86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A. MatrixB. Pure projectC. Project coordinatorD. Project expediterE.

题目

86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?

A. Matrix

B. Pure project

C. Project coordinator

D. Project expediter

E. Classical/traditional


相似考题
更多“86Team members want to work for a project manager that can provide them with career path p ”相关问题
  • 第1题:

    下列P2P网络中,属于分布式结构的是( )

    Ⅰ.Pastry

    Ⅱ.Tapestry

    Ⅲ.Chord

    Ⅳ.eDonkey

    Ⅴ.CAN


    正确答案:C
    目前采用分布式结构化拓扑的P2P网络系统有Pashry、Tapestry、Chord和CAN。

  • 第2题:

    已知基类Employee只有一个构造函数,其定义如下: Employee::Employee(int n):id(n){ } Manager是Employee的派生类,则下列对Manager的构造函数的定义中,正确的是?

    A.Manager::Manager(int n):id(n){}

    B.Manager::Manager(int n){id=n;}

    C.Manager::Manager(int n):Employee(n){}

    D.Manager::Manager(int n){Employee(n);}


    Manger::manger(int n):Employee(n){}

  • 第3题:

    2、若有以下说明和语句,则引用方式不正确的是? struct worker{ int no; char *name; }work, *p=&work;

    A.work.no

    B.(*p).no

    C.p->no

    D.work->no


    work->no

  • 第4题:

    In?project?net work?diagram,the?number?of?critical?path?is()。

    A.none
    B.only?one
    C.only?two
    D.one?or?more

    答案:D
    解析:
    本题翻译:在项目网络工作图中,关键路径的数目是()。
    A.没有B.只有一个C.只有两个D.一个或更多
    本题考查的是进度管理中的关键路径,正确选项为D一个或更多。
    在一个网络图中关键路径有一条或多条,关键路径是项目中时间最长的活动顺序,决定着可能的项目最短工期。

  • 第5题:

    若有以下说明和语句,则以下引用方式中不正确的是()。 struct worker { int no; char *name; }work, *p=&work;

    A.work.no

    B.(*p).no

    C.p->no

    D.work->no


    D解析:?的优先级远高于'&'和'*'。

  • 第6题:

    若有以下说明和语句,则引用方式不正确的是? struct worker{ int no; char *name; }work, *p=&work;

    A.work.no

    B.(*p).no

    C.p->no

    D.work->no


    D