatic Problem Reporting in ASMI using he embedded modem on the FSP.


    正确答案: A
    解析: 暂无解析

  • 第9题:

    单选题
    An administrator is applying a corrective service to their HMC. The corrective service has been shipped on 3 DVDs. Which action will ensure the corrective service is correctly installed?()
    A

    Select the option to automatically reboot the HMC

    B

    Select the option to automatically reboot the HMC after each disk

    C

    Shutdown all managed LPARs prior to beginning the install process

    D

    Copy all disks into the SERVICE directory and select concurrent install


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    Which of the following is a feature of Integrated Virtualization Manager (IVM)? ()
    A

     It has a GUI interface for upgrading system firmware. 

    B

     It creates and manages AIX/Linux and VIOS type LPARs. 

    C

     It can be managed by the Hardware Management Console (HMC). 

    D

     It supports Live Partition Mobility on POWER6 systems and above.


    正确答案: A
    解析: 暂无解析

  • 第11题:

    单选题
    A customer has a wide range of IBM enterprise disk systems and wants to manage copy services functions.  Which of the products should the storage specialist recommend to this customer()
    A

    DS Hardware Management Console (HMC), because it manages ESS 800, DS6000, DS8000, and SVC storage servers

    B

    Tivoli Storage Productivity Center for Data, because it manages ESS 800, DS6000, DS8000, and SVC storage servers

    C

    Tivoli Storage Productivity Center for Replication, because it manages ESS 800, DS6000, DS8000, and SVC storage servers

    D

    External DS Hardware Management Console (HMC), because it manages ESS 800, DS6000, DS8000, and SVC storage servers


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()
    A

     Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.

    B

     Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.

    C

     Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.

    D

     Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.


    正确答案: D
    解析: 暂无解析

  • 第13题:

    Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()

    • A、 The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).
    • B、 The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).
    • C、 Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).
    • D、 Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).

    正确答案:A

  • 第14题:

    A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()

    • A、All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or later
    • B、The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMC
    • C、They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based  systems connected to the existing one
    • D、The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM

    正确答案:A

  • 第15题:

    A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()

    • A、Purchase a second HMC and use this to manage the new servers.
    • B、Connect all of the new servers to the existing private HMC network.
    • C、Configure a second private network on their existing HMC for the new servers.
    • D、Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.

    正确答案:B

  • 第16题:

    Which of the following is a feature of Integrated Virtualization Manager (IVM)? ()

    • A、 It has a GUI interface for upgrading system firmware. 
    • B、 It creates and manages AIX/Linux and VIOS type LPARs. 
    • C、 It can be managed by the Hardware Management Console (HMC). 
    • D、 It supports Live Partition Mobility on POWER6 systems and above.

    正确答案:D

  • 第17题:

    An administrator is applying a corrective service to their HMC .The corrective service has been shipped on 3 DVDs. Which action will ensure the corrective service is correctly installed?()

    • A、Select the option to automatically reboot the HMC .
    • B、Select the option to automatically reboot the HMC after each disk.
    • C、Shutdown all managed LPARs prior to beginning the install process.
    • D、Copy all disks into the ""SERVICE"" directory and select concurrent install.

    正确答案:A

  • 第18题:

    单选题
    Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()
    A

    Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. 

    B

    The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. 

    C

    If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. 

    D

    The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()
    A

    Purchase a second HMC and use this to manage the new servers.

    B

    Connect all of the new servers to the existing private HMC network.

    C

    Configure a second private network on their existing HMC for the new servers.

    D

    Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.


    正确答案: B
    解析: 暂无解析

  • 第20题:

    单选题
    A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()
    A

    All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or later

    B

    The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMC

    C

    They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based  systems connected to the existing one

    D

    The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM


    正确答案: B
    解析: 暂无解析

  • 第21题:

    单选题
    ompany.com has recently received a new p5-570 in the data center and wants to connect it to an existing HMC environment where each of the existing POWER5 servers has been assigned a static IP address. Which of the following actions should the technical specialist perform to set the service processor network address for a static IP?()
    A

    Configure the IP address through the first client partition.

    B

    Configure the IP address through the ASMI menus.

    C

    Configure the POWER5 service processor for DHCP from the HMC DHCP server.

    D

    Configure the HMC to use the default IP address on the service processor when acquiring the managed server.


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    An administrator is applying a corrective service to their HMC .The corrective service has been shipped on 3 DVDs. Which action will ensure the corrective service is correctly installed?()
    A

    Select the option to automatically reboot the HMC .

    B

    Select the option to automatically reboot the HMC after each disk.

    C

    Shutdown all managed LPARs prior to beginning the install process.

    D

    Copy all disks into the SERVICE directory and select concurrent install.


    正确答案: D
    解析: 暂无解析

  • 第23题:

    单选题
    An administrator has an existing HMC and POWER6 570 connected to a network switch.  The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
    A

    An additional switch for the new HMc  

    B

    Asynchronous adapters on the new HMc

    C

    The two 570 servers are directly connected to the new HMc  

    D

    One 570 is directly connected to the new HMC and the other is directly connected to the existing HMc


    正确答案: C
    解析: 暂无解析