  • 第1题:

    A task-oriented family tree of activities is a:

    A.Detailed plan.

    B.Linear responsibility chart.

    C.Work breakdown structure.

    D.Cost account coding system.

    E.Work package description.


    正确答案:C
    C

  • 第2题:

    The most effective means of determining the cost of a project is to price out the _____.

    A . Work breakdown structure.

    B . Linear responsibility chart.

    C . Project charter.

    D . Scope statement.

    E . Management plan.


    正确答案:A

  • 第3题:

    146 The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

    A. Time, schedule and cost.

    B. Management coordination and organization structuring.

    C. Work methods and accountability.

    D. Quality of work.

    E. Risk and impact decision-making


    正确答案:D

  • 第4题:

    29 The WBS is:

    A. An organization oriented family tree of the project.

    B. A task oriented family tree of the project.

    C. A cost centered structure of the project.

    D. Only required on large complex projects where separately identifiable work packages are difficult to construct.

    E. None of the above


    正确答案:B

  • 第5题:

    178 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:

    A. Work breakdown structure

    B. milestone review and schedule technique

    C. cost/schedule control system

    D. planning programming budget system

    E. program and evaluation review technique


    正确答案:A

  • 第6题:

    61 The document authorizing functional areas to charge against the project is the:

    A. Work authorization form.

    B. Scope baseline

    C. Project charter

    D. Management plan

    E. Linear responsibility chart


    正确答案:A

  • 第7题:

    107 A work breakdown structure is most useful for:

    A. identifying individual tasks for a project

    B. scheduling the start of tasks

    C. developing a cost estimate

    D. determining potential delays

    E. A and C


    正确答案:E

  • 第8题:

    对一个风险事件的临时应对措施叫做:( )

    A.工作项(work item)

    B.工作包(work package)

    C.权变措施(workaround)

    D.工作分解结构(work breakdown structure)


    正确答案:C
    权变措施(workaround)是指为了应对那些事先没有识别出的或者是已经接受的风险而采取的临时应对措施。

  • 第9题:

    ● A work breakdown structure is most useful for:

    A identifying individual tasks for a project

    B scheduling the start of tasks

    C developing a cost estimate

    D determining potential delays

    E A and C


    正确答案:E

  • 第10题:

    A An organization oriented family tree of the project.

    B A task oriented family tree of the project.

    C A cost centered structure of the project.

    D Only required on large complex projects where separately identifiable work packages are difficult to construct.

    E None of the above.


    正确答案:B

  • 第11题:

    Define Activities is the process of identifying the specific actions to be performed to produce the ( ) .

    A.project elements
    B.work drafts
    C.work package
    D.project deliverables

    答案:D
    解析:

  • 第12题:

    单选题
    The SOW (Statement of Work) is another name for the:()
    A

    WBS (Work Breakdown Structure).

    B

    cost benefit analysis.

    C

    requirements specifications.

    D

    narrative description of the work to be accomplished.


    正确答案: C
    解析: 暂无解析

  • 第13题:

    The Cost Performance Index is computed as:

    A . budget cost of work performed divided by actual cost of work performed

    B . budget cost of work performed minus actual cost of work performed

    C . budget cost of work performed minus budget cost of work scheduled

    D . budget cost of work scheduled divided by budget cost of work performed

    E . actual cost of work scheduled divided by budget cost of work performed


    正确答案:A

  • 第14题:

    96 A task-oriented family tree of activities is a:

    A. Detailed plan.

    B. Linear responsibility chart.

    C. Work breakdown structure.

    D. Cost account coding system.

    E. Work package description.


    正确答案:C

  • 第15题:

    198 The most effective means of determining the cost of a project is to price out the _____.

    A. Work breakdown structure.

    B. Linear responsibility chart.

    C. Project charter.

    D. Scope statement.

    E. Management plan


    正确答案:A

  • 第16题:

    120 The Work Breakdown Structure (WBS) is the basis for communicating:

    A. Project scope, cost control, schedule, quality

    B. Project objectives, dependencies, plan, cost control

    C. Project scope, schedule, staffing, cost control

    D. Project scope, quality, schedule, dependencies

    E. Project budget, schedule, risk factors, work assignments


    正确答案:A

  • 第17题:

    25 A work breakdown structure is most useful for:

    A. identifying individual tasks for a project

    B scheduling the start of tasks

    C. developing a cost estimate

    D. determining potential delays

    E. A and C


    正确答案:E

  • 第18题:

    114 The Cost Performance Index is computed as:

    A. budget cost of work performed divided by actual cost of work performed

    B. budget cost of work performed minus actual cost of work performed

    C. budget cost of work performed minus budget cost of work scheduled

    D. budget cost of work scheduled divided by budget cost of work performed

    E. actual cost of work scheduled divided by budget cost of work performed


    正确答案:A

  • 第19题:

    ● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

    A task

    B level of effort

    C sub-task

    D project

    E work package


    正确答案:E

  • 第20题:

    ● The document authorizing functional areas to charge against the project is the:

    A Work authorization form

    B Scope baseline

    C Project charter

    D Management plan

    E Linear responsibility chart


    正确答案:A

  • 第21题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第22题:

    ● A task-oriented family tree of activities is a:

    A Detailed plan.

    B Linear responsibility chart.

    C Work breakdown structure.

    D Cost account coding system.

    E Work package description.


    正确答案:C

  • 第23题:

    The SOW (Statement of Work) is another name for the:()

    • A、WBS (Work Breakdown Structure).
    • B、cost benefit analysis.
    • C、requirements specifications.
    • D、narrative description of the work to be accomplished.

    正确答案:D