  • 第1题:

    A clear definition of the user's needs serves as the direct basis for the:

    A.Work breakdown structure.

    B.Functional requirements.

    C.Project cost estimate.

    D.Selection of personnel.

    E.Termination decision.


    正确答案:B
    B

  • 第2题:

    A task-oriented family tree of activities is a:

    A.Detailed plan.

    B.Linear responsibility chart.

    C.Work breakdown structure.

    D.Cost account coding system.

    E.Work package description.


    正确答案:C
    C

  • 第3题:

    51 Going from Level 2 to Level 4 in the work breakdown structure will result in

    A. Less estimating accuracy

    B. Better control of the project

    C. Lower status reporting costs

    D. A greater likelihood that something will fall through the cracks

    E. None of the above


    正确答案:E

  • 第4题:

    对一个风险事件的临时应对措施叫做:( )

    A.工作项(work item)

    B.工作包(work package)

    C.权变措施(workaround)

    D.工作分解结构(work breakdown structure)


    正确答案:C
    权变措施(workaround)是指为了应对那些事先没有识别出的或者是已经接受的风险而采取的临时应对措施。

  • 第5题:

    ● A Work Breakdown Structure:

    A assures all work is identified

    B subdivides the project into manageable segments

    C provides the project sponsor with a time-phase task summary

    D both A and B

    E All of the above.


    正确答案:D

  • 第6题:

    ● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

    A Time, schedule and cost.

    B Management coordination and organization structuring.

    C Work methods and accountability.

    D Quality of work.

    E Risk and impact decision-making.


    正确答案:D

  • 第7题:

    ● A task-oriented family tree of activities is a:

    A Detailed plan.

    B Linear responsibility chart.

    C Work breakdown structure.

    D Cost account coding system.

    E Work package description.


    正确答案:C

  • 第8题:

    ● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .

    (72)

    A.identifying individual tasks for a project

    B.scheduling the start of tasks

    C.scheduling the end of tasks

    D.determining potential delays


    正确答案:A

  • 第9题:

    A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements list

    A.Essences

    B.Elements

    C.Purposes

    D. Issues


    正确答案:B
    本题目翻译:进度表是常用的项目规划和项目组合管理。按计划元素可能是密切相关的工作分解结构(WBS)的终端元素,工作的陈述,或合同数据要求清单。考察的是进度计划。

  • 第10题:

    The creation of a work breakdown structure (WBS) is the process of______the major project deliverables.

    A.subdividing

    B.assessing

    C.planning

    D.integrating


    正确答案:A
    解析:创建工作分解结构是分解项目可交付物的过程。选项A是分解,选项B是估算,选项C是计划,选项D是整合。

  • 第11题:

    The work breakdown structure comprises several levels of decomposition of the total project.The lowest level of definition is always the ( ) .

    A.planning
    B.element
    C.subtask
    D.working interface

    答案:B
    解析:

  • 第12题:

    The SOW (Statement of Work) is another name for the:()

    • A、WBS (Work Breakdown Structure).
    • B、cost benefit analysis.
    • C、requirements specifications.
    • D、narrative description of the work to be accomplished.

    正确答案:D

  • 第13题:

    The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

    A.Time, schedule and cost.

    B.Management coordination and organization structuring.

    C.Work methods and accountability.

    D.Quality of work.

    E.Risk and impact decision-making.


    正确答案:D
    D

  • 第14题:

    106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

    A. Work packages.

    B. Subtasks.

    C. Tasks.

    D. Code of accounts.

    E. Integration points


    正确答案:C

  • 第15题:

    ● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

    A task

    B level of effort

    C sub-task

    D project

    E work package


    正确答案:E

  • 第16题:

    ● Going from Level 2 to Level 4 in the work breakdown structure will result in

    A Less estimating accuracy

    B Better control of the project

    C Lower status reporting costs

    D A greater likelihood that something will fall through the cracks

    E None of the above


    正确答案:E

  • 第17题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第18题:

    ● The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

    A Work packages.

    B Subtasks.

    C Tasks.

    D Code of accounts.

    E Integration points.


    正确答案:C

  • 第19题:

    Perform. Quality Control is the process of monitoring and recording resuks of executing the Quality Plan activities to assess performance and recommend necessary changes.( )are the techniques and tools in performing quality control. ①Activity network diagram②Cause and effect diagrams③Inspection④Flow chart⑤Work Breakdown Structure⑥Pareto chart A.①③⑤ B.②④⑤⑥ C.②③④⑤⑥ D.①②③④⑥


    正确答案:D
    执行质量控制是一个监督、评价项目质量计划活动执行结果和提出变更请求的过程。执行质量控制的技术和工具包括:活动网络图(Activity network diagram)、因果图(Cause and effect diagrams)、检查(Inspection)、流程图(Flow chart)和帕累托图(Pareto chart)等,但不包括工作分解结构(Work Breakdown Structure)。

  • 第20题:

    ● The work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the (75) .

    (75)

    A. planning element

    B.work package

    C.subtask

    D. working interface


    正确答案:B

  • 第21题:

    The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.

    A.Schedule and cost

    B.Organization structuring

    C.Management coordination

    D.Quality of work


    正确答案:D

  • 第22题:

    he work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the()

    A.Planning element
    B.Work package
    C.Subtask
    D.Working interface

    答案:B
    解析:
    工作分解结构包括完整项目的几个层次的分解,在工作分解结构中定义的最低级别总是(75)。A.计划元素B.工作包C.子任务D.工作接口

  • 第23题:

    A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.

    A.Essences
    B.Elements
    C.Purposes
    D.Issues

    答案:B
    解析:
    时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素,工作说明书,或合同数据需求清单密切相关。