参考答案和解析
正确答案:D
更多“● Which of the following are included as part of a scope statement?A Project justificationB Project deliverablesC Project objectivesD All of the aboveE B and C”相关问题
  • 第1题:

    118 A common way by which executives provide the project manager with written authority is through:

    A. A common job description for all project managers

    B. An appointment letter

    C. A project charter

    D. All of the above

    E. B and C only


    正确答案:E

  • 第2题:

    146 Which of the following are included as part of a scope statement?

    A. Project justification

    B. Project deliverables

    C. Project objectives

    D. All of the above

    E. B and C


    正确答案:D

  • 第3题:

    ● The use of the project reports:

    A are not necessary on small projects

    B provides a means whereby various levels of authority can judge project performance

    C provides insight into project areas and the effectiveness of the control systems

    D All of the above

    E B and C


    正确答案:E

  • 第4题:

    ● (74) is primarily concerned with defining and controlling what is and is not included in the project.

    (74)

    A. Project Time Management

    B. Project Cost Management

    C. Project Scope management

    D. Project Communications Management


    正确答案:C

  • 第5题:

    ( ) describes, in detail, the project’ s deliverables and the work required to create those deliverables.

    A.Product scope description B.Project objectives C.Product specification D.The project scope statement


    正确答案:D

  • 第6题:

    The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter


    正确答案:B
    制定项目管理计划过程定义、准备、集成和协调所有的分计划,以形成项目管理计划 。

  • 第7题:

    ● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)

    (74)

    A. Scope Planning

    B. Scope Verification

    C. Scope Change Control

    D. Scope Definition


    正确答案:D

  • 第8题:

    The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

    A.project charter

    B.project scope goal

    C.project budget

    D.project scope statement


    正确答案:C

  • 第9题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A:Create scopE
    B:Project stakeholder management
    C:Project scope management
    D:Project cost management

    答案:C
    解析:

  • 第10题:

    ( ) describes,in detail,the project’s deliverables and the work required to create those deliverables.

    A.Product scope description
    B.Project objectives
    C.Stakeholder Analysis
    D.The project scope statement

    答案:D
    解析:
    项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。(72) A.产品范围说明书 B.项目目标 C.干系人分析 D.项目范围说明说

  • 第11题:

    ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

    A. Create scopE
    B. Project stakeholder management
    C. Project scope management
    D. Project cost management

    答案:C
    解析:

  • 第12题:

    ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

    • A、Product scope description
    • B、Project objectives
    • C、Stakeholder Analysis
    • D、The project scope statement

    正确答案:D

  • 第13题:

    88 The scope statement provides

    A. A basis for future decisions about a project.

    B. A baseline to accomplish verification measures.

    C. A baseline to evaluate potential scope changes.

    D. All of the above

    E. B and C only


    正确答案:D

  • 第14题:

    151 Sources for data on activity durations and resource requirements can be gathered from which of the following:

    A. Past project records (historical data)

    B. Commercial techniques (standard practices, rules of thumb)

    C. Past project team members knowledge (experience, oldtimers)

    D. All of the above

    E. A and C only


    正确答案:D

  • 第15题:

    ● Sources for data on activity durations and resource requirements can be gathered from which of the following:

    A Past project records (historical data)

    B Commercial techniques (standard practices, rules of thumb)

    C Past project team members knowledge (experience, oldtimers)

    D All of the above

    E A and C only


    正确答案:D

  • 第16题:

    ●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.

    (74) A. Product scope description

    B. Project objectives

    C. Product specification

    D. The project scope statement


    正确答案:D

  • 第17题:

    ______describes,in detail,the project's deliverables and the work required to create those deliverables.

    A.Product scope description

    B.Project objectives

    C.Stakeholder Analysis

    D.The project scope statement


    正确答案:D
    解析:项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。
    选项A是产品范围说明书,选项B是项目目标,选项C是干系人分析,选项D是项目范围说明书。故D是正确的。

  • 第18题:

    ● ()is primarily concerned with defining and concerning what is and is not included in the project.()A. Project Time ManagementB. Project Cost ManagementC. Project Scope ManagementD. Project Communications Management


    正确答案:C
    项目范围管理定义并关心哪些工作是项目应该做的哪些不是项目应该做的。

  • 第19题:

    The (75) describes,in detail,the project's deliverables and the work required to create those deliverables.

    A.product specification

    B.project requirement

    C.project charter

    D.project scope statement


    正确答案:D

  • 第20题:

    ()describees,indetail,the project's deliverables and the work required to create those deliverables.


    A.Product scope description
    B.Project objectives
    C.Produce specification
    D.The project scope statement


    答案:D
    解析:
    项目范围说明书详细描述了项目的可交付物和提供这些可交付物必须要做的工作。

  • 第21题:

    is primarily concerned with defining and controlling what is and is not included in the project.

    A.Project Time Management
    B.Project Cost Management
    C.Project Scope Management
    D.Project Communications Management

    答案:C
    解析:
    项目范围管理是项目管理(包括时间、成本、沟通)的基础。
    项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。
    选项A是项目时间管理,选项B是项目成本管理,选项C是项目范围管理,选项D是项目沟通管理。因此应选择C。

  • 第22题:

    The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope.

    A.project charter
    B.project scope goal
    C.project budget
    D.project scope statement

    答案:D
    解析:
    翻译:范围管理计划是团队如何准备项目范围说明文件,包括描述创建WBS,核实项目的可交付成果的完成,并为项目范围变更控制的要求。A.项目章程 B.项目范围目标C.项目预算 D.范围说明书

  • 第23题:

    ( ) is primarily concerned with defining and controlling what is and is not included in the project.

    A.Project Time Management
    B.Project Cost Management
    C.Project Scope Management
    D.Project Communications Management

    答案:C
    解析:
    项目范围管理是项目管理(包括时间、成本、沟通)的基础。

    项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。

    选项A是项目时间管理,选项B是项目成本管理,选项C是项目范围管理,选项D是项目沟通管理。因此应选择C。