更多“Quality control is normally performed by the _____ .A . QA personnelB . project teamC . operating personnelD . project managementE . None of the above.”相关问题
  • 第1题:

    In project-driven companies, costs are usually billed againest the project based upon:

    A . The burdened labor rate of the actual employees who performed the work.

    B . The burdened labor rate of the line organization average salary.

    C . The burdened labor rate of the company average salary.

    D . The burdened labor rate of the average salary of the project team members.

    E . None of the above.


    正确答案:A

  • 第2题:

    Inspection of a complex project according to specifications is accomplished by _____.

    A . inspection by attributes.

    B . cyclical inspection

    C . quality conformance inspection

    D . original inspection

    E . None of the above.


    正确答案:C

  • 第3题:

    In the project environment, the individual ultimately responsible for quality control is:

    A . The line workers who must strive "to do things right the first time" to avoid quality problems.

    B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.

    C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.

    D . The project manager who has ultimate responsibility for the entire project.

    E . the customer who must ensure that he is receiving a quality product from the vendor.


    正确答案:D

  • 第4题:

    By which means is a contractor able to control cost overruns due to changing requirements?

    A Project data review

    B Change order

    C Purchase order amendment

    D Change control

    E None of the above.


    正确答案:D

  • 第5题:

    9 The best way to insure quality conformance is to _____.

    A. distribute the responsibility to subordinates.

    B maintain total control.

    C. train each worker to implement the work.

    D. inspect quality into the project.

    E. None of the above


    正确答案:C

  • 第6题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    A.Project

    B.project management team

    C.performingorganization

    D.customer


    参考答案:C

    该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • 第7题:

    ● Scope Management:

    A entails managing the project's work content.

    B is a subset of configuration management and as such is performed by CM specialists.

    C is concerned with naming all activities performed, the end products which results and the resources consumed.

    D is not a concern of the project manager.

    E None of the above.


    正确答案:C

  • 第8题:

    ● Proper implementation of project management will guarantee that:

    A Budgets will be met.

    B Schedules will be adhered to.

    C Quality/performance will be met.

    D The project will be a success.

    E None of the above.


    正确答案:E

  • 第9题:

    ______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

    A.euality assurance(QA)

    B.Quality planning

    C.Quality control(QC)

    D.Quality costs


    正确答案:A
    解析:质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。
      质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
      质量成本是指为满足质量要求所付出的主要成本。
      质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。因此应选择A。

  • 第10题:

    Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

    A.performing organization

    B.project management team

    C.project

    D.customer


    正确答案:A

  • 第11题:

    ( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

    A.Quality assurance(QA)
    B.Quality planning
    C.Quality control(QC)
    D.Quality costs

    答案:A
    解析:
    质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。
    质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
    质量成本是指为满足质量要求所付出的主要成本。
    质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。因此应选择A。

  • 第12题:

    Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

    • A、Project
    • B、project management team
    • C、performingorganization
    • D、customer

    正确答案:C

  • 第13题:

    It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?

    A . Direct labor dollars

    B . Direct labor hours.

    C . Overhead rates.

    D . Procurement costs.

    E . None of the above.


    正确答案:B

  • 第14题:

    The best way to insure quality conformance is to _____.

    A . distribute the responsibility to subordinates.

    B . maintain total control.

    C . train each worker to implement the work.

    D . inspect quality into the project.

    E . None of the above.


    正确答案:C

  • 第15题:

    ● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

    (71)

    A. project

    B. project management team

    C. performing organization

    D. customer


    正确答案:C

  • 第16题:

    41 In the project environment, the individual ultimately responsible for quality control is:

    A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

    C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

    D. The project manager who has ultimate responsibility for the entire project.

    E.the customer who must ensure that he is receiving a quality product from the vendor


    正确答案:D

  • 第17题:

    47 Quality control is normally performed by the _____ .

    A. QA personnel

    B. project team

    C. operating personnel

    D. project management

    E. None of the above


    正确答案:C

  • 第18题:

    ● The project charter is developed by:

    A senior management

    B the customer

    C the project manager

    D both A and C

    E None of the above.


    正确答案:D

  • 第19题:

    ● Scope management is:

    A a project control function.

    B employs change control.

    C a work authorization process.

    D considers Cost, Quality and Schedule.

    E All of the above.


    正确答案:E

  • 第20题:

    ● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

    (73)

    A. Quality assurance (QA)

    B. Quality planning

    C. Quality control (QC)

    D. Quality costs


    正确答案:A

  • 第21题:

    ● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs


    正确答案:A
    质量保证是一项有计划的、系统的质量活动,以确保项目的所有过程达到并符合要求。

  • 第22题:

    The intention of the__(75)__is to schedule,organize and control all activities to achieve the project goal eventually.No matter how difficult it is and what kind of risks are ther

    A.

    B.project work breakdown

    C.project security authentication

    D.project management

    E.project flowchart


    正确答案:C
    项目管理的目的就是计划、组织以及控制所有活动,以求实现项目的最终目标。无论这过程中会遇到任何困难与风险。

  • 第23题:

    ()is the application of planned,systematic quality activities to ensure thatthe project will employ all processes needed to meet requirements.

    A.Quality assurance(QA)
    B.Quality planning
    C.Quality control(QC)
    D.Quality costs

    答案:A
    解析:
    质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。质量成本是指为满足质量要求所付出的主要成本。质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项 A 是质量保证(QA),选项B 是质量计划,选项 C 是质量控制(QC),选项 D 是质量成本。因此应选择 A。